U.S. AIR FORCE

ST

FIGHTER WING

AVIANO AIR BASE, ITALY

Prepared and Submitted by:

Via di Sacco Pastore n. 4 - Rome, Italy Tel. +39.06.97848041 fax +39.06.97848175

E-mail: design@soinci.it

SO.IN.CI. S.r.l.

Architecture, Engineering & Consulting Services

PROJECT ASHE 09-1031

RESTORE HANGAR 1 BLDG. 921, AREA “F”,

AVIANO AIR BASE, AVIANO, ITALY

CONSTRUCTION COST ESTIMATE

FINAL SUBMITTAL (100%)

Date: November 2014

A/E CONTRACT No.: FA5682-13-D-0004 D.O.: 0004

FOR OFFICIAL USE ONLY

CONSTRUCTION COST ESTIMATE BREAKDOWN

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

A.

PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni

Ia Architectural - Ia Architettura

NOT APPLICABLE/ Non applicabile

Ib Structural Work - Ib Lavori Strutturali

SURVEYED WALL DEMOLITION FOR HVAC PASSAGEWAY

Demolizione controllata di muratura par passaggi HVAC

IT. No.

Art. n.

1 LS/AC

ROOF SLAB SLOT OPENINGS FOR HVAC PASSAGEWAY

Apertura asole in solaio copertura passaggi HVAC

IT. No.

Art. n.

2 LS/AC

Total structural - Totale Strutturali

Ic Civil Work - Ic Lavori Civili

NOT APPLICABLE/ Non applicabile

Id Mechanical - Id Meccanico

REMOVAL OF EXISTING AHUs W/ DUCTWORK, PIPES, VALVES, AIR GRILLES AND INSTALLED FITTINGS

Rimozione delle esistenti unità di trattamento aria comprei i canali, tubi, valvole, griglie ed accessori presenti

IT. No.

Art. n.

3 LS/AC

REMOVAL OF PUMPS, VALVE, PIPING AND FITTINGS INSIDE

MECH ROOM 14

Rimozione di elettropompe, valvole, tubazioni ed accessori nel locale meccanico 14

IT. No.

Art. n.

4 LS/AC

REMOVAL OF MONOSPLIT SYSTEM W/ PIPE, WIRING,

CONTROL PANEL

Rimozione di monosplit comprese le tubazioni, linee elettriche, pannello di controllo

IT. No.

Art. n.

5 EA/NO

REPAIR WORKS / Lavori di Ristrutturazione

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 1 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

REMOVAL OF DUALSPLIT SYSTEM W/ PIPE, WIRING,

CONTROL PANEL

Rimozione di dual split comprese le tubazioni, linee elettriche, pannello di controllo

IT. No.

Art. n.

6 EA/NO

REMOVAL OF FANCOIL WALL MOUNTED W/ FITTINGS

Rimozione di ventilconvettore a parete con accessori

IT. No.

Art. n.

7 EA/NO

REMOVAL OF ROOF EXHAUST FAN

Rimozione di ventilatore di estrazione

IT. No.

Art. n.

8 EA/NO

REMOVAL OF LITTLE CHILLER ON THE ROOF

Rimozione di piccolo chiller sulla copertura

IT. No.

Art. n.

9 EA/NO

REMOVAL OF PIPE W/ VALVES, INSULATION, BRACKETS AND

FITTINGS

Rimozione di tubazioni incluse le valvole, la coibentazione, gli staffaggi e gli accessori

IT. No.

Art. n.

10 LS/AC

Total Mechanical - Totale Meccanico

Ie Electrical - Ie Elettrico

REMOVE ELECTRICAL SYSTEM FEEDING A/C EQUIPMENT

Rimozione dell'impianto elettrico alimentante le apparecchiature di

Condizionamento

IT. No.

Art. n.

11 LS / AC

Total Electrical - Totale Elettrico

TOTAL PART I - Totale Parte I

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 2 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili

IIa Architectural - IIa Architettonico

LIGHT CONCRETE PADS AND SUPPORT BLOCKS FOR HVAC

UNITS

Basamenti e Baggioli per Unità Hvac

IT. No.

Art. n.

1 LS/AC

Total Architectural - Totale Architettura

IIb Structural Work - IIb Lavori Strutturali

NOT APPLICABLE/ Non applicabile

IIc Civil Work - IIc Lavori Civili

NOT APPLICABLE/ Non applicabile

TOTAL PART II / Totale Parte II

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 3 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

PART III - MECHANICAL WORK / Parte III - Lavori Meccanici

IIIa - HVAC System / IIIa - Impianto di Condizionamento

REVERSIBLE HEAT PUMP RHP-1 W/ LOW TEMP KIT, PUMP

KIT, PARTIAL HEAT RECOVERY AND FITTINGS

Pompa di calore reversione RHP-1 con kit bassa tempertura, modulo idronico, recupero di calore parziale ed accessori

IT. No.

Art. n.

1 EA/NO

VERTICAL SINGLE STAGE TWIN CENTRIFUGAL PUMP,

VARIABE SPEED W/ PRESSURE SENSOR & FITTINGS - CP1

Pompa gemellare centrifuga a singolo stadio, velocità variabile con sensore di pressione ed accessori - CP1

IT. No.

Art. n.

2a EA/NO

VERTICAL SINGLE STAGE TWIN CENTRIFUGAL PUMP,

VARIABE SPEED W/ PRESSURE SENSOR & FITTINGS - CP2

Pompa gemellare centrifuga a singolo stadio, velocità variabile con sensore di pressione ed accessori - CP2

IT. No.

Art. n.

2b EA/NO

VERTICAL SINGLE STAGE TWIN CENTRIFUGAL PUMP,

VARIABE SPEED W/ PRESSURE SENSOR & FITTINGS - CP4

Pompa gemellare centrifuga a singolo stadio, velocità variabile con sensore di pressione ed accessori - CP4

IT. No.

Art. n.

2c EA/NO

HIGH EFFICIENCIES CIRCULATOR - TWIN TYPE - CP3

Circolatore ad alta efficienza - Gemellare - CP3

IT. No.

