Attachment No. 4 for Solicitation No. FA5209-16-R-0011
ADDITIONAL CONTRACT REQUIREMENTS
Date: 14 Mar 16
1. Preparation of Progress Schedules and Reports
The schedules and reports prescribed by the clause at FAR 52.236-15, Schedules for Construction Contracts, in Section I shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule and AF Form 3065, Contract Progress Report.
2. Preparation of Material Approval Submittal
The submittals contemplated by the clause here titled “FAR 52.236-5, Material and Workmanship,” in Section I shall be accomplished on and in accordance with instruction pertaining to AF Form 3000, “Material Approval Submittal”.
3. Accounting and Appropriation Data
Accounting and appropriation data will be cited when funds are available.
4. Possession of Vehicle Insurance Certificate
Vehicle insurance certificate in paragraph (b) of the clause at AFFARS 5352.242-9000, Contractor Access to Air Force Installations, in Section I must cover the automobile liability insurance in the types and minimum amounts specified below:
(a) Bodily Injury Y30,000,000 per person per occurrence, in addition to the Japanese
Compulsory Insurance (JCI)
(b) Property Damage
Y3,000,000 per occurrence
5. Conciliation
Except as otherwise provided in this contract any disagreement arising under this contract which is not resolved by the parties to this contract may be submitted to the United States - Japan Joint Committee for conciliation in accordance with paragraph 10, Article XVIII, of the Status of Forces Agreement under Article VI of the Treaty of Mutual Cooperation and Security between Japan and United States of America.
Requests by the Contractor for conciliation shall be made in accordance with the following procedures:
(a) In the event the Contractor desires conciliation after the decision of the Contracting Officer has been served upon him, he will first file his appeal from such findings of fact with the appropriate authority in accordance with the Clause of this contract entitled DISPUTES, and within the time limits described therein before filing request for conciliation with the Joint Committee and then request the appellate authority under the Clause of this contract entitled DISPUTES, to suspend its action on his appeal until such time as the Joint Committee has had an opportunity for effecting conciliation.
(b) The request for conciliation will be submitted by the Contractor through the nearest local Japanese Defense Facilities Administration Bureau, to the Contract Conciliation Panel of the Joint Committee.
Upon the filing of the request with the Joint Committee, the Contractor will immediately notify the Contracting Officer in writing that the request for conciliation has been filed.
(c) In the event the disagreement submitted to the Joint Committee under subparagraph (b) above has been resolved through conciliation, it will be the responsibility of the Contractor to notify the appellate authority designated in the Clause of this contract entitled DISPUTES, of the settlement of the dispute and to withdraw his appeal.
(d) In the event the Contractor who has submitted a request for conciliation to the Joint Committee under subparagraph (b) above desires, notwithstanding pendency of his request for conciliation, that action by the appropriate authority under the Clause of this contract entitled DISPUTES, be resumed on his appeal, it is his responsibility to so request the said authority in writing. The Joint Committee shall be immediately informed by the Contractor of his action taken hereunder.
(e) No request for conciliation can be submitted to the Joint Committee in the case of a dispute upon which the final decision of the appropriate authority under the Clause of this contract entitled DISPUTES, has been rendered. Pending the hearing of conciliation panel the Contractor shall proceed diligently with the performance of the contract and in accordance with the Contracting Officer's decision. The provisions of this clause shall not prejudice any right which the parties to the contract may have to file a civil suit.