PROJECT ASHE 09-1031
RESTORE HANGAR 1 BLDG. 921, AREA “F”,
AVIANO AIR BASE, AVIANO, ITALY
CONSTRUCTION COST ESTIMATE
REVISION 1
FINAL SUBMITTAL (100%)
Date: November 2014
A/E CONTRACT No.: FA5682-13-D-0004 D.O.: 0004
Prepared and Submitted by:
SO.IN.CI. S.r.l.
Architecture, Engineering & Consulting Services
Via di Sacco Pastore n. 4 - Rome, Italy Tel. +39.06.97848041 fax +39.06.97848175
E-mail: design@soinci.it
U.S. AIR FORCE
31ST FIGHTER WING
AVIANO AIR BASE, ITALY
mailto:design@soinci.it
FOR OFFICIAL USE ONLY
CONSTRUCTION COST ESTIMATE BREAKDOWN – REV 1
CONTRACTOR ADDRESS
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
WORK LOCATION
AREA F, AVIANO AIR BASE, ITALY
LINE
NO.
ITEM
(1)
UNIT OF
MEASURE
(2)
QUANTITY
(3)
MATERIAL COSTS LABOR COSTS
OTHER DIRECT
COSTS
(9)
LINE TOTAL
(10)
UNIT
(4)
TOTAL
(5)
MANHOURS
MANDAYS
(6)
AVERAGE
RATE
(7)
(8)
A. REPAIR WORKS / Lavori di Ristrutturazione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni
Ia Architectural - Ia Architettura
NOT APPLICABLE/ Non applicabile
Ib Structural Work - Ib Lavori Strutturali
SURVEYED WALL DEMOLITION FOR HVAC PASSAGEWAY IT. No.
Demolizione controllata di muratura par passaggi HVAC Art. n. 1 LS/AC
ROOF SLAB SLOT OPENINGS FOR HVAC PASSAGEWAY IT. No.
Apertura asole in solaio copertura passaggi HVAC Art. n. 2 LS/AC
Total structural - Totale Strutturali
Ic Civil Work - Ic Lavori Civili
Id Mechanical - Id Meccanico
REMOVAL OF EXISTING AHUs W/ DUCTWORK, PIPES, VALVES, AIR GRILLES AND INSTALLED FITTINGS IT. No.
Rimozione delle esistenti unità di trattamento aria comprei i canali, Art. n. 3 tubi, valvole, griglie ed accessori presenti
LS/AC
REMOVAL OF PUMPS, VALVE, PIPING AND FITTINGS INSIDE
MECH ROOM 14 IT. No.
Rimozione di elettropompe, valvole, tubazioni ed accessori nel Art. n. 4 locale meccanico 14
REMOVAL OF MONOSPLIT SYSTEM W/ PIPE, WIRING,
CONTROL PANEL IT. No.
Rimozione di monosplit comprese le tubazioni, linee elettriche, Art. n. 5 pannello di controllo
EA/NO
FOR OFFICIAL USE ONLY Sheet 1 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
REMOVAL OF DUALSPLIT SYSTEM W/ PIPE, WIRING,
CONTROL PANEL IT. No.
Rimozione di dual split comprese le tubazioni, linee elettriche, Art. n. 6 pannello di controllo
REMOVAL OF FANCOIL WALL MOUNTED W/ FITTINGS IT. No.
Rimozione di ventilconvettore a parete con accessori Art. n. 7 EA/NO
REMOVAL OF ROOF EXHAUST FAN IT. No.
Rimozione di ventilatore di estrazione Art. n. 8 EA/NO
REMOVAL OF LITTLE CHILLER ON THE ROOF IT. No.
Rimozione di piccolo chiller sulla copertura Art. n. 9 EA/NO
REMOVAL OF PIPE W/ VALVES, INSULATION, BRACKETS AND
FITTINGS IT. No.
Rimozione di tubazioni incluse le valvole, la coibentazione, gli Art. n. 10 staffaggi e gli accessori
Total Mechanical - Totale Meccanico
Ie Electrical - Ie Elettrico
REMOVE ELECTRICAL SYSTEM FEEDING A/C EQUIPMENT IT. No. Rimozione dell'impianto elettrico alimentante le apparecchiature di 11 Condizionamento Art. n.
LS / AC
Total Electrical - Totale Elettrico
TOTAL PART I - Totale Parte I
FOR OFFICIAL USE ONLY Sheet 2 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili
IIa Architectural - IIa Architettonico
LIGHT CONCRETE PADS AND SUPPORT BLOCKS FOR HVAC IT. No. UNITS 1 Basamenti e Baggioli per Unità Hvac Art. n.
Total Architectural - Totale Architettura
IIb Structural Work - IIb Lavori Strutturali
IIc Civil Work - IIc Lavori Civili
TOTAL PART II / Totale Parte II
FOR OFFICIAL USE ONLY Sheet 3 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
PART III - MECHANICAL WORK / Parte III - Lavori Meccanici
IIIa - HVAC System / IIIa - Impianto di Condizionamento
REVERSIBLE HEAT PUMP RHP-1 W/ LOW TEMP KIT, PUMP
KIT, PARTIAL HEAT RECOVERY AND FITTINGS IT. No.
Pompa di calore reversione RHP-1 con kit bassa tempertura, Art. n. 1 modulo idronico, recupero di calore parziale ed accessori
VERTICAL SINGLE STAGE TWIN CENTRIFUGAL PUMP,
VARIABE SPEED W/ PRESSURE SENSOR & FITTINGS - CP1 IT. No.
Pompa gemellare centrifuga a singolo stadio, velocità variabile con Art. n. 2a sensore di pressione ed accessori - CP1
VARIABE SPEED W/ PRESSURE SENSOR & FITTINGS - CP2 IT. No.
Pompa gemellare centrifuga a singolo stadio, velocità variabile con Art. n. 2b sensore di pressione ed accessori - CP2
VARIABE SPEED W/ PRESSURE SENSOR & FITTINGS - CP4 IT. No.