Art. n.

3a EA/NO

HIGH EFFICIENCIES CIRCULATOR - SINGLE TYPE - CP4

Circolatore ad alta efficienza - singolo - CP4

IT. No.

Art. n.

3b EA/NO

HIGH EFFICIENCIES CIRCULATOR - SINGLE TYPE - CP6

Circolatore ad alta efficienza - singolo - CP6

IT. No.

Art. n.

4a EA/NO

INERTIAL TANK - IT-1

Serbatoio inerziale - IT-1

IT. No.

Art. n.

5 EA/NO

EXPANSION TANK - ET-1

Vaso di espansione - ET-1

IT. No.

Art. n.

6a EA/NO

EXPANSION TANK - ET-2

Vaso di espansione - ET-2

IT. No.

Art. n.

6b EA/NO

EXPANSION TANK - ET-3

Vaso di espansione - ET-3

IT. No.

Art. n.

6c EA/NO

2-WAY VALVE WITH ON/OFF MOTOR - DN100

Valvola a 2 vie con motorizzazione on/off - DN100

IT. No.

Art. n.

7 EA/NO

3-WAY VALVE WITH ON/OFF MOTOR - DN40

Valvola a 3 vie con motorizzazione on/off - DN40

IT. No.

Art. n.

8 EA/NO

3-WAY VALVE WITH MODULATING MOTOR - DN80

Valvola a 3 vie con motorizzazione modulante- DN80

IT. No.

Art. n.

9 EA/NO

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 4 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

ENERGY METER INTEGRATOR - DN 50

Contabilizzatore di energia termica- DN 50

IT. No.

Art. n.

10a EA/NO

ENERGY METER INTEGRATOR - DN 100

Contabilizzatore di energia termica - DN 100

IT. No.

Art. n.

10b EA/NO

BUTTERFLY VALVE - DN 25

Valvola a farfalla - DN 25

IT. No.

Art. n.

11a EA/NO

BUTTERFLY VALVE - DN 32

Valvola a farfalla - DN 32

IT. No.

Art. n.

11b EA/NO

BUTTERFLY VALVE - DN 40

Valvola a farfalla - DN 40

IT. No.

Art. n.

11c EA/NO

BUTTERFLY VALVE - DN 50

Valvola a farfalla - DN 50

IT. No.

Art. n.

11d EA/NO

BUTTERFLY VALVE - DN 80

Valvola a farfalla - DN 80

IT. No.

Art. n.

11e EA/NO

BUTTERFLY VALVE - DN 100

Valvola a farfalla - DN 100

IT. No.

Art. n.

11f EA/NO

CHECK VALVE - DN 20

Valvola di ritegno - DN 20

IT. No.

Art. n.

12a EA/NO

CHECK VALVE - DN 32

Valvola di ritegno - DN 32

IT. No.

Art. n.

12b EA/NO

CHECK VALVE - DN 40

Valvola di ritegno - DN 40

IT. No.

Art. n.

12c EA/NO

CHECK VALVE - DN 50

Valvola di ritegno - DN 50

IT. No.

Art. n.

12d EA/NO

CHECK VALVE - DN 100

Valvola di ritegno - DN 100

IT. No.

Art. n.

12e EA/NO

STRAINER FILTER - DN 25

Filtro obliquo - DN 25

IT. No.

Art. n.

13a EA/NO

STRAINER FILTER - DN 32

Filtro obliquo - DN 32

IT. No.

Art. n.

13b EA/NO

STRAINER FILTER - DN 40

Filtro obliquo - DN 40

IT. No.

Art. n.

13c EA/NO

STRAINER FILTER - DN 50

Filtro obliquo - DN 50

IT. No.

Art. n.

13d EA/NO

STRAINER FILTER - DN 100

Filtro obliquo - DN 100

IT. No.

Art. n.

13e EA/NO

STEEL ANTI VIBRATION CONNECTOR - DN 32

Giunto antivibrante in acciaio - DN 32

IT. No.

Art. n.

14a EA/NO

STEEL ANTI VIBRATION CONNECTOR - DN 40

Giunto antivibrante in acciaio - DN 40

IT. No.

Art. n.

14b EA/NO

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 5 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

STEEL ANTI VIBRATION CONNECTOR - DN 50

Giunto antivibrante in acciaio - DN 50

IT. No.

Art. n.

14c EA/NO

STEEL ANTI VIBRATION CONNECTOR - DN 100

Giunto antivibrante in acciaio - DN 100

IT. No.

Art. n.

14d EA/NO

Balancing valve - DN 20

Giunto antivibrante - DN 20

IT. No.

Art. n.

15a EA/NO

Balancing valve - DN 32

Giunto antivibrante - DN 32

IT. No.

Art. n.

15b EA/NO

Balancing valve - DN 100

Giunto antivibrante - DN 100

IT. No.

Art. n.

15c EA/NO

DRAIN AND VENT FOR CLOSED CIRCUIT IN ROOM 14

Drenaggi e sfiati per i circuiti chiusi nella Room 14

IT. No.

Art. n.

16 LS / AC

DRAIN LINE FOR ROOM 14

Rete di scarico Room 14

IT. No.

Art. n.

17 LS / AC

PRESSURE GAUGE FOR PIPE INSTALLATION

Manometro per tubazioni

IT. No.

Art. n.

18 EA/NO

THERMOMETER FOR PIPE INSTALLATION

Termometro per tubazioni

IT. No.

Art. n.

19 EA/NO

WATER SOFTENER - WS-1

Addolcitore - WS-1

IT. No.

Art. n.

20 EA/NO

CHEMICAL DOSING PUMP - DP-1

Pompa dosatrice - DP-1

IT. No.

Art. n.

21 EA/NO

REDUCED PRESSURE BACKFLOW PREVENTER - DN25

Disconnettore a zone di pressione controllabili - DN25

IT. No.

Art. n.

22 EA/NO

PRESSURE REGULATOR - DN25

Riduttore di pressione - DN25

IT. No.

Art. n.

