This document contains a summary of questions and answers from a pre-proposal conference and site visit for an indefinite-delivery/indefinite-quantity airfield and pavements contract at Misawa Air Base in Japan. The contract has a guaranteed minimum amount of 300,000 Japanese Yen and maximum limit of 5.2 billion Yen over its five-year period including a one-year base and four one-year options. Task orders under the contract will be for repair, maintenance, and construction of airfield pavements, roads, parking lots and associated incidental work. The summary clarifies that while the maximum order amounts in the solicitation refer to single and multiple work item task orders, tasks orders will likely contain multiple work items due to the nature of the work. It also confirms work at the Draughon Range site may take place during daytime hours only and a contractor storage yard can be coordinated on location.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF QUESTIONS AND ANSWERS
Pre-proposal Conference and Site Visit
RFP No. FA520522R0005 Airfield/Pavements IDIQ Contract, Misawa AB, Japan
Attachment 2 to Pre-Proposal Conference Minutes & Record of Site Visit
13 Jul 22
Questions and Answers at Conference held on 7 Jul 22
Q1: RFP, Clause at FAR 52.216-19 Order Limitations.
What are the difference between para. (b)(1) and (2) of maximum order where both of them are ¥600,000,000?
A1: (b)(1) is the maximum amount for a task order having a single work item of ELINs, and (b)(2) is for a task order having multiple work items of ELINs. While a single item task order can be technically issued, all task orders are most likely to have multiple items due to the nature of repair, maintenance and construction of the airfield and Draughon Range.
Questions and Answers at Site Visit to Airfield None.
Questions and Answers at Site Visit to Draughon Range
Q2: Are there any nighttime work expected in the Draughon Range?
It is most likely daytime work subject to coordination with the end user.
Q3: Are there any stock yard available at the Draughon Range?
Yes, the contractor will be required to coordinate actual location with the end user.