Attachement - 3 Statement of Requirements Concrete Pad.pdf

PDF 472 KB Posted

Attached to
422 FSS RAF FAIRFORD CAFE
Solicitation number
FA557027Q0002
Issued by

About this file

This is a Statement of Requirements (SoR) for a construction project at RAF Fairford, a United States Air Force facility in the United Kingdom, issued by 422 CES/CEN (Engineering Flight).

The contractor must deliver a feasibility report followed by a 100% design package and fixed-price construction cost estimate to complete all pre-construction engineering, site clearance, pad foundation installation, and utility connections for a new single-story modular building that will serve as a community hub housing a library and café. Key requirements include comprehensive topographical and geotechnical surveys; intrusive and non-intrusive ground investigations; buried services tracing and CCTV drainage surveys; procurement of statutory utility records; detailed structural and drainage designs; earthworks and subbase engineering; installation of pad foundations, leveling piers, and perimeter skirting; construction of foul and storm water drainage networks; utility service trenches and ducts; water supply and electrical infrastructure delivery; and external landscaping and reinstatement. The contractor must ensure all BMS, control, and fire alarm panels are open-protocol design; provide all equipment, materials, and labor; complete a costed risk register approved by stakeholders before construction begins; and ensure compliance with all equipment and systems during the first 12 months of warranty, including all manufacturer-required Planned Preventative Maintenance tasks. The contractor accepts design liability for the 100% design package and any design changes arising during construction, and the USAF will not incur additional charges if follow-up work is required for compliance with design intent.

Work must comply with all UK Building Standards, US Standards (UFCs and AFIs), CDM Regulations 2015, and applicable codes including BS 7671:2022, EISA 2007, and UFC standards for fire protection, geotechnical engineering, water distribution, and wastewater treatment. The project is located at RAF Fairford near Gloucester, UK, as indicated by the aerial site map. The contractor must coordinate with 422 CES/CEN and submit a Program of Works at least two weeks before commencing work. All dig permits require AF Form 103 submission at least three weeks in advance; hot work permits must be requested at least one week prior. Base security clearance applications must be submitted at least six months in advance for unescorted access, and ACL (Access Control List) approval is required for all contractors and is valid for six months. The contractor bears all costs for contractor escorting and security compliance failures. All mechanical and electrical works must be performed by RAF Fairford-approved engineers with valid skilled person certificates. A Refurbishment & Demolition asbestos survey is required before work commences. Indicative working hours are Monday–Friday 0730–1700; any afterhours work, including work on American holidays, requires approval from base leadership at least two weeks in advance. The contractor must submit Risk Assessment & Method Statements (RAMS) at least one week before work commences, with all electrical RAMS approved by the electrical AP/AE. Environmental compliance requires waste transfer licenses and notices; tree removal must be approved by USAF and DIO environmental teams with replacement on a 2:1 basis (minimum 1.2 meters tall) and establishment care. Handover documentation includes DIO Form 140 and Form 141 O&M manuals with professionally organized binders containing product data, as-built drawings in AutoCAD (.dwg) format submitted within 30 days of project completion, and geospatial data in GIS format complying with SDSFIE standards, delivered via DoDSAFE. The contractor is encouraged to have the original Architect-Engineer complete as-built drawing work and must provide stakeholder training on equipment operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown. Design submissions require a two-week review period and a design review meeting; all design review drawing sets must be submitted as a combined PDF document labeled "Not for Construction" prior to the final bid set.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. General Description of Works

The project is to provide a feasibility report, then based upon the output of the report, an approved 100% design and firm price construction cost sufficient to complete all pre-construction engineering designs, managing site clearances, installing the pad foundation network, and delivering fully commissioned utility connections up to the building’s internal termination points.

2. Requirements

Project Objective The objective of this contract is to provide all pre-construction engineering, design, site preparation, substructure installation, and utility servicing required to fully facilitate the installation of a new, single storey modular building. Upon completion, the structure will function as a community hub housing a library and café.

The completed works must be fully compliant, structurally sound, fit for purpose, and ready for immediate modular building installation.

Pre-Construction, Design & Survey Requirements

• Complete all comprehensive topographical, boundary, and level surveys required to establish definitive datum points and dimensional accuracy for the modular building footprint.