23 EA/NO

SELF CLEANING AUTOMATIC FILTER - DN25

Filtro autopulente automatico - DN25

IT. No.

Art. n.

24 EA/NO

AUTOMATIC FILLING UNIT - DN20

Gruppo di riempimento - DN20

IT. No.

Art. n.

25 EA/NO

BALL VALVE - BRONZE BODY - DN15

Valvola a sfera - Corpo in bronzo - DN15

IT. No.

Art. n.

26a EA/NO

BALL VALVE - BRONZE BODY - DN20

Valvola a sfera - Corpo in bronzo - DN20

IT. No.

Art. n.

26b EA/NO

BALL VALVE - BRONZE BODY - DN25

Valvola a sfera - Corpo in bronzo - DN255

IT. No.

Art. n.

26c EA/NO

SLUDGE SEPARATOR AND CHEMICAL FEEDER (CPF)

Separatore di sporco e dosatore chimico

IT. No.

Art. n.

27 EA/NO

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 6 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

CONNECTION OF NEW HVAC SYSTEM TO EXISTING HOT

WATER LINE FROM EXISTING EXTERNAL BOILER ROOM

Collegamento dei nuovi impianti HVAC al circuito acqua calda in arrivo dalla centrale termica esterna esistente

IT. No.

Art. n.

28 LS / AC

OUTDOOR AIR HANDLING UNIT W/ CONTROL SYSTEM -

AHU-1

Unità di trattamento aria da esterno - AHU-1

IT. No.

Art. n.

29a EA/NO

OUTDOOR AIR HANDLING UNIT W/ CONTROL SYSTEM -

AHU-2

Unità di trattamento aria da esterno - AHU-2

IT. No.

Art. n.

29b EA/NO

RECIRCULATION AIR HANDLING UNIT W/ SENSOR AND

ACTUATOR - AHU- 5

Unità di trattamento aria per ricircolo con sensori ed attuatori -

AHU-5

IT. No.

Art. n.

30a EA/NO

RECIRCULATION AIR HANDLING UNIT W/ SENSOR AND

ACTUATOR - AHU -6

Unità di trattamento aria per ricircolo con sensori ed attuatori -

AHU-6

IT. No.

Art. n.

30b EA/NO

RECIRCULATION AIR HANDLING UNIT W/ SENSOR AND

ACTUATOR - AHU -7

Unità di trattamento aria per ricircolo con sensori ed attuatori -

AHU-7

IT. No.

Art. n.

30c EA/NO

COMPLETE SUPPLY AND RETURN AIR DUCTWORKS FOR AIR

HANDLING UNITS AHU-1 , AHU-2, AHU-5, AHU-6, AHU-7

Unità di Reti complete di canalizzaizoni di mandata e ripresa aria per le unità AHU-1, AHU-2, AHU-5, AHU-6, AHU-7

IT. No.

Art. n.

31 LS / AC

FANCOIL UNIT FOR CEILING INSTALLATION COMPLETE OF

DUCTWORKS, PIPEWORK, CONTROLS - FC-1

Ventilconvettore per installazione pensile completo di canalizzaizoni, tubazioni e controlli - FC-1

IT. No.

Art. n.

32a EA/NO

FANCOIL UNIT FOR CEILING INSTALLATION COMPLETE OF

DUCTWORKS, PIPEWORK, CONTROLS - FC-2

Ventilconvettore per installazione pensile completo di canalizzaizoni, tubazioni e controlli - FC-2

IT. No.

Art. n.

32b EA/NO

FANCOIL UNIT FOR FALSE CEILING INSTALL. COMPLETE OF

DUCTWORKS, PIPEWORK, CONTROLS - FC-1

Ventilconvettore per installazione in controsoffitto completo di canalizzaizoni, tubazioni e controlli - FC-1

IT. No.

Art. n.

33a EA/NO

FANCOIL UNIT FOR FALSE CEILING INSTALL. COMPLETE OF

DUCTWORKS, PIPEWORK, CONTROLS - FC-2

Ventilconvettore per installazione in controsoffitto completo di canalizzaizoni, tubazioni e controlli - FC-2

IT. No.

Art. n.

33b EA/NO

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 7 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

FANCOIL UNIT FOR FALSE CEILING INSTALL. COMPLETE OF

DUCTWORKS, PIPEWORK, CONTROLS - FC-3

Ventilconvettore per installazione in controsoffitto completo di canalizzaizoni, tubazioni e controlli - FC-3

IT. No.

Art. n.

33c EA/NO

FANCOIL UNIT 6V COMPLETE OF DUCTWORKS, PIPEWORK,

CONTROLS - FC-2

Ventilconvettore a 6V completo di canalizzaizoni, tubazioni e controlli - FC-2

IT. No.

Art. n.

34b EA/NO

FANCOIL UNIT 6V COMPLETE OF DUCTWORKS, PIPEWORK,

CONTROLS - FC-3

Ventilconvettore a 6V completo di canalizzaizoni, tubazioni e controlli - FC-3

IT. No.

Art. n.

34c EA/NO

DEDICATED HVAC FOR BATT ROOM W/ AHU-4, EF-4 ATEX

TYPE , DUCTWORK, PIPEWORK, CONTROL & FITTINGS

Impianto HVAC dedicato per la Battery Room completo di AHU-4, EF-4 atex, canali, tubazioni, controlli ed accessori.

IT. No.

Art. n.

35 LS / AC

DEDICATED HVAC FOR LOX ROOM W/ AHU-3, EF-3 ATEX

TYPE , DUCTWORK, PIPEWORK, CONTROL & FITTINGS

Impianto HVAC dedicato per la Battery Room completo di AHU-3, EF-3 atex, canali, tubazioni, controlli ed accessori.

IT. No.

Art. n.

36 LS / AC

MAIN HOT / CHILLED PIPEWORK FROM MECH ROOM 14

INCLUDING PIPES, INSULATION, CONVER & FITTINGS

Reti principali acqua calda/refrigerata dalla Mech Room 14 comprensive di tubi, isolamenti, rivestimenti ed accessori.

