This document is a Salient Characteristics specification for a heavy-duty pallet racking system required by the 647 Civil Engineer Squadron (CES) at Base X to support contingency training operations, including CBRN Defense classes, Warrior Airman Training, Base Readiness Exercise, Prime BEEF, and Expeditionary Training.
The vendor must supply and install a complete pallet racking system configured as one starter unit and four add-on units in a continuous, interlocking bay run. The starter unit must be a two-shelf heavy-duty pallet rack measuring approximately 144" Length × 48" Width × 144" Height with a minimum load capacity of 7,000 lbs per unit. The four add-on units consist of two units at 120" Length × 48" Width × 144" Height and two units at 144" Length × 48" Width × 144" Height, each supporting a minimum 7,000 lbs. The system includes 44 wire decking pieces measuring approximately 58" Width × 48" Depth, each supporting a minimum 3,500 lbs. Frames must be constructed of welded 14-gauge steel with 16-gauge steel beams in a boltless design with 2-inch vertical adjustability. The package includes six rack protectors (6.5" Width × 24" Height) and all installation hardware including concrete wedge anchors. The vendor must provide full-service installation with certified operators, completing on-site installation within 14 calendar days of material delivery. All materials and components must be delivered within 45 calendar days after contract award. The system will be installed in a pre-designated area within a pre-engineered metal building on the base.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Salient Characteristics for Pallet Racking System
Rationale of Requirement
The 647 CES operates and stores 1.8K sq-ft of contingency training equipment for Wing CBRN Defense classes, Warrior Airman Training, Base Readiness Exercise, Prime BEEF and Expeditionary Training at Base X.
To support these critical operations, a heavy-duty, industrial-grade pallet rack system is required. This system must provide safe, high-capacity vertical storage to optimize the physical footprint, protect government equipment, and ensure immediate operational readiness.
Physical and Functional Requirements
The vendor must provide a heavy-duty pallet rack system that meets or exceeds the following minimum essential physical and functional characteristics.
System Components & Dimensions
The racking system must be configured as a continuous, interlocking bay run consisting of one (1) Starter Unit and four (4) Add-On Units to share vertical uprights, maximizing floor space and structural integrity.
• Starter Unit (1 each):
• Type: Two-shelf heavy-duty pallet rack starter unit.
• Dimensions: Approximately 144” Length x 48” Width x 144” Height.
• Load Capacity: Must support a minimum of 7,000 lbs per unit.
• Add-On Units (4 each):
• Type: Heavy-duty pallet rack add-on units.
• Dimensions & Quantity:
• Two (2) units at approximately 120” Length x 48” Width x 144” Height.
• Two (2) units at approximately 144” Length x 48” Width x 144” Height.
• Load Capacity: Each unit must support a minimum of 7,000 lbs.
• Wire Decking (44 each):
• Type: Heavy-duty pallet rack wire decking.
• Dimensions: Approximately 58” Width x 48” Depth.
• Load Capacity: Each deck must support a minimum of 3,500 lbs.
Construction and Material Characteristics
• Frame: Must be constructed of welded 14-gauge steel (or equivalent strength).
• Beams: Must be constructed of 16-gauge steel (or equivalent strength).
• Assembly: System must feature a boltless design where beams securely lock into the upright frame.
• Adjustability: Beams must be vertically adjustable in 2-inch increments to accommodate various load sizes.
Safety Components
• Rack Protectors (6 each): Must include post protectors with dimensions of approximately 6.5” Width x 24” Height to prevent damage from forklifts or other equipment.
• Installation Hardware: Must include all necessary hardware for assembly and for anchoring the system to a concrete floor or equivalent (e.g., concrete wedge anchors).
Installation and Delivery Requirements
• Full Service Installation: The vendor is required to provide all necessary equipment, materials, and certified operators to complete the full installation of the pallet rack system.
• Anchoring: Vendor must securely anchor each rack section to the existing concrete floor using appropriate hardware (e.g., standard wedge anchors) to ensure system stability and safety.
• Installation Site: The system is to be installed in a pre-designated, open, and clear area within a pre-engineered metal building.
• Installation Timeframe: On-site installation must be completed within 14 calendar days after the delivery of all materials and components.
• Delivery Lead Time: All materials and components for the project must be delivered within 45 calendar days after contract award.