Pompa gemellare centrifuga a singolo stadio, velocità variabile con Art. n. 2c sensore di pressione ed accessori - CP4
HIGH EFFICIENCIES CIRCULATOR - TWIN TYPE - CP3 IT. No.
Circolatore ad alta efficienza - Gemellare - CP3 Art. n. 3a EA/NO
HIGH EFFICIENCIES CIRCULATOR - SINGLE TYPE - CP4 IT. No.
Circolatore ad alta efficienza - singolo - CP4 Art. n. 3b EA/NO
HIGH EFFICIENCIES CIRCULATOR - SINGLE TYPE - CP6 IT. No.
Circolatore ad alta efficienza - singolo - CP6 Art. n. 4a EA/NO
INERTIAL TANK - IT-1 IT. No.
Serbatoio inerziale - IT-1 Art. n. 5 EA/NO
EXPANSION TANK - ET-1 IT. No.
Vaso di espansione - ET-1 Art. n. 6a EA/NO
EXPANSION TANK - ET-2 IT. No.
Vaso di espansione - ET-2 Art. n. 6b EA/NO
EXPANSION TANK - ET-3 IT. No.
Vaso di espansione - ET-3 Art. n. 6c EA/NO
2-WAY VALVE WITH ON/OFF MOTOR - DN100 IT. No.
Valvola a 2 vie con motorizzazione on/off - DN100 Art. n. 7 EA/NO
3-WAY VALVE WITH ON/OFF MOTOR - DN40 IT. No.
Valvola a 3 vie con motorizzazione on/off - DN40 Art. n. 8 EA/NO
3-WAY VALVE WITH MODULATING MOTOR - DN80 IT. No.
Valvola a 3 vie con motorizzazione modulante- DN80 Art. n. 9 EA/NO
FOR OFFICIAL USE ONLY Sheet 4 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
ENERGY METER INTEGRATOR - DN 50 IT. No.
Contabilizzatore di energia termica- DN 50 Art. n. 10a EA/NO
ENERGY METER INTEGRATOR - DN 100 IT. No.
Contabilizzatore di energia termica - DN 100 Art. n. 10b EA/NO
BUTTERFLY VALVE - DN 25 IT. No.
Valvola a farfalla - DN 25 Art. n. 11a EA/NO
BUTTERFLY VALVE - DN 32 IT. No.
Valvola a farfalla - DN 32 Art. n. 11b EA/NO
BUTTERFLY VALVE - DN 40 IT. No.
Valvola a farfalla - DN 40 Art. n. 11c EA/NO
BUTTERFLY VALVE - DN 50 IT. No.
Valvola a farfalla - DN 50 Art. n. 11d EA/NO
BUTTERFLY VALVE - DN 80 IT. No.
Valvola a farfalla - DN 80 Art. n. 11e EA/NO
BUTTERFLY VALVE - DN 100 IT. No.
Valvola a farfalla - DN 100 Art. n. 11f EA/NO
CHECK VALVE - DN 20 IT. No.
Valvola di ritegno - DN 20 Art. n. 12a EA/NO
CHECK VALVE - DN 32 IT. No.
Valvola di ritegno - DN 32 Art. n. 12b EA/NO
CHECK VALVE - DN 40 IT. No.
Valvola di ritegno - DN 40 Art. n. 12c EA/NO
CHECK VALVE - DN 50 IT. No.
Valvola di ritegno - DN 50 Art. n. 12d EA/NO
CHECK VALVE - DN 100 IT. No.
Valvola di ritegno - DN 100 Art. n. 12e EA/NO
STRAINER FILTER - DN 25 IT. No.
Filtro obliquo - DN 25 Art. n. 13a EA/NO
STRAINER FILTER - DN 32 IT. No.
Filtro obliquo - DN 32 Art. n. 13b EA/NO
STRAINER FILTER - DN 40 IT. No.
Filtro obliquo - DN 40 Art. n. 13c EA/NO
STRAINER FILTER - DN 50 IT. No.
Filtro obliquo - DN 50 Art. n. 13d EA/NO
STRAINER FILTER - DN 100 IT. No.
Filtro obliquo - DN 100 Art. n. 13e EA/NO
STEEL ANTI VIBRATION CONNECTOR - DN 32 IT. No.
Giunto antivibrante in acciaio - DN 32 Art. n. 14a EA/NO
STEEL ANTI VIBRATION CONNECTOR - DN 40 IT. No.
Giunto antivibrante in acciaio - DN 40 Art. n. 14b EA/NO
FOR OFFICIAL USE ONLY Sheet 5 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
STEEL ANTI VIBRATION CONNECTOR - DN 50 IT. No.
Giunto antivibrante in acciaio - DN 50 Art. n. 14c EA/NO
STEEL ANTI VIBRATION CONNECTOR - DN 100 IT. No.
Giunto antivibrante in acciaio - DN 100 Art. n. 14d EA/NO
Balancing valve - DN 20 IT. No.
Giunto antivibrante - DN 20 Art. n. 15a EA/NO
Balancing valve - DN 32 IT. No.
Giunto antivibrante - DN 32 Art. n. 15b EA/NO
Balancing valve - DN 100 IT. No.
Giunto antivibrante - DN 100 Art. n. 15c EA/NO
DRAIN AND VENT FOR CLOSED CIRCUIT IN ROOM 14 IT. No.
Drenaggi e sfiati per i circuiti chiusi nella Room 14 Art. n. 16 LS / AC
DRAIN LINE FOR ROOM 14 IT. No.
Rete di scarico Room 14 Art. n. 17 LS / AC
PRESSURE GAUGE FOR PIPE INSTALLATION IT. No.
Manometro per tubazioni Art. n. 18 EA/NO
THERMOMETER FOR PIPE INSTALLATION IT. No.
Termometro per tubazioni Art. n. 19 EA/NO
WATER SOFTENER - WS-1 IT. No.
