Internal Air Transport Certification Summary

This is an Internal Air Transport Certification document issued by the Air Force on 19 April 2012 for the Eagle EB2-5 Flightline Tow Tractor Bobtail. The certification upgrades the item from temporary one-time approval to full-time air transport certification. The vehicle has dimensions of 216" L x 96" W x 82" H, with a gross vehicle weight of 11,400 lbs and a gross vehicle weight rating (GVWR) of 13,000 lbs. The front axle is rated at 4,850 lbs and the rear axle at 9,750 lbs. The Eagle EB2-5 is certified for air transport on USAF C-130, C-17, and C-5 aircraft.

Maximum transport weight is 13,000 lbs with sleeper shoring required. Front axle limits are 3,880 lbs without sleeper shoring or 4,850 lbs with it; rear axle limits are 7,800 lbs without shoring or 9,750 lbs with it. Item preparation requires approach shoring and potentially sleeper shoring, provided by the shipper. All equipment must be prepared to withstand aircraft environmental extremes per MIL-STD-810, and hazardous materials (fuel, batteries) must be certified per TM 38-250/AFMAN 24-204(I). Loading procedures follow respective aircraft cargo loading manuals with specific shoring requirements for each aircraft type: C-5 forward ramp loading with forward kneel configuration, C-17, and C-130. Restraint must meet MIL-HDBK-1791 requirements of 3G forward, 1.5G aft and lateral, and 2G up, with 4.5G down load capability. The point of contact is Brian Herriott at Brian.Herriott@wpafb.af.mil or ATTLA@wpafb.af.mil, DSN 986-9954, with reference to file number 2010.08.19 Rev 1.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Internal Air Transport Certification

ASC/ENFC (ATTLA)

2145 Monahan Way

WPAFB, OH 45433-7017

https://afkm.wpafb.af.mil/AirTransport

Date: 19 April 2012 Item Nomenclature: Eagle EB2-5 Flightline Tow Tractor Bobtail File Number: 2010.08.19 Rev 1 Requestor: Global Hawk, WR-ALC/GRCAC (Timothy Foley) Superseded Certification Date: 26 Aug 2010

New Information Summary: Converted from a temporary one-time approval to a full time air transport certification.

Item Description: The subject item is identified to be an Eagle EB2-5 Flightline Tow Tractor Bobtail.

Its approximate dimensions are 216” L x 96“ W x 82” H. The vehicle gross weight is reported to be 11,400 lbs with a gross vehicle weight rating (GVWR) of 13,000 lbs. Axle weights were not reported.

The front axle has a rating of 4,850 lbs. The rear axle has a rating of 9,750 lbs.

Figure 1: Eagle EB2-5 Flightline Tow Tractor Bobtail

Certified Aircraft: USAF C-130, C-17 and C-5

Conditions of Certification:

1. Maximum Weight for Air Transport:

a. Gross Vehicle Weight: 13,000 lbs (sleeper shoring required, see paragraph 5 for dimensions).

(1) Front Axle – 3,880 lbs (without sleeper shoring) – 4,850 lbs (with sleeper shoring)

(2) Rear Axle – 7,800 lbs (without sleeper shoring) – 9,750 lbs (with sleeper shoring)

2. Item Preparation:

a. Approach shoring is required. Sleeper shoring might be required as per paragraph 1.a.

Shipper shall provide all shoring.

File Number 2010.08.19 Rev 1

b. All equipment shall be prepared, packaged, or mounted such that there is no adverse effect on the functioning of the equipment after being subjected to the aircraft environmental extremes. MIL- STD-810 provides guidance on approved test methods and data gathering techniques.

c. All hazardous materials (to include fuel level, batteries, etc.) must be prepared and certified for airlift in accordance with TM 38-250/AFMAN 24-204(I). Do not consider this air transport certification as approval for hazardous materials. Authorization for airlifting hazardous material is the responsibility of 401 SCMS/GUMAA (DSN 787-4503 or COM (937) 257-4503).

3. Loading Instructions:

a. The vehicle can be loaded using general loading procedures as listed in the respective aircraft cargo loading manual.

b. C-5: Load the vehicle over the forward ramp with the aircraft in the forward kneel configuration.

c. Approach shoring is required. See paragraph 5 for dimensions. (Will not be required if item is being loaded straight into the cargo compartment via K-loader).

d. Sleeper shoring shall be placed under the frame near the axles (2 stacks each axle) if required per paragraph 1.a.

4. Restraint Requirements: The Eagle EB2-5 Flightline Tow Tractor Bobtail and all accompanying cargo must be restrained to meet MIL-HDBK-1791 requirements of 3G forward, 1.5G aft and lateral, and 2G up. In addition, stored or installed equipment must meet these requirements and be capable of withstanding a 4.5G down load. Restraint may be applied using largest frame components, preferably at longitudinal main frames adjacent to lateral cross members. Restraint may be applied to axles up to their rated capacity in longitudinal and lateral directions as listed in the Item Description paragraph. Do not apply more than 50% of required restraint to vehicle axles for longitudinal and lateral directions.

Note that spring mounted axles provide zero vertical restraint. The Pintle hook is rated at 9,750 lbs for longitudinal restraint only.

5. Required Shoring Dimensions & Diagrams:

a. Approach shoring: minimum recommended dimensions for 9˚ approach angle, requirements for other configurations are in the applicable aircraft loading manual.

C-5 Forward Shoring (Forward Kneel) Pedestal Shoring “A” 16” L x 13” W x 4” H (2 each inboard) 18” L x 15” W x 4” H (2 each outboard) “B” 15” L x 15” W x 10” H (4 each) Approach Shoring “C” 92” L x 24” W x 13” H (2 required) (Ramp toe end shall be supported by the approach shoring – min 11” L)

(C-5) CAUTION: Width of approach shoring “C” in the area under the toe must be as wide as the ramp toe it is placed under. The remaining approach shoring extending away from the ramp toe extension contact point must be a minimum of 18 inches wide.

File Number 2010.08.19 Rev 1

C-17 Shoring Ramp Pedestal Shoring “A” 18” L x 30” W x 1” H Approach Shoring “B” 96” L x 24” W x 13” H (2 required)

C-130 Shoring Pedestal Shoring “A” 18” L x 18” W x 6” H Approach Shoring “B” 84” L x 24” W x 11” H (2 required)

b. Sleeper Shoring: Front axle 7” L x 7” W. Rear axle 10” L x 10” W. The sleeper shoring must be stacked to within ½” of chassis/frame area and secured with cargo straps.

Required Distribution:

1. Shipper shall give a copy of this certification to the ATOC representative when the item is presented for airlift. This memo shall be part of the official cargo manifest documentation package and shall be briefed to the aircraft loadmaster prior to loading this item.

2. AMC/A3V & AMC/A4T

Point of Contact: Brian Herriott, at Brian.Herriott@wpafb.af.mil or ATTLA@wpafb.af.mil, DSN 986- 9954 or Commercial (937) 656-9954. Refer to file number 2010.08.19 Rev 1 regarding this item.

Reviewed by: MARK A. KUNTAVANIS

Aerial Delivery Technical Expert Crew Systems Branch

Approved by: MARTIN J. ANDRIES Technical Advisor Crew Systems Branch

File details come from the government source that posted it. Updated .