• Execute all necessary intrusive and non-intrusive ground investigations including dynamic sampling, borehole testing, and trial pits, to produce a conclusive geotechnical report for the foundation design.

• Conduct all necessary soil sampling and Waste Acceptance Criteria (WAC) testing to accurately classify, manage, and legally dispose of all surplus excavated materials off site.

• Perform a comprehensive buried services trace, utility mapping exercise, and CCTV drainage connectivity survey to verify the exact location, condition, and capacity of all existing infrastructure.

• Procure all mandatory statutory utility records and secure all necessary technical approvals prior to the commencement of physical works.

• Produce a detail, and sign off on all comprehensive structural substructure designs, pad foundation layouts, and gravity fed drainage networks.

Earthworks & Sub-Base Engineering

• The Contractor is responsible for verifying all subsurface conditions and executing all earthworks required to achieve the necessary structural bearing capacity and final design levels.

• Strip and segregate all topsoil across the works footprint to a depth determined by the site investigations as necessary to reach a clean, load bearing subgrade.

• Execute all bulk excavations to the definitive depths required to achieve the final design formation levels, ensuring the removal of all structurally unsuitable subsoil.

• Dispose of all surplus excavated materials, inert waste, and site arisings to a licensed off site tipping facility.

• Supply and install a high-performance geotextile separation membrane over the entire prepared subgrade to prevent material migration and protect the structural integrity of the subbase.

• Supply, spread, and mechanically compact a granular subbase layer (utilizing Type 1 or equivalent engineered aggregate) to the precise thickness and density required to safely support all construction and operational design loads.

Substructures, Structural Foundations & Plant Bases

• Determine the exact dimensions, spacing, and depths of all structural pad foundation excavations for the modular building.

• Design, supply, and pour mass concrete to all structural foundation bases.

• Supply and install heavy duty levelling piers/paving slab details to the exact structural dimensions and heights required.

• Design, supply, and construct a dedicated, level, base engineered to support the dimensions and weight of the specified air conditioning condenser unit.

• Supply and install all necessary perimeter skirting, to finish the building perimeter and protect the underside of the modular structure.

Foul & Storm Water Drainage Networks

• Excavate all drainage trenches to the depths and gradients required to ensure continuous gravity flow. Supply and install all gravity fed uPVC pipework, fully encased in a compliant granular bed, surround, and backfill material.

• Supply and install robust plastic inspection chambers at all mandatory change of direction and junction points, finished to final ground levels with appropriate load rated access covers to suit the surrounding traffic profile.

• Supply and install all required rodding eyes, rainwater pipe access gullies, and system accessories to deliver a fully functional, maintenance accessible network.

• Survey, locate, and form secure gravity connections to the existing on site foul and storm water manholes.

• Undertake all mandatory air pressure testing on the entire new drainage network.

Ducts & Utility Service Trenches

• Excavate all utility service trenches to compliant statutory depths and widths. Prepare and lay a protective sand blinding layer prior to utility installation and safely backfill and compact upon completion.

• Supply and lay continuous, flexible, general purpose utility ducts within the prepared trenches.

Water & Electrical Infrastructure Delivery

• Supply and lay a continuous MDPE water supply pipe within the service trench, routing it safely into the building footprint and terminating it at the designated internal connection point.

• Execute all necessary alterations and physical connections to the existing live water network.

• Chlorinate, flush, and pressure test the new water infrastructure.

• Supply, manage and coordinate the complete installation, testing, and live commissioning of the new electrical supply and final utility connections.

External Landscaping & Reinstatement

• Spread, level, and smoothly grade all retained on site topsoil over all areas disturbed by the construction works, ensuring seamless integration with the surrounding untouched area.

• Supply and evenly sow a high-quality, hard-wearing grass seed mix across all reinstated topsoil areas to establish a uniform, visually acceptable grass finish.

General The Contractor is responsible to ensure:

• All BMS, Control and Fire Alarm panels are of “open” protocol design.

• The supply of all equipment, materials and labour required to complete the works.

• That all paperwork and guarantees are provided to the 422 CES/CEN (Engineering Flight) project lead, as per Section 12 of the SoR.

• Any damage to the surrounding area resulting from the works being carried out, is made good. i.e., material set down / storage areas, site cabins and compounds etc.

• All external areas which require ground works must be returned to a condition suitable for maintenance under the base ground’s maintenance contract.