Addolcitore - WS-1 Art. n. 20 EA/NO
CHEMICAL DOSING PUMP - DP-1 IT. No.
Pompa dosatrice - DP-1 Art. n. 21 EA/NO
REDUCED PRESSURE BACKFLOW PREVENTER - DN25 IT. No.
Disconnettore a zone di pressione controllabili - DN25 Art. n. 22 EA/NO
PRESSURE REGULATOR - DN25 IT. No.
Riduttore di pressione - DN25 Art. n. 23 EA/NO
SELF CLEANING AUTOMATIC FILTER - DN25 IT. No.
Filtro autopulente automatico - DN25 Art. n. 24 EA/NO
AUTOMATIC FILLING UNIT - DN20 IT. No.
Gruppo di riempimento - DN20 Art. n. 25 EA/NO
BALL VALVE - BRONZE BODY - DN15 IT. No.
Valvola a sfera - Corpo in bronzo - DN15 Art. n. 26a EA/NO
BALL VALVE - BRONZE BODY - DN20 IT. No.
Valvola a sfera - Corpo in bronzo - DN20 Art. n. 26b EA/NO
BALL VALVE - BRONZE BODY - DN25 IT. No.
Valvola a sfera - Corpo in bronzo - DN255 Art. n. 26c EA/NO
SLUDGE SEPARATOR AND CHEMICAL FEEDER (CPF) IT. No.
Separatore di sporco e dosatore chimico Art. n. 27 EA/NO
FOR OFFICIAL USE ONLY Sheet 6 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
CONNECTION OF NEW HVAC SYSTEM TO EXISTING HOT
WATER LINE FROM EXISTING EXTERNAL BOILER ROOM IT. No.
Collegamento dei nuovi impianti HVAC al circuito acqua calda in Art. n. 28 arrivo dalla centrale termica esterna esistente
OUTDOOR AIR HANDLING UNIT W/ CONTROL SYSTEM - IT. No. AHU-1 29a Unità di trattamento aria da esterno - AHU-1 Art. n.
OUTDOOR AIR HANDLING UNIT W/ CONTROL SYSTEM - IT. No. AHU-2 29b Unità di trattamento aria da esterno - AHU-2 Art. n.
RECIRCULATION AIR HANDLING UNIT W/ SENSOR AND
ACTUATOR - AHU- 5 IT. No.
Unità di trattamento aria per ricircolo con sensori ed attuatori - Art. n. 30a
AHU-5
ACTUATOR - AHU -6 IT. No.
Unità di trattamento aria per ricircolo con sensori ed attuatori - Art. n. 30b
AHU-6
ACTUATOR - AHU -7 IT. No.
Unità di trattamento aria per ricircolo con sensori ed attuatori - Art. n. 30c
AHU-7
COMPLETE SUPPLY AND RETURN AIR DUCTWORKS FOR AIR
HANDLING UNITS AHU-1 , AHU-2, AHU-5, AHU-6, AHU-7 IT. No.
Unità di Reti complete di canalizzaizoni di mandata e ripresa aria Art. n. 31 per le unità AHU-1, AHU-2, AHU-5, AHU-6, AHU-7
FANCOIL UNIT FOR CEILING INSTALLATION COMPLETE OF
DUCTWORKS, PIPEWORK, CONTROLS - FC-1 IT. No.
Ventilconvettore per installazione pensile completo di Art. n. 32a canalizzaizoni, tubazioni e controlli - FC-1
FANCOIL UNIT FOR CEILING INSTALLATION COMPLETE OF
DUCTWORKS, PIPEWORK, CONTROLS - FC-2 IT. No.
Ventilconvettore per installazione pensile completo di Art. n. 32b canalizzaizoni, tubazioni e controlli - FC-2
FANCOIL UNIT FOR FALSE CEILING INSTALL. COMPLETE OF
DUCTWORKS, PIPEWORK, CONTROLS - FC-1 IT. No.
Ventilconvettore per installazione in controsoffitto completo di Art. n. 33a canalizzaizoni, tubazioni e controlli - FC-1
DUCTWORKS, PIPEWORK, CONTROLS - FC-2 IT. No.
Ventilconvettore per installazione in controsoffitto completo di Art. n. 33b canalizzaizoni, tubazioni e controlli - FC-2
FOR OFFICIAL USE ONLY Sheet 7 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
DUCTWORKS, PIPEWORK, CONTROLS - FC-3 IT. No.
Ventilconvettore per installazione in controsoffitto completo di Art. n. 33c canalizzaizoni, tubazioni e controlli - FC-3
FANCOIL UNIT 6V COMPLETE OF DUCTWORKS, PIPEWORK,
CONTROLS - FC-2 IT. No.
Ventilconvettore a 6V completo di canalizzaizoni, tubazioni e Art. n. 34a controlli - FC-2
FANCOIL UNIT 6V COMPLETE OF DUCTWORKS, PIPEWORK,
CONTROLS - FC-3 IT. No.
Ventilconvettore a 6V completo di canalizzaizoni, tubazioni e Art. n. 34b controlli - FC-3
DEDICATED HVAC FOR BATT ROOM W/ AHU-4, EF-4 ATEX
TYPE , DUCTWORK, PIPEWORK, CONTROL & FITTINGS IT. No.
Impianto HVAC dedicato per la Battery Room completo di AHU-4, Art. n. 35 EF-4 atex, canali, tubazioni, controlli ed accessori.
DEDICATED HVAC FOR LOX ROOM W/ AHU-3, EF-3 ATEX
TYPE , DUCTWORK, PIPEWORK, CONTROL & FITTINGS IT. No.
Impianto HVAC dedicato per la Battery Room completo di AHU-3, Art. n. 36 EF-3 atex, canali, tubazioni, controlli ed accessori.
MAIN HOT / CHILLED PIPEWORK FROM MECH ROOM 14
INCLUDING PIPES, INSULATION, CONVER & FITTINGS IT. No.
