Attachment 5 to FA5205-11-R-0001 Model Project Content 2
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MODEL PROJECT
Information for Drawing Preparation and Quantity Survey
QKKA00000X, Repair Bldg 653, Misawa AB, Japan
This document is a supplement to the Scope of Work for the SABER Model Project, QKKA 00000X, Repair Bldg 653, Misawa AB, Japan, to assist offerors for their preparation of Model Project Proposal under limited project site information.
[NOTE: In the actual execution of SABER project(s), the Government is not obligated to provide this or similar information to the successful contractor.]
ABSTRACT
1. For pavement repair, replacement of curbs and gutters is not required.
2. Underground utility lines should not be disturbed.
3. No change to interior layout is necessary.
4. Re-paint interior doors except the main entrance.
5. Floor tiles of the waiting area, Rooms 1002 and 1004, are not included.
6. All wall papers shall be removed and paint the surface.
7. Roll-up doors, venetian blind, curtain and curtain rails/boxes are not included.
8. Include replacing baseboards where necessary.
9. Wall telephone cabinet and reception counters and in the waiting area are not included.
10. Remove and re-install diaper changes on latrine walls.
11. All other fixtures, outlets and utilities on interior surface shall be replaced with new.
12. Work area will be vacated, and the main entrance, Room 1001, can be closed during the renovation.
13. Include all temporary work as necessary. Do not include construction sign except safety purpose.
14. Work in non-regular time is not permitted.
15. No Government Furnished Material/Equipment will be issued.
16. No asbestos sampling/abatement is required.
17. To make the quantity survey report, show at least 7 subtotals below:
a. Civil Work
b. Offices, Architectural Work
c. Offices, Electrical Work
d. Offices, Mechanical Work
e. Latrines, Architectural Work
f. Latrines, Electrical Work
g. Latrines, Mechanical Work
18. The list should include price of effort for the drawings/quantity survey.
19. For using SABER Unit Price Book, refer to SAMPLE SURVEY REPORT attached.