FA524025B0002_RFI_Responses_15APR2025.pdf
PDF 97 KB Posted
- Solicitation number
- FA524025B0002
About this file
This document is a Questions and Answers (Q&A) file for the federal contract opportunity FA524025B0002, solicitation AJJY 22-1058 for Repair Tie Feeder Circuit P-84 and P-85 at Andersen Air Force Base, Guam. The Q&A addresses 24 technical and procedural questions from potential contractors, covering topics such as bid extensions, site visit requirements, design specifications, power outages, hazardous materials, electrical analysis software, and project execution details. Key clarifications include the government's willingness to extend bid submission dates, confirmation of design-bid-build project requirements, and contractor responsibilities for maintaining power service, coordinating utility agencies, and managing airfield operations.
The document provides critical guidance for contractors, including specifications about Professional Engineer registration, energy conservation compliance, building commissioning, cybersecurity applicability, and site development coordination. The government consistently directs contractors to refer to the original RFP documents, attachments, and specifications for detailed information. Responses emphasize the contractor's responsibility to verify existing conditions, coordinate with base operations, and submit detailed scheduling and phasing plans for government review and approval.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A # Reference Question Government Response
1 SF 1442 and SF 30 AMD
This is to request bid extension from 14 April 2025 to 30 April 2025 to give us more time to source out special materials. Thank you!
The government has extended the proposal due date for Solicitation FA524025B0002 from 14 April 2025 at 0900 ChST to 07 May 2025 at 0900 ChST. Refer to SF 1442 and SF 30 in regard to the official amendment and futher information.
2 SF 1442 and SF 30 AMD
Request For Extension:
- Our suppliers are still working on the required material quotations and have expressed concerns about the short bid submission timeline. Therefore, we kindly request a four-week extension to ensure our participation in this opportunity.
Refer to RFI #1 above for further information and direction.
3 SF 1442 and SF 30 AMD
This is to request for an additional 2-week extension to the current submission deadline.
Our Supplier is asking for extension due to the volatile situation of the current tariff issue. Refer to RFI #1 above for further information and direction.
4 SF 1442 and SF 30 AMD
As you may be aware, contractors received a temporary suspension on all MEC/UXO activities until a final notice is issued. MEC/UXO would be one of the major items in determining the price proposal for the subject RFP. As such, I am requesting to extend the bid by at least 2 weeks to get better understanding of this new requirement. Thank you.
Refer to RFI #1 above for further information and direction.
5 SF 1442
I wanted to clarify on a solicitation (AJJY 22-1058 Repair Tie Feeder Circuit P-84 and P- 85 AAFB, GU) in regards to the site visit requirements. I am trying to understand the verbiage with “Offerors are urged and expected to inspect the site where work will be performed in accordance with FAR 52.236-27.” Does this mean that it is mandatory and required to attend the pre-bid conference/site visit to bid on this exact RFP?
In accordance with FAR 52.236-27 (Alternate I), offerors or quoters are not required to attend the pre-bid conference/site visit to submit a bid for this IFB (Solicitation FA524025B0002). However, offerors or quoters are strongly encouraged to inspect the site where the work will be performed to ensure thorough understanding and accurate proposal preparation.
6 SOW
SOW Item 4.1 states “All design drawings, specifications and calculations shall be done by/or under the direct supervision of a Professional Engineer with current National Council of Examiners for Engineering and Surveying (NCEES) registration issued from a state within the United States of America (USA) or one of its territories who shall stamp all design drawings, specifications, and calculations”. Please clarify if this is applicable for this project.
This is design-bid-build project. Contractor shall comply all the requirements specified on design drawings and specifications that requires stamped and signed by Professional Engineer.
7 SOW Will SOW Item 4,2 Energy Conservation be applicable for this project? The Contractor shall comply with all the requirements of the SOW, Item 4.2 without exception.
8 SOW
SOW Item 4.4 Building Commissioning states, “Provide commissioning to meet requirements identified in Section 01 91 00.15 Total Building Commissioning, and UFC 1-200-02 High Performance and Sustainable Building Requirements”. Will these be applicable for this project?
The Contractor shall comply with all the requirements of the SOW, Item 4.4 without exception.
9 SOW Will SOW Item 4.6 Cybersecurity be applicable for this project? Not applicable.
10 Please clarify if 15KV EPR cables can be used in lieu of 15KV XLP cables. Contractor to comply the RFP design drawings and specifications.
11 SF 1442 and SF 30 AMD
During site visit, we did not able to verify the existing submersible switches that has to be removed. Please provide information of the existing submersible switches.
Refer to Attachment E Site Photos for REFERENCE ONLY. Contractor to field verify the existing and actual conditions.
12 SOW
SOW Item 2.11 states “QA/QC Manager shall be assigned no other duties and will not under Project Superintendent’s chain of command”. Will the Superintendent be allowed to be dual hat/ collateral duty as Site Safety & Health Officer (SSHO)?