Reti principali acqua calda/refrigerata dalla Mech Room 14 Art. n. 37 comprensive di tubi, isolamenti, rivestimenti ed accessori.
DX UNIT FOR ROOM 33 IT. No.
Unità ad espansione diretta per il locale 33 Art. n. 38
HOT WATER PIPEWORK FROM ROOM 14 TO H. BAY HEAT
EXCHANGER W/ PIPES, INSULATION, CONVER & FITTINGS IT. No.
Circuito acqua calda dalla Mech Room 14 allo scambiatore area Art. n. 39 Bay inclusi tubi, isolamenti, rivestimenti ed accessori.
COMPLETION OF MECHANICAL CONTROL SYSTEM - DDC
TYPE - INCLUDING SENSORS, CONTROLLER AND FITTINGS IT. No.
Completamento del di controllo dell'impianto meccanico - Tipo Art. n. 40 DDC - Completo di sensori, attuatori, regolatori ed accessori
CONDENSATE DRAIN SYSTEM MAIN PIPELINES IT. No.
Tubazioni principali del sistema di raccolta della condensa Art. n. 41 LS/AC
TESTING; ADJUSTING AND BALANCING OF THE HVAC IT. No. SYSTEMS 42 Prove, tarature e bilanciamento impianti HVAC Art. n.
IIIb Plumbing system / IIIb Impianto Idraulico
FOR OFFICIAL USE ONLY Sheet 8 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
PORTABLE EYEWASH W/ FITTINGS - WALL MOUNTED IT. No.
Lavaocchi portatile con accessori - Montato a parete Art. n. 43 LS/AC
UPGRADING POTABLE WATER AND COMPRESSED AIR
CONNECTION POINTS IN THE SHOP AREA IT. No.
Modifiche ai punti di prelievo acqua potabile ed aria compressa Art. n. 44 nell'area delle officine
NEW COMPRESSED AIR LINE IN BAY AREA IT. No.
Nuova linea aria compressa nell'area BAY Art. n. 45
RELOCATION OF COMPRESSED AIR EQUIPMENTS IT. No. Modifiche ai punti di prelievo acqua potabile ed aria compressa 46 nell'area delle officine Art. n.
RELOCATION OF EXISTING FOAM CONCENTRATE TAN K AND
BLADDER REPLACEMENT IT. No.
Spostamento dell'esistente serbatoio della schiuma e sostituzione Art. n. 47 della membrana
FOAM GENERATOR REPAIR IT. No.
Riparazione generatore di schiuma Art. n. 48 LS/AC
TOTAL PART III / Totale Parte III
FOR OFFICIAL USE ONLY Sheet 9 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REPAIR WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici
NEW 4P-250 A CIRCUIT BREAKER IN 400V MDP IT. No.
Nuovo interruttore 4P-250 A nel MDP a 400 V Art. n. 1 EA / No
A/C PANEL IT. No.
Quadro elettrico per A/C Art. n. 2 EA / No
A/C SYSTEM DISTRIBUTION IT. No.
Distribuzione impianto A/C Art. n. 3 LS / AC
COMPRESSOR SYSTEM DISCONNECT SWITCH IT. No.
Sezionatore impianto aria compressa Art. n. 4 EA / No
LIGHTING FIXTURE REINSTALLATION AND ADJUSTMENT IT. No.
Reinstallazione e modifica elementi illuminanti Art. n. 5 LS / AC
TOTAL PART IV - Totale Parte IV
REPAIR WORKS SUMMARY / Riepilogo Lavori di Ristrutturazione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK
PART III - MECHANICAL WORK
PART IV - ELECTRICAL WORK
TOTAL PRICE / Costo Totale
OR US DOLLARS (RATE 1$ = 0.7452€)
FOR OFFICIAL USE ONLY Sheet 10 of 22 PREVIOUS EDITION IS OBSOLETE
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANHOUR
S
MANDAYS
(6)
AVERAGE
B. SUSTAIN WORK / Lavori di Manutenzione
PART I - DEMOLITIONS, EXCAVATIONS AND REMOVALS / Parte I - Demolizioni, Scavi e Rimozioni
Ia Architectural - Ia Architettura
REMOVAL OF WOOD DOORS IT. No.
Rimozione di porte in legno Art. n. 1 EA/NO
REMOVAL OF METAL DOORS IT. No.
Rimozione di porte in metallo Art. n. 2 EA/NO
REMOVAL OF METAL WINDOWS W/INSECT SCREEN IT. No.
Rimozione di finestre in metallo con rete antinsetto Art. n. 3 EA/NO
REMOVAL OF WINDOW METAL GRATE IT. No.
Rimozione di grate metalliche finestre Art. n. 4 KG
REM. OF 10X20cm GRES TILE FLOOR W/SETT.BED IT. No.
Rimozione di pavimento in gres 10x20 cm incluso massetto Art. n. 5 SM/MQ
REMOVAL OF CERAMIC BASEBOARD IT. No.
Rimozione di zoccolino in ceramica Art. n. 6 LM/ML
REMOVAL OF METAL WAINSCOTING IT. No.
Rimozione di rivestimento metallico Art. n. 7 SM/MQ
REMOVAL OF RUBBER/PAINT FLOOR INCL. SETTING BED IT. No.
Rimozione di pavimento in gomma/resina incluso massetto di posa Art. n. 8
SM/MQ
DEMOLITION OF GYPSUM BOARD PARTITIONS IT. No.
Demolizione di tramezzo in pannelli di gesso Art. n. 9 SM/MQ
REMOVAL OF SUSPENDED CEILING IT. No.
Rimozione di controsoffitto Art. n. 10 SM/MQ
REMOVAL OF MEMBRANE ROOFING, INCL. THERMAL
INSULATION AND SLOPING BED IT. No.
Rimozione di impermeabilizzazione in copertura, incluso isolamento Art. n. 11 termico e massetto pendenze
REMOVAL OF METAL FLASHING IT. No.
