FA5205-11-R-0001_ Atch5-Content3.pdf
PDF 143 KB Posted
- Attached to
- Simplified Acquisition of Base Engineering Requirements (SABER) Contract, Misawa Air Base Japan
- Solicitation number
- FA5205-11-R-0001
About this file
Attachment 5 to FA5205-11-R-0001 Model Project Content 3
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAMPLE SURVEY REPORT
1. PARKING APRON DEMOLITION & REPAIR
a. DESCRIPTION OF WORK: Repair parking aprons. Remove Five existing 4,000mm
(L) x 5,000 (W) x 150 mm (T) concrete slabs and replace with 3,000 PSI concrete.
b. QUANTITIES
Demolition: Concrete Pavement 5 x 4 x 5 = 100 M² Concrete Disposal 5 x 4 x 5 x 0.15 x 1.2 = 18 M³ To Disposal Place 5 x 4 x 5 x 0.15 x 1.2 = 18 M³
Repair: Crusher-run 5 x 4 x 5 x 0.05 = 5 M³ Concrete Form 5 x (4+5) x 2 x 0.15 = 13.5 M² Welded Wire Fabric 5 x 4 x 5 = 100 M² Concrete 5 x 4 x 5 x 0.15 = 15 M³
c. ITEMS IN UNIT PRICE BOOK AND CALCULATIONS
Item UPB Number Description Unit Qty U/P Line Total
Subset 1: Survey and test 001 01030-3001 Drawings & Qty Calculation Set 1.0 60,000 60,000
Subset 2: Demolition 002 02220-4202 Concrete Pavement w/Mesh M² 100.0 1,323 132,300 003 02226-2002 Concrete Disposal M³ 18.0 3,120 56,160 004 02320-1107 To Disposal Place M³ 18.0 963 17,334
Subset 3: Repair 005 02720-2101 Crusher-run M³ 5.0 8,544 42,720 006 03110-1001 Concrete Form M² 13.5 3,911 52,799 007 03220-1002 Welded Wire Fabric M² 100.0 783 78,300 008 03310-1201 Concrete M³ 15.0 17,063 255,945
Total Direct Cost 695,558 Coefficient (sample) 112%
Total Amount of Project ¥779,025
SAMPLE SURVEY REPORT
2. REPLACEMENT OF HEATING EQUIPMENT
a. DESCRIPTION OF WORK: Replace Six existing 800 mm length finned tube type baseboard units new including associate devices.
b. QUANTITIES
Removal: Finned tube type baseboard heater 6 EA Steam supply and return pipes 12 M
Installation: Finned tube type baseboard heater 6 EA Steam supply and return pipes 12 M Thermal insulation 12 M Radiator valve 6 EA Steam trap 6 EA
c. ITEMS IN UNIT PRICE BOOK AND CALCULATIONS
Item UPB Number Description Unit Qty U/P Demo Line Total
Subset 1: Survey and Test 001 01030-3001 Drawings & Qty Set 1 60,000 60,000
Subset 2: Removal 002 15522-5001 Remove Convector EA 6 7,742 46,452 003 15111-5102 Black Steel Pipe M 12 3,708 21% 9,344
Subset 3: Repair 004 15521-1002 Baseboard Heater EA 6 18,668 112,008 005 15111-5102 Black Steel Pipe M 12 3,708 44,496 006 15710-4102 Pipe Insulation M 12 2,612 31,344 007 15231-2002 Radiator Valve S EA 6 6,633 39,798 008 15232-4002 Steam Trap EA 6 8,528 51,168
Total Direct Cost 394,610 Coefficient (sample) 108%
Total Amount of Project ¥426,179