IT. No.

Art. n.

37 LS / AC

DX UNIT FOR ROOM 33

Unità ad espansione diretta per il locale 33

IT. No.

Art. n.

38 EA/NO

HOT WATER PIPEWORK FROM ROOM 14 TO H. BAY HEAT

EXCHANGER W/ PIPES, INSULATION, CONVER & FITTINGS

Circuito acqua calda dalla Mech Room 14 allo scambiatore area

Bay inclusi tubi, isolamenti, rivestimenti ed accessori.

IT. No.

Art. n.

39 LS / AC

COMPLETION OF MECHANICAL CONTROL SYSTEM - DDC

TYPE - INCLUDING SENSORS, CONTROLLER AND FITTINGS

Completamento del di controllo dell'impianto meccanico - Tipo

DDC - Completo di sensori, attuatori, regolatori ed accessori

IT. No.

Art. n.

40 LS / AC

CONDENSATE DRAIN SYSTEM MAIN PIPELINES

Tubazioni principali del sistema di raccolta della condensa

IT. No.

Art. n.

41 LS/AC

TESTING; ADJUSTING AND BALANCING OF THE HVAC

SYSTEMS

Prove, tarature e bilanciamento impianti HVAC

IT. No.

Art. n.

42 LS/AC

IIIb Plumbing system / IIIb Impianto Idraulico

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 8 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

PORTABLE EYEWASH W/ FITTINGS - WALL MOUNTED

Lavaocchi portatile con accessori - Montato a parete

IT. No.

Art. n.

43 LS/AC

UPGRADING POTABLE WATER AND COMPRESSED AIR

CONNECTION POINTS IN THE SHOP AREA

Modifiche ai punti di prelievo acqua potabile ed aria compressa nell'area delle officine

IT. No.

Art. n.

44 LS/AC

NEW COMPRESSED AIR LINE IN BAY AREA

Nuova linea aria compressa nell'area BAY

IT. No.

Art. n.

45 LS/AC

RELOCATION OF COMPRESSED AIR EQUIPMENTS

Modifiche ai punti di prelievo acqua potabile ed aria compressa nell'area delle officine

IT. No.

Art. n.

46 LS/AC

RELOCATION OF EXISTING FOAM CONCENTRATE TAN K AND

BLADDER REPLACEMENT

Spostamento dell'esistente serbatoio della schiuma e sostituzione della membrana

IT. No.

Art. n.

47 LS/AC

FOAM GENERATOR REPAIR

Riparazione generatore di schiuma

IT. No.

Art. n.

48 LS/AC

TOTAL PART III / Totale Parte III

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 9 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici

NEW 4P-250 A CIRCUIT BREAKER IN 400V MDP

Nuovo interruttore 4P-250 A nel MDP a 400 V

IT. No.

Art. n.

1 EA / No

A/C PANEL

Quadro elettrico per A/C

IT. No.

Art. n.

2 EA / No

A/C SYSTEM DISTRIBUTION

Distribuzione impianto A/C

IT. No.

Art. n.

3 LS / AC

COMPRESSOR SYSTEM DISCONNECT SWITCH

Sezionatore impianto aria compressa

IT. No.

Art. n.

4 EA / No

LIGHTING FIXTURE REINSTALLATION AND ADJUSTMENT

Reinstallazione e modifica elementi illuminanti

IT. No.

Art. n.

5 LS / AC

TOTAL PART IV - Totale Parte IV

TOTAL PRICE / Costo Totale

OR US DOLLARS (RATE 1$ = 0.7452€)

PART IV - ELECTRICAL WORK

PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS

PART III - MECHANICAL WORK

PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK

REPAIR WORKS SUMMARY / Riepilogo Lavori di

Ristrutturazione

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 10 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

B.

PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni

Ia Architectural - Ia Architettura

REMOVAL OF WOOD DOORS

Rimozione di porte in legno

IT. No.

Art. n.

1 EA/NO

REMOVAL OF METAL DOORS

Rimozione di porte in metallo

IT. No.

Art. n.

2 EA/NO

REMOVAL OF METAL WINDOWS W/INSECT SCREEN

Rimozione di finestre in metallo con rete antinsetto

IT. No.

Art. n.

3 EA/NO

REMOVAL OF WINDOW METAL GRATE

Rimozione di grate metalliche finestre

IT. No.

Art. n.

4 KG

REM. OF 10X20cm GRES TILE FLOOR W/SETT.BED

Rimozione di pavimento in gres 10x20 cm incluso massetto

IT. No.

Art. n.

5 SM/MQ

REMOVAL OF CERAMIC BASEBOARD

Rimozione di zoccolino in ceramica

IT. No.

Art. n.

6 LM/ML

REMOVAL OF METAL WAINSCOTING

Rimozione di rivestimento metallico

IT. No.

Art. n.

7 SM/MQ

REMOVAL OF RUBBER/PAINT FLOOR INCL. SETTING BED

Rimozione di pavimento in gomma/resina incluso massetto di posa

IT. No.

Art. n.

8 SM/MQ

DEMOLITION OF GYPSUM BOARD PARTITIONS

Demolizione di tramezzo in pannelli di gesso

IT. No.

Art. n.

9 SM/MQ

REMOVAL OF SUSPENDED CEILING

Rimozione di controsoffitto

IT. No.

Art. n.

10 SM/MQ

REMOVAL OF MEMBRANE ROOFING, INCL. THERMAL

INSULATION AND SLOPING BED

Rimozione di impermeabilizzazione in copertura, incluso isolamento termico e massetto pendenze

IT. No.

Art. n.

11 SM/MQ

REMOVAL OF METAL FLASHING

Rimozione di scossalina metallica

IT. No.

Art. n.

12 LM/ML

REMOVAL OF EXTERNAL STEP, ROOM 016

Rimozione di gradino esterni

IT. No.

Art. n.

13 EA/NO

PARTIAL DEMOLITION OF INTERIOR PLASTER

Demolizione parziale di intonaci interni

IT. No.

Art. n.