Rimozione di scossalina metallica Art. n. 12 LM/ML
REMOVAL OF EXTERNAL STEP, ROOM 016 IT. No.
Rimozione di gradino esterni Art. n. 13 EA/NO
PARTIAL DEMOLITION OF INTERIOR PLASTER IT. No.
Demolizione parziale di intonaci interni Art. n. 14 SM/MQ
PARTIAL DEMOLITION OF EXTERIOR PLASTER IT. No.
Parziale demolizione di intonaci esterni Art. n. 15 SM/MQ
DEMOLITION OF EXISTING METAL CANOPY IT. No.
Demolizione di tettoia metallica esistente Art. n. 16 LS/AC
DEMOLITION OF EXISTING COMM ROOM, ROOM No. 33 IT. No.
Demolizione del locale telecomunicazioni, locale n. 33 Art. n. 17 LS/AC
HANGAR BAY, CUTTING OF EXISTING INDUSTRIAL IT. No. PAVEMENT 18 Hangar, taglio di pavimentazione industriale Art. n.
LM/ML
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 11 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
HANGAR BAY, TRENCH EXCAVATION IN EXISTING CONCRETE
FLOOR FOR NEW CABLEDUCT IT. No.
Hangar, scavo in trincea in pavimentazione industriale in Art. n. 19 calcestruzzo per nuovo cavidotto
CU.M/MC
HANGAR BAY, INDUSTRIAL CEMENT FLOOR SHOOT IT. No. BLASTING 20 Hangar, pulizia meccanica pavimentazione industriale Art. n.
HANGAR BAY, SLIDING FRONT DOOR PANEL CUT FOR PASS
110x90 THRU DOOR INSTALLATION IT. No. 21 Hangar, taglio pannello portone scorrevole hangar per installazione portella 110x90
REMOVAL OF CEMENT ASBESTOS DOWNSPOUT ELBOW
Rimozione di raccordi in cemento amianto dei pluviali IT. No. 22 EA/NO
Total Architectural - Totale Architettura
Ib Structural Work - Ib Lavori Strutturali
Ic Civil Work - Ic Lavori Civili
Id Mechanical - Id Meccanico
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 12 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
Ie Electrical - Ie Elettrico
REMOVAL INTERLOCKED OUTLETS INCLUDING WIRING IT. No. SYSTEM 23 Rimozione prese interbloccate compresi i collegamenti Art. n.
REMOVAL ITALIAN/USA TYPE OUTLETS INCLUDING WIRING IT. No. SYSTEM 24 Rimozione prese tipo italiano/USA compresi i collegamenti Art. n.
REMOVAL ELECTRICAL PANELS IT. No.
Rimozione quadri elettrici Art. n. 25 LS/AC
REMOVAL OF WIRING SYSTEM FEEDING LIGHTING FIXTURES IT. No. Rimozione di collegamenti elettrici alimentanti i corpi illuminanti 26 esistenti Art. n.
REMOVAL OF TELECOMM OUTLETS INCLUDING WIRING IT. No. SYSTEM 27 Rimozione di prese telefoniche compresi i collegamenti Art. n.
REMOVAL OF TELECOMM RACK IT. No.
Rimozione armdi telefonici Art. n. 28 LS/AC
REMOVAL GROUNDING & LIGHTNING PROTECTION SYSTEM IT. No.
Rimozione impianti di terra e parafulmini Art. n. 29 LS/AC
REMOVAL AND REINSTALL OF FIRE DETECTION EQUIPMENT IT. No.
Rimozione e reinstallazione di apparecchiature rilevazione incendi Art. n. 30
REMOVAL OF OUTDOOR LIGHTING FIXTURES INCLUDING IT. No. WIRING SYSTEM 31 Rimozione dei corpi illuminanti esterni compresi i collegamenti Art. n.
Total Electrical - Totale Elettrico
TOTAL PART I / Totale Parte I
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 13 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK / Parte II - Lavori Architettonici, Strutturali e Civili
IIa Architectural - IIa Architettonico
30x30 CM GRANITE CERAMIC TILE FLOOR, INCL SETT. BED IT. No.
Pavimento in piastrelle di granito ceramico 30x30, incl. massetto Art. n. 1
GRANITE CERAMIC COVE BASE IT. No.
Zoccolino in granito ceramico Art. n. 2 LM/ML
EPOXY RESIN ON INDUSTRIAL FLOOR IN ANNEX AREA IT. No. Applicazione di resina epossidica su pavimento industriale nelle 3 aree di supporto. Art. n.
RUBBER COVE BASE IT. No.
Zoccolino in gomma Art. n. 4 LM/ML
RUBBER FLOOR SETTING BED IT. No.
Letto di posa pavimento in gomma Art. n. 5 SM/MQ
MINERAL FIBER PANEL SUSPENDED CEILING IT. No.
Controsoffitto in pannelli di fibra minerale Art. n. 6 SM/MQ
PAINT INTERIOR SURFACES WITH WATER ENAMEL IT. No.
Pitturazione con idropittura lavabile delle superfici interne Art. n. 7 SM/MQ
PAINT INTERIOR CEILING IT. No.
Pitturazione a tempera dei soffitti Art. n. 8 SM/MQ
PAINT EXTERIOR SURFACES WITH WATER ENAMEL IT. No.
Pitturazione con idropittura lavabile delle superfici esterne Art. n. 9 SM/MQ
INTERIOR PLASTER IT. No.
Intonaco interno Art. n. 10 SM/MQ
EXTERIOR PLASTER IT. No.
Intonaco esterno Art. n. 11 SM/MQ
240x220cm REI120 STEEL DOORS, Di1 Type IT. No.
Porta in acciaio 240x220 REI120, tipo Di1 Art. n. 12a EA/NO
120x220cm REI120 STEEL DOORS, Di2 Type IT. No.
Porta in acciaio 120x220 REI120, tipo Di2 Art. n. 12b EA/NO
150x250cm REI120 STEEL DOORS, Di3 Type IT. No.