• That all rubbish and debris generated by the project is cleared from site and disposed of in accordance with Section 10 of this SoR.

• A costed risk register must be completed and agreed with all stakeholders prior to any construction works commencing.

• Compliance of all equipment and systems installed as part of the project, during the first

12 months of the warranty period from date of handover. This shall include all Planned Preventative Maintenance (PPM’s) tasks that are required by the manufacture with the first 12-month period.

The contractor shall include for the procurement, supply, and delivery of any related equipment necessary to meet the project’s requirements. If follow up work is required for the works to be made compliant with the design’s intent, United States Air Force (USAF) shall not incur any additional charge.

Works must be carried out to best practice standards and in accordance with the current UK regulations and established codes of practice whether specifically mentioned or not.

The Contractor will accept design liability for the 100% design package supplied prior to construction, and any design changes that may arise throughout the construction period.

3. Site Information

This Statement of Requirement and all associated drawings and specifications that are provided to the contractor, are for information purposes only. The contractor shall assume all responsibility for the site verification required to successfully complete the design and subsequently the construction of the project. It is the contractor's responsibility to identify all the necessary design, site and infrastructure surveys in order to determine a firm/fixed price construction cost.

4. Constraints

The building or facility will remain in use throughout the works, unless specified in the contract documents as vacated during the period of works.

All Base security, access pass, and Base rules will apply. Base security clearance applications will need to be submitted at least 6 months in advance of required unescorted access on base.

ACL (Access Control List) approval will need to be submitted via DIO for all contractors on the job site and is only valid for 6 months from the date of application. The contractor should be aware that approval can take 1 month or more from date of application. The contractor must allow sufficient time for approval to be granted. Escorting of contractors not listed on ACL will be completed by the contractor; passes to be obtained daily from Gate 7.

The contractor should make allowances for all escorting requirements associated with the project.

USAF will not be responsible for any escorting requirements throughout the project.

USAF will not incur any financial costs if additional requirements are identified after the identified surveys have been conducted, unless the additional requirements are as a result in a change in scope requested by USAF.

A Refurbishment & Demolition (R&D) asbestos survey of the building will be required to identify any potential risk of asbestos exposure and allow for the correct abatement to be costed.

All Mechanical and Electrical (M&E) works must be carried out by RAF Fairford approved engineers with a valid skilled person certificate issued by the relevant AP (Authorised Person) for RAF Fairford.

Any delays or costs incurred by failure to comply with Base entry requirements, including (but not limited to) failure to provide adequate personal identification, use or conveyancing of prohibited items (weapons, illicit drugs, alcohol) will be borne by the contractor and will not impact project schedule or cost.

5. Standards

Contractor must comply with but not limited to:

All UK Building Standards.

All relevant US Standards UFC’s, AFI’s. See the Whole Building Design Guide for list of standards. https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc CDM Regulations 2015.

UFC 3-600-01, “Fire Protection Engineering for Facilities”, relevant NFPA and British

Standards.

DMG 8 (Design and Maintenance Guide) - Space Requirements for Plant Access, Operation &

Maintenance.

JSP 375 - Management of Health and Safety in Defence.

Spec 36 – Heating, Hot & Cold Water, Steam & Gas Installation Standards.

BS7671: 2022 - 18th Edition Wiring Regulations.

EISA2007 - Energy Independence & Security Act 2007.

UFC 1-200-01 (DoD Building Code General Requirements) UFC 3-220-01 (Geotechnical Engineering) BS EN 1997 (Eurocode 7) & BS 8004 UFC 3-510-01 (Foreign Language and Host Nation Compliance for Utilities):

PAS 128:2014: The British standard for underground utility detection. The contractor must use this to map existing base utilities, so they do not hit live lines during mass excavation.

UFC 3-230-01 (Water Storage and Distribution) UFC 3-240-01 (Wastewater Collection and Treatment) https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc

UK Building Regulations Approved Document H For Electrical & Sub-Mains (Section 7) UFC 3-520-01 (Interior Electrical Systems) BS 7671 (IET Wiring Regulations)

NOTE: Where UK and US standards conflict the most onerous standard must be adhered to.

6. Location of Work

7. Program/Coordination

The contractor must coordinate and gain approval from 422 CES/CEN before commencing work.

A Program of Works/Works Schedule must also be provided to 422 CES/CEN at least 2 weeks in advance of any work instigation, this is to allow all stakeholders time to review and grant approval.