14 SM/MQ

PARTIAL DEMOLITION OF EXTERIOR PLASTER

Parziale demolizione di intonaci esterni

IT. No.

Art. n.

15 SM/MQ

DEMOLITION OF EXISTING METAL CANOPY

Demolizione di tettoia metallica esistente

IT. No.

Art. n.

16 LS/AC

DEMOLITION OF EXISTING COMM ROOM, ROOM No. 33

Demolizione del locale telecomunicazioni, locale n. 33

IT. No.

Art. n.

17 LS/AC

HANGAR BAY, CUTTING OF EXISTING INDUSTRIAL

PAVEMENT

Hangar, taglio di pavimentazione industriale

IT. No.

Art. n.

18 LM/ML

SUSTAIN WORK / Lavori di Manutenzione

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 11 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

HANGAR BAY, TRENCH EXCAVATION IN EXISTING CONCRETE

FLOOR FOR NEW CABLEDUCT

Hangar, scavo in trincea in pavimentazione industriale in calcestruzzo per nuovo cavidotto

IT. No.

Art. n.

19 CU.M/MC

HANGAR BAY, INDUSTRIAL CEMENT FLOOR SHOOT

BLASTING

Hangar, pulizia meccanica pavimentazione industriale

IT. No.

Art. n.

20 SM/MQ

HANGAR BAY, SLIDING FRONT DOOR PANEL CUT FOR PASS

110x90 THRU DOOR INSTALLATION

Hangar, taglio pannello portone scorrevole hangar per installazione portella 110x90

IT. No. 21 LS/AC

REMOVAL OF CEMENT ASBESTOS DOWNSPOUT ELBOW

Rimozione di raccordi in cemento amianto dei pluviali IT. No. 22 EA/NO

Total Architectural - Totale Architettura

Ib Structural Work - Ib Lavori Strutturali

NOT APPLICABLE/ Non applicabile

Ic Civil Work - Ic Lavori Civili

NOT APPLICABLE/ Non applicabile

Id Mechanical - Id Meccanico

NOT APPLICABLE/ Non applicabile

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 12 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Ie Electrical - Ie Elettrico

REMOVAL INTERLOCKED OUTLETS INCLUDING WIRING

SYSTEM

Rimozione prese interbloccate compresi i collegamenti

IT. No.

Art. n.

23 LS/AC

REMOVAL ITALIAN/USA TYPE OUTLETS INCLUDING WIRING

SYSTEM

Rimozione prese tipo italiano/USA compresi i collegamenti

IT. No.

Art. n.

24 LS/AC

REMOVAL ELECTRICAL PANELS

Rimozione quadri elettrici

IT. No.

Art. n.

25 LS/AC

REMOVAL OF WIRING SYSTEM FEEDING LIGHTING FIXTURES

Rimozione di collegamenti elettrici alimentanti i corpi illuminanti esistenti

IT. No.

Art. n.

26 LS/AC

REMOVAL OF TELECOMM OUTLETS INCLUDING WIRING

SYSTEM

Rimozione di prese telefoniche compresi i collegamenti

IT. No.

Art. n.

27 LS/AC

REMOVAL OF TELECOMM RACK

Rimozione armdi telefonici

IT. No.

Art. n.

28 LS/AC

REMOVAL GROUNDING & LIGHTNING PROTECTION SYSTEM

Rimozione impianti di terra e parafulmini

IT. No.

Art. n.

29 LS/AC

REMOVAL AND REINSTALL OF FIRE DETECTION EQUIPMENT

Rimozione e reinstallazione di apparecchiature rilevazione incendi

IT. No.

Art. n.

30 LS/AC

REMOVAL OF OUTDOOR LIGHTING FIXTURES INCLUDING

WIRING SYSTEM

Rimozione dei corpi illuminanti esterni compresi i collegamenti

IT. No.

Art. n.

31 LS/AC

Total Electrical - Totale Elettrico

TOTAL PART I / Totale Parte I

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 13 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili

IIa Architectural - IIa Architettonico

30x30 CM GRANITE CERAMIC TILE FLOOR, INCL SETT. BED

Pavimento in piastrelle di granito ceramico 30x30, incl. massetto

IT. No.

Art. n.

1 SM/MQ

GRANITE CERAMIC COVE BASE

Zoccolino in granito ceramico

IT. No.

Art. n.

2 LM/ML

EPOXY RESIN ON INDUSTRIAL FLOOR IN ANNEX AREA

Applicazione di resina epossidica su pavimento industriale nelle aree di supporto.

IT. No.

Art. n.

3 SM/MQ

RUBBER COVE BASE

Zoccolino in gomma

IT. No.

Art. n.

4 LM/ML

RUBBER FLOOR SETTING BED

Letto di posa pavimento in gomma

IT. No.

Art. n.

5 SM/MQ

MINERAL FIBER PANEL SUSPENDED CEILING

Controsoffitto in pannelli di fibra minerale

IT. No.

Art. n.

6 SM/MQ

PAINT INTERIOR SURFACES WITH WATER ENAMEL

Pitturazione con idropittura lavabile delle superfici interne

IT. No.

Art. n.

7 SM/MQ

PAINT INTERIOR CEILING

Pitturazione a tempera dei soffitti

IT. No.

Art. n.

8 SM/MQ

PAINT EXTERIOR SURFACES WITH WATER ENAMEL

Pitturazione con idropittura lavabile delle superfici esterne

IT. No.

Art. n.

9 SM/MQ

INTERIOR PLASTER

Intonaco interno

IT. No.

Art. n.

10 SM/MQ

EXTERIOR PLASTER

Intonaco esterno

IT. No.

Art. n.

11 SM/MQ

240x220cm REI120 STEEL DOORS, Di1 Type

Porta in acciaio 240x220 REI120, tipo Di1

IT. No.

Art. n.

12a EA/NO

120x220cm REI120 STEEL DOORS, Di2 Type

Porta in acciaio 120x220 REI120, tipo Di2

IT. No.

Art. n.