Porta in acciaio 150x250 REI120, tipo Di3 Art. n. 12c EA/NO
220x250cm REI120 STEEL DOORS, Di4 Type IT. No.
Porta in acciaio 220x250 REI120, tipo Di4 Art. n. 12d EA/NO
90x215cm REI120 STEEL DOORS, Di5 Type IT. No.
Porta in acciaio 90x215 REI120, tipo Di5 Art. n. 12e EA/NO
100x220 INTERIOR WOOD DOOR, Di6 Type IT. No.
Porte interne in legno 100x220, tipo Di6 Art. n. 13a EA/NO
170x210 INTERIOR WOOD DOOR, Di7 Type IT. No.
Porte interne in legno 170x210, tipo Di7 Art. n. 13b EA/NO
80x210 INTERIOR WOOD DOOR, Di8 Type IT. No.
Porte interne in legno 80x210, tipo Di8 Art. n. 13c EA/NO
100x210 INTERIOR WOOD DOOR, Di9 Type IT. No.
Porte interne in legno 100x210, tipo Di9 Art. n. 13d EA/NO
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 14 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
100x230 INTERIOR WOOD DOOR, Di10 Type IT. No.
Porte interne in legno 100x230, tipo Di10 Art. n. 13e EA/NO
70x220 INTERIOR STEEL DOOR, Di11 Type IT. No.
Porte interne in acciaio 70x220, tipo Di11 Art. n. 14 EA/NO
190x265 EXTERIOR ALUMINUM DOOR, De1 Type IT. No.
Porte esterne in alluminio 190x265, tipo De1 Art. n. 15 EA/NO
150x225 EXTERIOR STEEL DOOR, De2 Type IT. No.
Porte esterne in acciaio 150x225, tipo De2 Art. n. 16a EA/NO
100x215 EXTERIOR STEEL DOOR, De3 Type IT. No.
Porte esterne in acciaio 100x215, tipo De3 Art. n. 16b EA/NO
110x230 EXTERIOR STEEL DOOR, De4 Type IT. No.
Porte esterne in acciaio 110x230, tipo De4 Art. n. 16c EA/NO
140x220 EXTERIOR STEEL DOOR, De5 Type IT. No.
Porte esterne in acciaio 140x220, tipo De5 Art. n. 16d EA/NO
190x220 EXTERIOR STEEL DOOR, De6 Type IT. No.
Porte esterne in acciaio 190x220, tipo De6 Art. n. 16e EA/NO
100x220 EXTERIOR STEEL DOOR, De7 Type IT. No.
Porte esterne in acciaio 100x220, tipo De7 Art. n. 16f EA/NO
315x270 ROLLING UP EXTERIOR DOOR, De8 Type IT. No.
Portone esterno a saracinesca 315x270, tipo De8 Art. n. 17 EA/NO
155x150cm ANDZ. ALUM. WINDOW , F1 Type IT. No.
Finestra in alluminio anodiz., 155x155 cm, tipo F1 Art. n. 18a EA/NO
115x155cm ANDZ. ALUM. WINDOW , F2 Type IT. No.
Finestra in alluminio anodiz., 115x155 cm, tipo F2 Art. n. 18b EA/NO
140x150cm ANDZ. ALUM. WINDOW , F3 Type IT. No.
Finestra in alluminio anodiz., 140x150 cm, tipo F3 Art. n. 18c EA/NO
220x155cm ANDZ. ALUM. WINDOW , F4 Type IT. No.
Finestra in alluminio anodiz., 220x155 cm, tipo F4 Art. n. 18d EA/NO
100x125cm ANDZ. ALUM. WINDOW , F5 Type IT. No.
Finestra in alluminio anodiz., 100x125 cm, tipo F5 Art. n. 18e EA/NO
Dia. 130cm ANDZ. ALUM. WINDOW , F6 Type IT. No.
Finestra in alluminio anodiz., dia 130 cm, tipo F6 Art. n. 18f EA/NO
140x140cm ANDZ. ALUM. WINDOW , F7 Type IT. No.
Finestra in alluminio anodiz., 140x140 cm, tipo F7 Art. n. 18g EA/NO
215x270cm ANDZ. ALUM. WINDOW , F8 Type IT. No.
Finestra in alluminio anodiz., 215x270 cm, tipo F8 Art. n. 18h EA/NO
165x155cm ANDZ. ALUM. WINDOW , F9 Type IT. No.
Finestra in alluminio anodiz., 165x155 cm, tipo F9 Art. n. 18i EA/NO
105x95cm ANDZ. ALUM. WINDOW , F10 Type IT. No.
Finestra in alluminio anodiz., 105x95 cm, tipo F10 Art. n. 18j EA/NO
140x800cm ANDZ. ALUM. WINDOW , F11 Type IT. No.
Finestra in alluminio anodiz., 140x80 cm, tipo F11 Art. n. 18k EA/NO
117x143cm ANDZ. ALUM. WINDOW , F12 Type IT. No.
Finestra in alluminio anodiz., 117x143 cm, tipo F12 Art. n. 18l EA/NO
GLAZING PANEL REPLACEMENT IT. No.
Sostituzione pannelli vetrati Art. n. 19 SM/MQ
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 15 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
EXTERNAL STEPS REPAIR IT. No.
Ripristino gradini esterni Art. n. 20 LS/AC
8/10 MM ALLMINUM FLASHINGS IT. No.
Scossaline in alluminio da 8/10mm Art. n. 21 LM/ML
NEW ROOFING IT. No.
Nuovo pacchetto di copertura Art. n. 22 SM/MQ
25CM THICK LOAD BEARING WALL IT. No.
Muro porttante, spessore 25cm Art. n. 23 SM/MQ
CEILING CORRUGATED STEEL SLAB IT. No.
Solaio di copertura in lamiera grecata Art. n. 24 SM/MQ
HANGAR BAY CEMENT FLOOR REPAIR IT. No.