If any base road closures are required as part of the project, a minimum of 3 weeks’ notice is required for 422 CES/CEN to notify leadership and gain approval.

All dig permits must be requested to 422 CES/CEN via an AF Form 103, a minimum of 3 weeks prior to the scheduled work commencing date. Permits are only valid for 30 calendar days, after this time they will require extending / renewing. Dig permit renewal must be requested a minimum of 2 weeks prior to the work commencing, it is the responsibility of the contractor to request any extension/renewal via 422 CES/CEN.

All hot works on base require a Hot Work Permit. The contractor should request a Hot Work Permit to the 422 CES/CEFP (Fire Prevention Inspector) & 422 CES/CEN project lead at least 1 week prior to works commencing. No hot work shall be undertaken unless a valid hot work permit has been issued by the Fire Prevention Inspector on base.

The contractor is responsible for timely coordination with the BMC (Base Maintenance Contractor) AP’s (Appointed Persons) for any works that require their approval/attendance.

Minimum of 20 business days’ notice is required for any AP attendance. AP requests must be submitted via the BMC’s AP request form which can be provided by 422 CES/CEN upon request.

The contractor shall be solely responsible for the proper coordination of all phases of the work and timely delivery to the site of all equipment and materials for proper execution of the work. Any temporary disruption or disconnection of existing services that will be necessary to carry out the works shall only be made at such time as is agreed in writing with RAF Fairford CE Operations.

Indicative Working Hours:

Monday – Friday 0730-1700 Saturday and Sunday – Weekend out-of-hours working subject to agreement.

Any afterhours work must be requested at least two weeks ahead of time and approved by base leadership. The CEN project manager can provide the form and will circulate the form for approval.

American Holidays/Family Days – American holidays are considered out-of-hours periods and work on American holidays will be subject to agreement. Additionally, a weekday before or after the American holiday may be classified as a Family Day. Work on a Family Day may limit access to the site. Work on Family Days shall be established through 422 CES/CEN prior to all works commencing.

American Holidays

• New Year’s Day January 1

• Martin Luther King’s Birthday 3rd Monday in January

• Washington’s Birthday 3rd Monday in February

• Memorial Day last Monday in May

• Juneteenth National Independence Day June 19

• Independence Day July 4

• Labor Day 1st Monday in September

• Columbus Day 2nd Monday in October

• Veterans’ Day November 11

• Thanksgiving Day 4th Thursday in November

• Christmas Day December 25

8. Asbestos

RAF Fairford has a current asbestos register which is held in 422 CES/CEIE (Environmental Department). Access to the register will be granted to the contractor for reference, but a R&D survey and risk assessment statements must be completed prior to all works commencing.

9. Health and Safety

The contractor shall provide all method statements and plans detailing health and safety proposals and must comply with JSP 375.

All RAMS (Risk Assessment & Method Statements) must be submitted for review at least 1 week prior to commencement of work to allow for acceptance. All electrical RAMS must be approved by the electrical AP/AE before any works commence.

10. Environmental & Waste

The contractor must issue all waste transfer licenses and all waste transfer notices which are associated with the project, to the appointed USAF project lead.

If any trees are to be removed as part of the project, this must be agreed with both USAF & DIO environmental teams prior to any removal. The contractor should allow for their replacement on a 2:1 basis, said trees should be a minimum of 1.2 meters tall, and allowance for future care & maintenance should be made until they have been established.

Reseeding of grass areas must be to the standard of the base incumbent grounds team and provision made for its bedding down and establishment, including watering and reseeding as required.

11. Energy

All projects should be mindful of the energy conservation requirements. As such highly efficient systems should be considered and evaluated during the design process.

The use of Wind Turbines and PV (Photo Voltaic) panel are not authorised for use on base.

Water saving and backflow prevention devices must be considered and approved by the 422 CES/CEN Project Manager and CE’s Backflow Prevention Manager during the design phase and fitted where required.

If a discharge consent is required, it must be applied for, and approval granted through both USAF & DIO Environmental Departments.