12b EA/NO

150x250cm REI120 STEEL DOORS, Di3 Type

Porta in acciaio 150x250 REI120, tipo Di3

IT. No.

Art. n.

12c EA/NO

220x250cm REI120 STEEL DOORS, Di4 Type

Porta in acciaio 220x250 REI120, tipo Di4

IT. No.

Art. n.

12d EA/NO

90x215cm REI120 STEEL DOORS, Di5 Type

Porta in acciaio 90x215 REI120, tipo Di5

IT. No.

Art. n.

12e EA/NO

100x220 INTERIOR WOOD DOOR, Di6 Type

Porte interne in legno 100x220, tipo Di6

IT. No.

Art. n.

13a EA/NO

170x210 INTERIOR WOOD DOOR, Di7 Type

Porte interne in legno 170x210, tipo Di7

IT. No.

Art. n.

13b EA/NO

80x210 INTERIOR WOOD DOOR, Di8 Type

Porte interne in legno 80x210, tipo Di8

IT. No.

Art. n.

13c EA/NO

100x210 INTERIOR WOOD DOOR, Di9 Type

Porte interne in legno 100x210, tipo Di9

IT. No.

Art. n.

13d EA/NO

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 14 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

100x230 INTERIOR WOOD DOOR, Di10 Type

Porte interne in legno 100x230, tipo Di10

IT. No.

Art. n.

13e EA/NO

70x220 INTERIOR STEEL DOOR, Di11 Type

Porte interne in acciaio 70x220, tipo Di11

IT. No.

Art. n.

14 EA/NO

190x265 EXTERIOR ALUMINUM DOOR, De1 Type

Porte esterne in alluminio 190x265, tipo De1

IT. No.

Art. n.

15 EA/NO

150x225 EXTERIOR STEEL DOOR, De2 Type

Porte esterne in acciaio 150x225, tipo De2

IT. No.

Art. n.

16a EA/NO

100x215 EXTERIOR STEEL DOOR, De3 Type

Porte esterne in acciaio 100x215, tipo De3

IT. No.

Art. n.

16b EA/NO

110x230 EXTERIOR STEEL DOOR, De4 Type

Porte esterne in acciaio 110x230, tipo De4

IT. No.

Art. n.

16c EA/NO

140x220 EXTERIOR STEEL DOOR, De5 Type

Porte esterne in acciaio 140x220, tipo De5

IT. No.

Art. n.

16d EA/NO

190x220 EXTERIOR STEEL DOOR, De6 Type

Porte esterne in acciaio 190x220, tipo De6

IT. No.

Art. n.

16e EA/NO

100x220 EXTERIOR STEEL DOOR, De7 Type

Porte esterne in acciaio 100x220, tipo De7

IT. No.

Art. n.

16f EA/NO

315x270 ROLLING UP EXTERIOR DOOR, De8 Type

Portone esterno a saracinesca 315x270, tipo De8

IT. No.

Art. n.

17 EA/NO

155x150cm ANDZ. ALUM. WINDOW , F1 Type

Finestra in alluminio anodiz., 155x155 cm, tipo F1

IT. No.

Art. n.

18a EA/NO

115x155cm ANDZ. ALUM. WINDOW , F2 Type

Finestra in alluminio anodiz., 115x155 cm, tipo F2

IT. No.

Art. n.

18b EA/NO

140x150cm ANDZ. ALUM. WINDOW , F3 Type

Finestra in alluminio anodiz., 140x150 cm, tipo F3

IT. No.

Art. n.

18c EA/NO

220x155cm ANDZ. ALUM. WINDOW , F4 Type

Finestra in alluminio anodiz., 220x155 cm, tipo F4

IT. No.

Art. n.

18d EA/NO

100x125cm ANDZ. ALUM. WINDOW , F5 Type

Finestra in alluminio anodiz., 100x125 cm, tipo F5

IT. No.

Art. n.

18e EA/NO

Dia. 130cm ANDZ. ALUM. WINDOW , F6 Type

Finestra in alluminio anodiz., dia 130 cm, tipo F6

IT. No.

Art. n.

18f EA/NO

140x140cm ANDZ. ALUM. WINDOW , F7 Type

Finestra in alluminio anodiz., 140x140 cm, tipo F7

IT. No.

Art. n.

18g EA/NO

215x270cm ANDZ. ALUM. WINDOW , F8 Type

Finestra in alluminio anodiz., 215x270 cm, tipo F8

IT. No.

Art. n.

18h EA/NO

165x155cm ANDZ. ALUM. WINDOW , F9 Type

Finestra in alluminio anodiz., 165x155 cm, tipo F9

IT. No.

Art. n.

18i EA/NO

105x95cm ANDZ. ALUM. WINDOW , F10 Type

Finestra in alluminio anodiz., 105x95 cm, tipo F10

IT. No.

Art. n.

18j EA/NO

140x800cm ANDZ. ALUM. WINDOW , F11 Type

Finestra in alluminio anodiz., 140x80 cm, tipo F11

IT. No.

Art. n.

18k EA/NO

117x143cm ANDZ. ALUM. WINDOW , F12 Type

Finestra in alluminio anodiz., 117x143 cm, tipo F12

IT. No.

Art. n.

18l EA/NO

GLAZING PANEL REPLACEMENT

Sostituzione pannelli vetrati

IT. No.

Art. n.

19 SM/MQ

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 15 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

EXTERNAL STEPS REPAIR

Ripristino gradini esterni

IT. No.

Art. n.

20 LS/AC

8/10 MM ALLMINUM FLASHINGS

Scossaline in alluminio da 8/10mm

IT. No.

Art. n.

21 LM/ML

NEW ROOFING

Nuovo pacchetto di copertura

IT. No.

Art. n.

22 SM/MQ

25CM THICK LOAD BEARING WALL

Muro porttante, spessore 25cm

IT. No.

Art. n.

23 SM/MQ

CEILING CORRUGATED STEEL SLAB

Solaio di copertura in lamiera grecata

IT. No.

Art. n.

24 SM/MQ

HANGAR BAY CEMENT FLOOR REPAIR

Ripristino pavimentazione in cemento hangar

IT. No.

