Q A_Doc.pdf

PDF 184 KB Posted

Attached to
Cryogenics Plant Removal and Installation Federal contract opportunity
Solicitation number
FA5270-15-Q-A047
Issued by
Department of the Air Force Pacific Air Forces

About this file

Question and Answer

View the file

Other files for this federal contract opportunity

Other files attached to Cryogenics Plant Removal and Installation, newest first.
File Type Posted
Q A_with_Attachment.pdf PDF
Compressor_and_Chiller.pdf PDF
Amendment_0001.pdf PDF
Revised_Cryo_Plant_Demo_Removal_SOW.pdf PDF
Cold_Box_and_Roof.pdf PDF
Attachment_1_Whole_Plant_Layout.pdf PDF
Attachment_5_Top_down_anchoring_plan_-_all_components.pdf PDF
Attachment_3_Plant_Piping_and_Instrument_Schematic.pdf PDF
Attachment_2__Cold_Box_Mass.pdf PDF
Attachment_4_Electrical _entire_plant.pdf PDF
Attachment_6_Cold_Box_Base_Plate_plan.pdf PDF
Full_Solicitation.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ#: FA5270-15-Q-A047

Questions and Answers

Cryogenics Plant Removal and Installation

1. Is the new cold box the same size as the old one? No. The new cold box is 5 feet taller.

2. Will the the contractor need to remove the vaporizer? No. The contractor will not need to remove the vaporizer.

3. Will the contractors need to disconnect all of the electrical equipment that needs to be removed?

Yes. The contractor will need to disconnect all of the electrical equipment.

4. Will the condenser fan need to be removed? Yes. The contractor will remove condenser fan.

5. Will the contractor need to dispose of all of the equipment that is removed. No. All of the large equipment such as the cold box, condenser fan, and the air compresser unit etc. will be disposed of by the Air Force. The contractor will just be in charge of removing the equipment from the building and arranging it neatly outside. All of the smaller equipment such as nuts and bolts should be disposed of by the contractor.

6. Will the contractor be in charge of oil removal? Yes. 18 LRS will be in charge of the majority of oil removal from equipment like the lube oil skid but the contractor might be required to do some oil removal.

7. What kind of equipment is recommended to have for removal of the items? A 15 ton crane as well as a 10k fork lift is recommended but not necessarily needed.

8. Can the contractors cut the equipment to make it easier for removal? Some of the equipment can be cut and taken apart to make it easier for removal but some equipment such as the aircompressor will not be taken apart.

9. What are the dimensions of the garage doors that contractors will be using to remove most of the equipment? The doors are 141.5 inches in height and 119 inches

MCTAGUE, KILE J A1C USAF

CONTRACT SPECIALIST