12. Handover Documentation

O&M Manuals

The contractor is responsible for supplying a DIO Form 140 (future maintainable assets) at both design stage and at final handover. The contractor shall also supply final construction O&M (Operations & Maintenance) manuals to the standard laid out in the DIO form 141, completed with as built drawing updated where necessary from the approved design drawings. The O&M manuals should be submitted to 422 CES/CEN in digital format until final approval is granted, then a final hard copy and a digital copy should be issued to 422 CES/CEN. Provide all product data for materials installed on the project, as well as maintenance sheets, and MDS sheets, where required.

One separate “Finishes” binder shall be submitted, organized by discipline to contain product data, including selected finishes, paint colours, etc.

O&M Manuals will be professional in appearance with a minimum of handwritten notes or labels.

Each binder will be labelled on the cover and spine. Cover and spine labels will include the project name, number and general contractor’s name. Labels for the cover and spine will describe the contents of binder “Mechanical”, “As-Builts”, etc. A binder count is required for each label, for example “1 of 3” or “Binder 3 of 6” to allow end user to easily verify all binders are present. The O&M manual will be organized logically to industry standard with an index of contents listing sections and subsections at the front of each binder. Each section and subsection will have a tabbed divider for ease of use. All as-built plan sheets will be enclosed in a plastic sleeve.

As-Built Requirements

By definition, the as-built drawings are an accurate record of the construction as actually installed and completed including all the information shown on the original set of contract drawings, unless work was deleted by modification or additive bid, and a record of all deviations, modifications or additions to the contract drawings however minor, which were incorporated in the work from notice to proceed until final acceptance.

Throughout the course of the work, the Contractor shall keep two RECORD SETs of drawings and specifications. They shall be marked in red showing changes and deviations from the original contract set. Each change shall be dated and initialled by the Contractor and the Contracting Officer. Changes shall be drawn as accurately as possible given field conditions and shall show all changes. Where changes were due to an approved change order or a field order, enter at the location of change, the change order number or field order number. Prior to final inspection, the Contractor shall submit a RECORD SET to the Government for review. The Project Inspector and Project Engineer will compare the RECORD SET with actual construction conditions for accuracy. The drawings shall include but not be limited to the following information:

The location and description of any utility lines or other installations of any kind or description known to exist within the construction area. The location includes dimensions of permanent features.

The location and dimensions of any changes within the building or structure.

Correct grade or alignment of structures or utilities if any changes were made from contract plans.

Changes in details of design or additional information obtained from working drawings specified to be prepared and/or furnished by the Contractor including but not limited to fabrication, erection, installation plans and placing details, bolt sizes, dimensions of equipment foundations, etc.

All changes and modifications which result from the final inspection.

After receipt of the Government approved RECORD SET (red lines) along with a digital file containing the original electronic design drawings, the Contractor shall prepare and submit an AS BUILT - redrawn in AutoCAD (.dwg) with actual construction conditions - set of drawings on 24" x 36" (D size) sheets. All site and building drawings will be to scale. All dimensions shall be expressed in inch-pound (English Imperial) and Standard International (SI) metric units. All files shall be DWG (AutoCAD) format. All drawings shall be drawn full size (1 to 1). Model Spaces shall be identical to the hard copy and only contain the data shown in the Model Space for that file. Also submit a digital file with digital AS BUILT - sets of drawings prepared using AutoCAD, version 2020 or higher, for Windows and in pdf format. All digital files and electronic and hardcopy drawings shall be labelled with the building number, drawing number, project number, project name, company name, and the date the electronic file/drawing was made. The drawing sheets shall be numbered consecutively starting with the cover sheet as sheet number 1. Sheet numbering shall be reflected as, for example, 1 of 8, 2 of 8, 3 of 8, etc. All electronic and hardcopy drawings shall be marked "AS BUILT" on each sheet with revision date. Show all changes that have been made and noted on the Government approved RECORD SET of drawings. Submit the final "AS BUILT" drawings on electronic files and hardcopy not later than 30 days after project completion. The Project Manager and Construction Inspector shall QC "AS BUILT" electronic files for correct data before submission to Engineering Technicians to archive. Electronic and hardcopy "AS BUILT" drawings shall be developed and delivered in the format specified United

States Army Corps of Engineers (USACE) Engineering and Construction Bulletin (ECB) 2018-7.

The USACE ECB 2018-7 can be downloaded from the Whole Building Design Guide website at https://www.wbdg.org/ffc/af-afcec/bim.

