FA5682-15-R-0002-0001.pdf

PDF 30 KB Posted

Attached to
ASHE 09-1031 RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB
Solicitation number
FA5682-15-R-0002
Issued by

About this file

AMENDMENT FA5682-15-R-0002-0001

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F1F3A24329A001 ASHE 09-1031

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See page 2 for narrative

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Feb-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA5682-15-R-0002

X 9B. DATED (SEE ITEM 11)

04-Feb-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Feb-2015

CODE

31 CONS LGC - FA5682

VIA PORDENONE 89/B, AREA "E" EDIF. 600

BASE AEREA DI AVIANO

AVIANO (PN) 33081

FA5682 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA5682-15-R-0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

MODIFICATION NARRATIVE

The purpose of this amendment is to:

-incorporate Addendum#2 to the solicitation Technical Specifications, -add clause 52.236-1 Perforrmance of Work by the Contractor (APR 1984) and -change the site visit date indicated in provision 52.236-27 as indicated in the Summary of Changes here below

SUMMARY OF CHANGES

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0002

The CLIN extended description has changed from THE CONTRACTOR SHALL

FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION,

SUPERVISION AND ANY OTHER NECESSARY WORK TO ACCOMPLISH THE

PROJECT HEREIN LISTED AT THE PRICE STATED BELOW AND STRICTLY IN

ACCORDANCE WITH THE TERMS AND CONDITIONS OF THIS CONTRACT

INCLUDING THE FOLLOWING ATTACHED DOCUMENTS LISTED IN SECTION J

HEREIN: PROJECT ASHE 09-1031 RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO

AIR BASE, AVIANO, ITALY - TECHNICAL SPECIFICATIONS REVISION 1 - SECTION

B. SUSTAIN WORKS to THE CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION, SUPERVISION AND ANY OTHER

NECESSARY WORK TO ACCOMPLISH THE PROJECT HEREIN LISTED AT THE PRICE

STATED BELOW AND STRICTLY IN ACCORDANCE WITH THE TERMS AND

CONDITIONS OF THIS CONTRACT INCLUDING THE FOLLOWING ATTACHED

DOCUMENTS LISTED IN SECTION J HEREIN: PROJECT ASHE 09-1031 RESTORE

HANGAR 1 BLDG 921, AREA F, AVIANO AIR BASE, AVIANO, ITALY - TECHNICAL

SPECIFICATIONS REVISION 1 - SECTION B. SUSTAIN WORKS & ADDENDUM#2.

SECTION I - CONTRACT CLAUSES

The following have been added by full text:

52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least twenty five (25) percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

(End of clause)

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

LIST OF ATTACHMENTS – CONSTRUCTION CONTRACTS

The following documents are attachments to this document and are an integral part thereof:

a. Attachment 1

PROJECT ASHE 09-1031 RESTORE HANGAR 1 BLDG. 921, AREA F, AVIANO AIR BASE,

AVIANO, ITALY – TECHNICAL SPECIFICATIONS REVISION 1 dated November 2014

- 195 pages including cover page, ADDENDUM#1 and ADDENDUM #2

b. Attachment 2

PROJECT ASHE 09-1031 RESTORE HANGAR 1 BLDG. 921, AREA F, AVIANO AIR BASE,

AVIANO, ITALY – DRAWINGS dated November 2014

- 71 sheets

c. Attachment 3

Master Technical Specifications for Construction Projects Aviano Air Base, Aviano, Italy dated November

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been modified:

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- 19 FEBRUARY 2015 at 0900 HRS

(c) Participants will meet at-- Parking Area of Gate 8 (LVIS Gate – Contractors entry gate) Area F – Flightline

Aviano Air Base, Aviano (PN) Italy

(End of provision)

(End of Summary of Changes)