Ripristino pavimentazione in cemento hangar Art. n. 25 SM/MQ
HANGAR BAY CEMENT FLOOR SURFACE TREATMENT IT. No.
Trattamento superficiale pavimentazione in cemento hangar Art. n. 26 SM/MQ
100x100CM PASS THRU SERVICE DOOR AT HANGAR DOOR IT. No.
Portella di servizio 100x100cm nel potone scorrevole hangar Art. n. 27
STEEL LADDER FOR ROOF ACCESS IT. No.
Scale metalliche per accesso in copertura Art. n. 28 KG
SAFETY GLVD STEEL RAILING IT. No.
Ringhiera di sicurezza in acciaio zincato Art. n. 29 KG
180x80cm RECESSED COCCO MAT, ROOM 012 IT. No.
Zerbino incassato in cocco 180x80cm, locale 012 Art. n. 30 EA/NO
WALL MOUNTEDELECTROMAGNETIC DOOR HOLDERS IT. No.
Fermi elettromagnetici montati a parete Art. n. 31a EA/NO
FLOOR MOUNTED ELECTROMAGNETIC DOOR HOLDERS IT. No.
Fermi elettromagnetici montati a pavimento Art. n. 31b EA/NO
DOOR HOLDERS ANCHOR SYSTEM IT. No.
Ancora per fermi elettromagnetici Art. n. 31c EA/NO
HDPE DOWNSPOUT ELBOWS, INCL. SURFACES REPAIR IT. No.
Raccordi pluviali in PEAD, incluso ripristino superfici Art. n. 32 EA/NO
REI120 PARTITION WALL, ROOM 009. INCL. CEILING IT. No.
Tramezzo Rei120, locale 009. Incluso soletta di chiusura Art. n. 33 LS/AC
OVERHEAD DOOR REPAIR, ROOM 008 IT. No.
Riparazione portone sezionale, locale 008 Art. n. 34 LS/AC
Total Architectural - Totale architettonico
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 16 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
IIb Structural Work - IIc Lavori Strutturali
IIc Civil Work - IIc Lavori Civili
TOTAL PART II / Totale Parte II
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 17 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
PART III - MECHANICAL WORK / Parte III - Lavori Meccanici
PART IV- ELECTRICAL WORK / Parte VI - Lavori Elettrici
SONIC BIRD CONTROL SYSTEM IT. No.
Dissuasore sonoro allontanamento volatili Art. n. 1 LS/AC
NEW CABLES FEEDING NEW ELECTRICAL PANELS
3x1x70+35N+35PE IT. No.
Nuovi cavi alimentanti i nuovi quadri elettrici Art. n. 2a 3x1x70+35N+35PE
3x1x70+35N+35PE IT. No.
Nuovi cavi alimentanti i nuovi quadri elettrici Art. n. 2b
3x1x95+50N+50PE IT. No.
Nuovi cavi alimentanti i nuovi quadri elettrici Art. n. 2c 3x1x95+50N+50PE
3x1x120+70N+70PE IT. No.
Nuovi cavi alimentanti i nuovi quadri elettrici Art. n. 2d 3x1x120+70N+70PE
3x1x95+50N+50PE IT. No.
Nuovi cavi alimentanti i nuovi quadri elettrici Art. n. 2e 3x1x95+50N+50PE
3x1x70+35N+35PE IT. No.
Nuovi cavi alimentanti i nuovi quadri elettrici Art. n. 2f
500x150 CABLE TRAY IT. No.
Canaletta 500x150 Art. n. 2g LM/ML
100x75 CABLE TRAY IT. No.
Canaletta 100x75 Art. n. 2h LM/ML
NEW 4P-250A CIRCUIT BREAKER IT. No.
Nuovo interruttore 4P-250A Art. n. 3 EA/NO
NEW ELECTRICAL PANELS A AND B - PANEL A IT. No.
Nuovi quadri elettrici A e B - Quadro A Art. n. 4a EA/NO
NEW ELECTRICAL PANELS A AND B - QUADRO B IT. No.
Nuovi quadri elettrici A e B - Quadro B Art. n. 4b EA/NO
NEW ELECTRICAL PANELS C AND D - PANEL C IT. No.
Nuovi quadri elettrici C e D - Quadro C Art. n. 5a EA/NO
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 18 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
NEW ELECTRICAL PANELS C AND D - PANEL D IT. No.
Nuovi quadri elettrici C e D - Quadro D Art. n. 5b EA/NO
NEW ELECTRICAL PANEL HBOP IT. No.
Nuovo quadro elettrico HBOP Art. n. 6 EA/NO
NEW ZONE OUTLET PANEL IT. No.
Nuovo quadro prese di zona Art. n. 7 EA/NO
NEW INTERLOCKED OUTLETS IT. No.
Nove prese interbloccate Art. n. 8 EA/NO
NEW IDIGITAL MULTI-METER IT. No.
Novo Multimetro Digitale Art. n. 9 EA/NO
NEW OUTLETS ITALIAN STYLE IT. No.
Nuove prese tipo Italiano Art. n. 10 EA/NO
NEW OUTLETS USA STYLE IT. No.
Nuove prese tipo USA Art. n. 11 EA/NO
NEW GROUND FAULT OUTLETS IT. No.
Nuove prese con differenziale Art. n. 12 EA/NO
TWO SECTION 195x65 FLOOR BASE CHANNEL IT. No.
Canalina battiscopa a due scomparti 195x65 Art. n. 13 LM/ML
CIVIL OUTLET POINT IT. No.
Punto presa civile Art. n. 14 EA/NO
LIGHTING POINT IT. No.
Punto luce Art. n. 15 EA/NO
UPGRADING EXISTING 10% LIGHTING FIXTURES IT. No.
Revisione 10% corpi illuminanti esistenti Art. n. 16 LS/AC
NEW CABLES FEEDING NEW INTERLOCKED OUTLETS, 5x16 IT. No.