Considering project amount, area coverage and its location at the airfield, no dual hat for this project. Contractor to submit a construction phasing and sequencing plan for manageable and planned project execution.
FA524025B0002
AJJY 22-1058 Repair Tie Feeder Circuit P-84 and P-85
Questions & Answers (Q&A)
FA524025B0002
AJJY 22-1058 Repair Tie Feeder Circuit P-84 and P-85
Questions & Answers (Q&A)
13 SF 1442 and SF 30 AMD
The specs 26 28 01.00 10 specified to provide the calculation performed for analysis to utilize EasyPower for electrical analysis software. Please clarify if we can use the SKM POWER Tools software for this project?
Refer to Spec Section 26 28 01.00 10 par 2.1.6.e to utilize the Easy Power for electrical analysis and UFC 3 501 01 par 3-2.2.1 for electrical analysis software to utilize EasyPower only (Air Force) instead of SKM Power (Navy). Please see Attachment F.
14 Is there an approved MEC Annex for this project? If so, please provide. MEC Annex is not currently available and a copy will be provided upon project award.
15 Can the expansion footprint of the existing switchgears concrete enclosure be considered previously disturbed or a know utility trench? Please advise.
Existing switchgear enclosures and the soil immediately adjacent are estimated to be previously disturbed soil. However, until the MRESS Annex is approved, this classification is not authorized as a deviation from MEC requirements. MEC Annex will be provided upon project award.
The project have multiple power outages like replacing/upgarding the switchgears, existing primary cables and intercepting existing cables and splice to the new cables, please clarify if consecutive days of outages is allowed or the circuit to be outages is totally shut off until the completion of the circuit and ready to energize.
Contractor to provide a construction phasing/sequencing plan schedule for Government review and approval. Refer to RFP SOW par 4.13 for utility outage requirement.
Once the circuit is shut off, please clarify if we need to provide temporary power to those affected existing pad mounted transformer with essential service to the operation of the taxiway/runway system? If yes, please provide the equipment/facility feeding by the transformers.
The Contractor is responsible for maintaining power to affected facilities during project execution and for determining the alternative service connection points necessary to ensure continuous power service to affected facilities. Coordinate to BOS contractor (DZSP 21) for all information needed.
18 Since the power outage will be incurred and pay by the contractor, please provide the cost for the power outage per day for our reference in our bid.
It is Contractor's responsbility to coordinate all power outages with the CO, DZSP21, GPA and other applicable agencies and pay all charges incurred at no additional cost to the Government.
19 SOW
The SOW item 3.2 Site Development stated "The contractor shall be responsible for paying the BOS contractor in locating underground electrical transmission line and respectively local utility agencies for all coordination and permit costs". Is it possible to waive the charges of this scope of work by/from the contractor? Contractor will just coordinate with the 36 CES Base utility agencies and DZSP21 in locating the exsiting utilities with in the boundaries of affected areas of excavation work? Please advise.
No, it is part of RFP SOW as mentioned in par 3.2 Site Development.
20 Please provide the updated as-built one line diagram of the affected power circuit.
All power outages will be coordinated to DZSP 21 and other applicable agencies at no additional cost to the Government. As-built drawings will be provided to contractor for reference only upon project award. Contractor to field verify the existing and actual conditions.
21 SOW The SOW item 2. 7 specified Hazardous Materials Assessment, please clarify if this item is intended to the existing switchgear and enclosure excluding the trence work.
Testing will covers all existing cables, switchgears, transformers (submersible and padmounted), and other equipment to be removed and disposed by the Contractor.
In case the trench work or excavated materials is part of the the hazardous materials, what will be the parameters to be considered like the area or locations because it cannot be determined the condition of the soil unless excavation is to be performed at the site. Please advise.
If excavated soil and other materials need to be disposed to an outside waste facility, a hazardous waste determination is required by using RCRA hazardous waste regulation.
The excavation work are mostlikely at taxiway access road and taxiway parking, please clarify if both North & South Runway are open for aircraft movement: Or one runway (North) is open and the other runway (South) is closed or vice verza? Please confirm.
Prior to start of work, Contractor must submit a detailed schedule/phasing plan to Contracting Officer for Government's review and approval. All works will be coordinated to 36 Operations Support Squadron (OSS) to ensure and maintain the airfield operations.
FA524025B0002
AJJY 22-1058 Repair Tie Feeder Circuit P-84 and P-85
Questions & Answers (Q&A)
13.8 KV Power Distribution Repair works (Drawing sheet E-602):
- Are there any Transformers or loads connected to the power circuits that needs to be maintained to support a continues operation during power outage? And if such loads require emergency power or a generator back up power, can you please identify their sizes as per:
a. The KVA rating/Voltage rating.
b. Their required Frequency.
c. The required hours of operation.
It is contractor's responsibility to field verify all the existing conditions and required informations for project scheduling and execution.
*** NO FURTHER ENTRIES ***