Art. n.

25 SM/MQ

HANGAR BAY CEMENT FLOOR SURFACE TREATMENT

Trattamento superficiale pavimentazione in cemento hangar

IT. No.

Art. n.

26 SM/MQ

100x100CM PASS THRU SERVICE DOOR AT HANGAR DOOR

Portella di servizio 100x100cm nel potone scorrevole hangar

IT. No.

Art. n.

27 EA/NO

STEEL LADDER FOR ROOF ACCESS

Scale metalliche per accesso in copertura

IT. No.

Art. n.

28 KG

SAFETY GLVD STEEL RAILING

Ringhiera di sicurezza in acciaio zincato

IT. No.

Art. n.

29 KG

180x80cm RECESSED COCCO MAT, ROOM 012

Zerbino incassato in cocco 180x80cm, locale 012

IT. No.

Art. n.

30 EA/NO

WALL MOUNTEDELECTROMAGNETIC DOOR HOLDERS

Fermi elettromagnetici montati a parete

IT. No.

Art. n.

31a EA/NO

FLOOR MOUNTED ELECTROMAGNETIC DOOR HOLDERS

Fermi elettromagnetici montati a pavimento

IT. No.

Art. n.

31b EA/NO

DOOR HOLDERS ANCHOR SYSTEM

Ancora per fermi elettromagnetici

IT. No.

Art. n.

31c EA/NO

HDPE DOWNSPOUT ELBOWS, INCL. SURFACES REPAIR

Raccordi pluviali in PEAD, incluso ripristino superfici

IT. No.

Art. n.

32 EA/NO

REI120 PARTITION WALL, ROOM 009. INCL. CEILING

Tramezzo Rei120, locale 009. Incluso soletta di chiusura

IT. No.

Art. n.

33 LS/AC

OVERHEAD DOOR REPAIR, ROOM 008

Riparazione portone sezionale, locale 008

IT. No.

Art. n.

34 LS/AC

Total Architectural - Totale architettonico

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 16 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

IIb Structural Work - IIc Lavori Strutturali

NOT APPLICABLE/ Non applicabile

IIc Civil Work - IIc Lavori Civili

NOT APPLICABLE/ Non applicabile

TOTAL PART II / Totale Parte II

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 17 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

PART III - MECHANICAL WORK / Parte III - Lavori Meccanici

NOT APPLICABLE/ Non applicabile

PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici

SONIC BIRD CONTROL SYSTEM

Dissuasore sonoro allontanamento volatili

IT. No.

Art. n.

1 LS/AC

NEW CABLES FEEDING NEW ELECTRICAL PANELS

3x1x70+35N+35PE

Nuovi cavi alimentanti i nuovi quadri elettrici

3x1x70+35N+35PE

IT. No.

Art. n.

2a LM/ML

NEW CABLES FEEDING NEW ELECTRICAL PANELS

3x1x70+35N+35PE

Nuovi cavi alimentanti i nuovi quadri elettrici

3x1x70+35N+35PE

IT. No.

Art. n.

2b LM/ML

NEW CABLES FEEDING NEW ELECTRICAL PANELS

3x1x95+50N+50PE

Nuovi cavi alimentanti i nuovi quadri elettrici

3x1x95+50N+50PE

IT. No.

Art. n.

2c LM/ML

NEW CABLES FEEDING NEW ELECTRICAL PANELS

3x1x120+70N+70PE

Nuovi cavi alimentanti i nuovi quadri elettrici

3x1x120+70N+70PE

IT. No.

Art. n.

2d LM/ML

NEW CABLES FEEDING NEW ELECTRICAL PANELS

3x1x95+50N+50PE

Nuovi cavi alimentanti i nuovi quadri elettrici

3x1x95+50N+50PE

IT. No.

Art. n.

2e LM/ML

NEW CABLES FEEDING NEW ELECTRICAL PANELS

3x1x70+35N+35PE

Nuovi cavi alimentanti i nuovi quadri elettrici

3x1x70+35N+35PE

IT. No.

Art. n.

2f LM/ML

500x150 CABLE TRAY

Canaletta 500x150

IT. No.

Art. n.

2g LM/ML

100x75 CABLE TRAY

Canaletta 100x75

IT. No.

Art. n.

2h LM/ML

NEW 4P-250A CIRCUIT BREAKER

Nuovo interruttore 4P-250A

IT. No.

Art. n.

3 EA/NO

NEW ELECTRICAL PANELS A AND B - PANEL A

Nuovi quadri elettrici A e B - Quadro A

IT. No.

Art. n.

4a EA/NO

NEW ELECTRICAL PANELS A AND B - QUADRO B

Nuovi quadri elettrici A e B - Quadro B

IT. No.

Art. n.

4b EA/NO

NEW ELECTRICAL PANELS C AND D - PANEL C

Nuovi quadri elettrici C e D - Quadro C

IT. No.

Art. n.

5a EA/NO

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 18 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

NEW ELECTRICAL PANELS C AND D - PANEL D

Nuovi quadri elettrici C e D - Quadro D

IT. No.

Art. n.

5b EA/NO

NEW ELECTRICAL PANEL HBOP

Nuovo quadro elettrico HBOP

IT. No.

Art. n.

6 EA/NO

NEW ZONE OUTLET PANEL

Nuovo quadro prese di zona

IT. No.

Art. n.

7 EA/NO

NEW INTERLOCKED OUTLETS

Nove prese interbloccate

IT. No.

Art. n.

8 EA/NO

NEW IDIGITAL MULTI-METER

Novo Multimetro Digitale

IT. No.

Art. n.

9 EA/NO

NEW OUTLETS ITALIAN STYLE

Nuove prese tipo Italiano

IT. No.

Art. n.

10 EA/NO

NEW OUTLETS USA STYLE

Nuove prese tipo USA

IT. No.

Art. n.

11 EA/NO

NEW GROUND FAULT OUTLETS

Nuove prese con differenziale

IT. No.

Art. n.