Nuovi cavi alimentanti le prese interbloccate, 5x16 Art. n. 17a
NEW CABLES FEEDING NEW INTERLOCKED OUTLETS, 5x6 IT. No.
Nuovi cavi alimentanti le prese interbloccate, 5x6 Art. n. 17b LM/ML
NEW CABLES FEEDING NEW INTERLOCKED OUTLETS, 3x6 IT. No.
Nuovi cavi alimentanti le prese interbloccate, 3x6 Art. n. 17c LM/ML
NEW 2X36 W LIGHTING FIXTURES IT. No.
Nuovi corpi illuminanti 2x36 W Art. n. 18 EA/NO
NEW 4X18 W LIGHTING FIXTURES IT. No.
Nuovi corpi illuminanti 4X18 W Art. n. 19 EA/NO
NEW LED TYPE OUTDOOR FLOODLIGHTS IT. No.
Nuovi proiettori da esterno a LED Art. n. 20 EA/NO
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 19 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - SUSTAIN WORKS
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
S
MANDAYS
(6)
AVERAGE
NEW COMMUNICATION OUTLETS IT. No.
Nuove prese per comunicazioni Art. n. 21 EA/NO
NEW COMMUNICATION POINT IT. No.
Nuovo punto per comunicazioni Art. n. 22 EA/NO
NEW COMMUNICATION RACK - MAIN RACK IT. No.
Nuove Armadio per comunicazioni - Rack Principale Art. n. 23a EA/NO
NEW COMMUNICATION RACK - TR1 IT. No.
Nuove Armadio per comunicazioni - TR1 Art. n. 23b EA/NO
NEW COMMUNICATION RACK - TR2 IT. No.
Nuove Armadio per comunicazioni - TR2 Art. n. 23c EA/NO
NEW COMMUNICATION RACK - OPTIC FIBER CABLE IT. No.
Nuove Armadio per comunicazioni - Cavi Fibra Ottica Art. n. 23d LM/ML
NEW WIFI ACCESS POINT - OFFICES IT. No.
Nuovi punti di accesso WIFI - Uffici Art. n. 24a LS/AC
NEW WIFI ACCESS POINT - HANGAR BAY IT. No.
Nuovi punti di accesso WIFI - Area hangar Art. n. 24b LS/AC
NEW WIFI ACCESS POINT - OUTDOOR IT. No.
Nuovi punti di accesso WIFI - Esterno Art. n. 24c LS/AC
TEMPERATURE CONTROL PANEL IT. No.
Quadro controllo temperatura Art. n. 25 LS/AC
ELECTROMAGNETIC HOLDERS CONNECTIONS IT. No.
Collegamenti degli elettromagneti Art. n. 26 LS/AC
NEW LPS SYSTEM IT. No.
Nuovo impianto LPS Art. n. 27 LS/AC
ELECTRICAL SYSTEMS TESTS IT. No.
Collaudo Impianti Elettrici Art. n. 28 LS/AC
TELECOMM SYSTEM TESTS IT. No.
Collaudo Impianto Telefonico Art. n. 29 LS/AC
TOTAL PART IV - Totale Parte IV
SUSTAIN WORKS SUMMARY / Riepilogo Lavori di Manutenzione
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK
FOR OFFICIAL USE ONLY PREVIOUS EDITION IS OBSOLETE Sheet 20 of 22
CONTRACT FOR (Work to be performed)
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY
PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST NUMBER PROJECT NUMBER
ASHE 09-1031
MANDAYS
(6)
AVERAGE
A. REPAIR WORKS / Lavori di Ristutturazione
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK
PART III - MECHANICAL WORK
SUB TOTAL A.
B. SUSTAIN WORKS / Lavori di Manutenzione
PART II - ARCHITECTURAL, STRUCTURAL AND CIVIL WORK
SUB TOTAL B.
PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 21 of 22
RESTORE HANGAR 1 BLDG 921, AREA F, AVIANO AB, ITALY - REV 1
INSTRUCTIONS FOR COMPLETING AF FORM
Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards-SY, cubic yards-CY, square feet- SF, linear feet-LF, board feet-BF, each-EA,, pound-LB).
Col 3 Quantity. Contractor's estimated of quantity required in terms of unit of measure (column 2). Item and units of measure will be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issued.
Otherwise, the contractor is responsible for determining quantity estimates.
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (Col 5) for item listed in column 1.
Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 the average rate per manhour (manday) and in col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1), which are special to the contract and of significant dollar value.
Col 10 Line. Self-explanatory.
Note: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on the last page as follows:
TOTAL MATERIAL COSTS
A
REPAIR B
. SUSTAIN
TOTAL A+B (€)
TOTAL LABOR COSTS
TOTAL OTHER DIRECT COSTS
TOTAL DIRECT COSTS € € €
OVERHEAD % € € €
SUBTOTAL € € €
PROFIT % € € €
TOTAL PRICE € € €
DATE FIRM NAME
TITLE BY
INSTRUCTIONS TO OFFERORS
1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and estimated costs, (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from this proposal, the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data (see ASPR 3-807.3 and 3-807.4).
2. In addition to the specific information required by this form, the offeror is experted, in good faith, to incorporate in and submit with this form any additional data, supporting schedules, or substation which are reasonably required for the conduct of an appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clean understanding of:
a. The existing, verifiable data.
b. The judgmental factors applied in projecting from know data to the estimate, and
c. The contingencies used by the offeror in his proposed price.
In short, the offeror's estimating process itself needs to be disclosed.
3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate) and made available to the contracting officer or his authorized representative upon request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any negotiations prior to contract award.
PREVIOUS EDITION IS OBSOLETE FOR OFFICIAL USE ONLY Sheet 22 of 22
| FOR OFFICIAL USE ONLY |
| FOR OFFICIAL USE ONLY |
| INSTRUCTIONS FOR COMPLETING AF FORM |
| INSTRUCTIONS TO OFFERORS |
File details come from the government source that posted it. Updated .