All electronic drawings shall be in the following format:

Digital data files shall be provided in Vector format (modifiable drawings) and saved as a DWG file utilizing AutoCAD 2014, Release 15 platform or higher and pdf format in separate folders.

CADD data shall be provided with the building number, drawing number, project number, project name, company name, and the date.

No zipped, compressed or spliced files will be accepted.

Drawing files may contain only one drawing per filename.

Electronic drawings must include an index specifying file names as they correspond to sheet names, i.e. for 0397M3.dwg, 03-97 is the assigned drawing number and M3 is the sheet name.

The Contractor shall ensure that the drawings which use external file references (XFREF's) shall be attached without device or directory specifications.

After design completion and Government acceptance the Contractor shall retain a copy of a digital media (with all files included) for at least one year and during this period of time, will provide up to 2 additional copies of each to the Government at no additional cost.

All electronic deliverables shall be virus free.

The Contractor is encouraged to have the original Architect-Engineer complete the work under this section, as they will be most familiar with the drawings and requirements.

Geospatial Data Requirements

Work outside the boundary of existing footprints of buildings and structures shall require the submission of geospatial/mapping data. This includes, but is not limited to, building and structure footprints, utilities, infrastructure, survey data, etc. The collection and delivery of georeferenced geospatial data shall comply with survey grade Global Positioning System (GPS) survey methods for data collection and can be supplemented by the use of equally accurate traditional survey methods. Deliverables that involve digital maps or other geospatial data must be delivered in a georeferenced Geographic Information System (GIS) format which would include file geodatabase format. Detailed specifications for data precision, data collection, attribution, and file format delivery should be included in each contract. Guidance on geospatial data deliverables and the latest version of SDSFIE is available from the installation’s Geo Integration Office (GIO)/GeoBase office.

All deliverables that involve geospatial data and maps must meet the following requirements:

All geospatial data must comply with the latest version of Spatial Data Standards for Facilities, Infrastructure, and Environmental (SDSFIE) data standards available via website https://www.sdsfieonline.org/Components/USAF at the time of contract award. Information must be collected at no less than 1:1200 scale for base cantonment areas and 1:4800 for large undeveloped base areas. Spatial data will meet or exceed National Map Accuracy Standards at those scales.

https://www.wbdg.org/ffc/af-afcec/bim https://www.sdsfieonline.org/Components/USAF

Class and feature level metadata will be provided in accordance with Air Force GeoBase Guidance and Governance and will use Federal Geographic Data Committee (FGDC), Content Standards for Digital Geospatial Metadata (CSDGM) for organization. Further guidance regarding data and metadata standards is available from the Installation GIO.

Geospatial data must be delivered in a file geodatabase. Any required attributes will be specifically outlined in the contract and must be included either in the file geodatabase or as a separate table with a SDSFIE key variable that may be used to relationally join the separate table with the GIS data file.

All geospatial data must be delivered in the Geographic Coordinate System WGS 1984/UTM Zone 30 North. Further guidance on mapping units, coordinate systems, and projections is available from the Installation GIO.

Survey Grade GPS or comparable traditional survey methods will be used to collect geospatial data. In the case of construction requirements involving utility construction, location and attribute data will be obtained at the time of excavation. Further information about survey requirements not mentioned elsewhere should be obtained from the Installation GIO.

Delivery of Digital Files

Digital deliverables shall be delivered to the Government via DoDSAFE (https://safe.apps.mil/).

When the Contractor is prepared to submit digital deliverables, they shall request a “DoDSAFE drop-off” from their Government representative whereby the contractor will receive an email link with instructions on uploading the required files for submission.

If the DoDSAFE web service is determined to be non-operational the Contractor shall work with their Government representative on alternative means for the submission of the digital deliverables (i.e. CD, DVD, Blu-Ray, etc).

13. Stakeholders

The contractor will be required to demonstrate start-up, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment to all the stakeholders designated by 422 CES/CEN, this may need to be via several different training sessions.

14. Additional Information

Design submissions to be reviewed and approved by 422 CES/CEN prior to acceptance, with a two-week review period and a design review meeting held at the end of this period.

All design review project drawing sets shall be submitted in one combined .PDF document, in logical order of disciplines, with a cover sheet indexing all drawings included in the submission set. All sets prior to the final bid set shall be labelled “Not for Construction.”

https://safe.apps.mil/

File details come from the government source that posted it. Updated .