12 EA/NO

TWO SECTION 195x65 FLOOR BASE CHANNEL

Canalina battiscopa a due scomparti 195x65

IT. No.

Art. n.

13 LM/ML

CIVIL OUTLET POINT

Punto presa civile

IT. No.

Art. n.

14 EA/NO

LIGHTING POINT

Punto luce

IT. No.

Art. n.

15 EA/NO

UPGRADING EXISTING 10% LIGHTING FIXTURES

Revisione 10% corpi illuminanti esistenti

IT. No.

Art. n.

16 LS/AC

NEW CABLES FEEDING NEW INTERLOCKED OUTLETS, 5x16

Nuovi cavi alimentanti le prese interbloccate, 5x16

IT. No.

Art. n.

17a LM/ML

NEW CABLES FEEDING NEW INTERLOCKED OUTLETS, 5x6

Nuovi cavi alimentanti le prese interbloccate, 5x6

IT. No.

Art. n.

17b LM/ML

NEW CABLES FEEDING NEW INTERLOCKED OUTLETS, 3x6

Nuovi cavi alimentanti le prese interbloccate, 3x6

IT. No.

Art. n.

17c LM/ML

NEW 2X36 W LIGHTING FIXTURES

Nuovi corpi illuminanti 2x36 W

IT. No.

Art. n.

18 EA/NO

NEW 4X18 W LIGHTING FIXTURES

Nuovi corpi illuminanti 4X18 W

IT. No.

Art. n.

19 EA/NO

NEW LED TYPE OUTDOOR FLOODLIGHTS

Nuovi proiettori da esterno a LED

IT. No.

Art. n.

20 EA/NO

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 19 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOUR

S

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

NEW COMMUNICATION OUTLETS

Nuove prese per comunicazioni

IT. No.

Art. n.

21 EA/NO

NEW COMMUNICATION POINT

Nuovo punto per comunicazioni

IT. No.

Art. n.

22 EA/NO

NEW COMMUNICATION RACK - MAIN RACK

Nuove Armadio per comunicazioni - Rack Principale

IT. No.

Art. n.

23a EA/NO

NEW COMMUNICATION RACK - TR1

Nuove Armadio per comunicazioni - TR1

IT. No.

Art. n.

23b EA/NO

NEW COMMUNICATION RACK - TR2

Nuove Armadio per comunicazioni - TR2

IT. No.

Art. n.

23c EA/NO

NEW COMMUNICATION RACK - OPTIC FIBER CABLE

Nuove Armadio per comunicazioni - Cavi Fibra Ottica

IT. No.

Art. n.

23d LM/ML

NEW WIFI ACCESS POINT - OFFICES

Nuovi punti di accesso WIFI - Uffici

IT. No.

Art. n.

24a LS/AC

NEW WIFI ACCESS POINT - HANGAR BAY

Nuovi punti di accesso WIFI - Area hangar

IT. No.

Art. n.

24b LS/AC

NEW WIFI ACCESS POINT - OUTDOOR

Nuovi punti di accesso WIFI - Esterno

IT. No.

Art. n.

24c LS/AC

TEMPERATURE CONTROL PANEL

Quadro controllo temperatura

IT. No.

Art. n.

25 LS/AC

ELECTROMAGNETIC HOLDERS CONNECTIONS

Collegamenti degli elettromagneti

IT. No.

Art. n.

26 LS/AC

NEW LPS SYSTEM

Nuovo impianto LPS

IT. No.

Art. n.

27 LS/AC

ELECTRICAL SYSTEMS TESTS

Collaudo Impianti Elettrici

IT. No.

Art. n.

28 LS/AC

TELECOMM SYSTEM TESTS

Collaudo Impianto Telefonico

IT. No.

Art. n.

29 LS/AC

SUSTAIN WORKS SUMMARY / Riepilogo Lavori di

Manutenzione

TOTAL PRICE / Costo Totale

OR US DOLLARS (RATE 1$ = 0.7452€)

PART IV - ELECTRICAL WORK

TOTAL PART IV - Totale Parte IV

PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS

PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 20 of 22

CONTRACTOR ADDRESS

CONTRACT FOR (Work to be performed) PROPOSED TOTAL CONTRACT PRICE

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY

PURCHASE REQUEST NUMBER PROJECT NUMBER WORK LOCATION

ASHE 09-1031 AREA F, AVIANO AIR BASE, ITALY

MATERIAL COSTS LABOR COSTS

LINE

NO.

ITEM

UNIT OF

MEASURE

QUANTITY UNIT TOTAL

MANHOURS

MANDAYS

AVERAGE

RATE

TOTAL

OTHER DIRECT

COSTS

LINE TOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

A.

SUB TOTAL A.

B.

SUB TOTAL B.

TOTAL PRICE / Costo Totale

OR US DOLLARS (RATE 1$ = 0.7452€)

REPAIR WORKS / Lavori di Ristutturazione

PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS

PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK

PART IV - ELECTRICAL WORK

PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS

PART III - MECHANICAL WORK

PART IV - ELECTRICAL WORK

PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK

SUSTAIN WORKS / Lavori di Manutenzione

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 21 of 22

INSTRUCTIONS FOR COMPLETING AF FORM

TOTAL MATERIAL COSTS € € € $

TOTAL LABOR COSTS € € € $

TOTAL OTHER DIRECT COSTS € € € $

OVERHEAD % € € € $

SUBTOTAL € € € $

PROFIT % € € € $

TOTAL PRICE € € € $

DATE FIRM NAME

TITLE BY

INSTRUCTIONS TO OFFERORS

RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY

TOTAL A+B (€) TOTAL A+B ($)A. REPAIR B. SUSTAIN

TOTAL DIRECT COSTS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see

ASPR 3-807.3 and 3-807.4).

2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:

a. The existing, verifiable data.

b. The judgmental factors applied in projecting from know data to the estimate, and

c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.

4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.

Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.

Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet-

SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).

Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). Item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued.

Otherwise, the contractor is responsible for determining quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.

Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.

Col 10 Line. Self-explanatory.

Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:

PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 22 of 22