Install Lift Station Generators Additional Questions 30 May.pdf

PDF 101 KB Posted

Attached to
Install Lift Station Generators - Eielson AFB, AK -( Amended see description) Federal contract opportunity
Solicitation number
FA500423R0009
Issued by
Department of the Air Force Pacific Air Forces

About this file

This document contains questions and answers regarding a federal contract opportunity to install lift station generators at Eielson Air Force Base in Alaska. The opportunity involves replacing generators, fuel storage tanks, and automatic transfer switches at three lift station sites. Generators of 40kW, 60kW, and 225A will be installed, along with 72-hour runtime fuel tanks in arctic rated walk-in enclosures. Load studies were previously conducted but are unavailable. The contract is firm-fixed price between $500,000 and $1,000,000 under Solicitation FA500423R0009 for the Department of the Air Force Pacific Air Forces.

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FTQW23‐1400 Install Lift Station Generators

Questions

1. Attachment 4 SOW paragraph 3.2.2 references a "new pump house". Please confirm this is a typo.

‐ This is a typo which was removed in an updated document.

2. Does the Government desire gensets equipped with outdoor "reach‐in" minimally heated metal‐ clad enclosures or "walk‐in" environmental enclosures?

‐ Walk‐In environmental enclosures with space heaters and insulated for artic climate.

3. Are the double‐throw bypass switches intended to provide means to switch the lift station supply from utility source to a connection point for a portable generator?

‐ This is correct. We must have a means of hooking up an alternate generator in the event that the primary goes down.

4. Should a 20kW (50% genset rating) radiator‐mount load bank be included (with load leveling control) to ensure adequate loading is provided when genset is supplying the load, or being exercised (automatically by ATS programmable exerciser, say 30 minutes a month) to maintain readiness?

‐ Yes. Since these generator sets won’t always have pumps running to keep them loaded, a load bank would optimize monthly, semi‐annual, and annual testing.

5. What is required standby run time for sizing the sub‐base fuel tank (i.e. 24 hours @ 100% load, etc..)

‐ Unified Facility Criteria specifies 24‐hours of storage at full load when a reliable delivery source is available. Given the circumstances that Eielson faces in the winter, we would strongly recommend, and prefer 72‐hrs of storage at full load.

6. Attachment 4 (Statement of work), section 3.2.2 indicates, “The Contractor shall provide the Government with all the design documents necessary to construct the new pump house”. The 100% design, minimum submittal requirements, sub‐bullet 2, indicates, “Updated drawings to provide a constructible pump house …”. Please confirm that this project is not providing any design of a pump house.

‐ This project is not providing any design of a pump house. This typo was removed in an updated document.

7. Numerous locations in Attachment 4 and Attachment 7 reference a “40kW 120/208VAC” generator. Attachment 2 (Asbuilts) indicates that the French Creek site has a 400A panelboard with 117 kVA of calculated load and that the Moose Lake site has a 400A panelboard with 108 KVA of calculated load at 208Y/120V. At the French Creek and Moose sites, is the intent to use 40kW generators (which may be undersized)? Alternatively, should the generators be sized to match the asbuilt calculated load (~125 kVA generators), or be sized to match the 400A service rating (~150 kVA generators)?

‐ These generators weren’t sized to support the entire facility. There are existing double throws switches the automatic transfer switches and generators were sized to…not to the service panelboard. All load studies were conducted prior to listing generator sizes in the authorizations to AFCEC.

8. Numerous locations in Attachment 4 and Attachment 7 reference a “40kW 120/208VAC” generator. During the site visit on 04/13/2023, it was noted that the Glacier lift station is served at 480Y/277‐volt, 3‐phase, with a 200‐amp service. Please confirm that a 480Y/277‐volt generator should be provided at this site and not a 208Y/120‐volt generator. If so, should it be sized at 20kW (equivalent to a 40kW 208Y/120V), or be sized to match the 200A service rating (175kW)?

‐ Not sure where 40kW 120/208VAC came from, but our request for Glacier Lift Station was a

60kW 277/480 VAC generator. This sizing was determined by a record review and load analysis. Mission essential loads are the only thing we are authorized to have backup power for so matching the 200A service rating would not be the solution.

9. During the site visit on 04/13/2023, it was noted that the Glacier site is already equipped with a manual transfer switch downstream of the service disconnect. Should this manual transfer switch be removed after when the new transfer switch is installed?

‐ Yes. There will be no need for a manual transfer switch to be left in place.

10. Attachment 7 (Brand Name and Supporting Documents) refers to a 225 Amp Bypass transfer switch. The Moose Lake and French Creek sites have 400A service disconnects. A 225A transfer switch cannot be installed and protected by a 400A service. Please confirm that 400A transfer switches should be provided at these sites.

‐ These generators weren’t sized to support the entire facility. There are existing double throws switches the automatic transfer switches and generators were sized to…not to the service panelboard. All load studies were conducted prior to listing generator sizes in the authorizations to AFCEC.

11. Attachment 2 (Asbuilts) does not include any asbuilts for the Glacier site. Are any asbuilts for the

Glacier site available that the Government can supply?

‐ No – the government does not currently have as‐builts for this site.

12. Attachment 4 (Statement of work) references generator, belly tank, and automatic transfer switch. Does the Government prefer a walk‐in enclosure to house all the equipment, or should the equipment be configured separate pieces?

‐ Given the climate in Alaska, the best option for us is to have walk‐in, arctic rated enclosures to house all of the equipment.

13. Attachment 4 (Statement of work) refers to a generator “belly tank” in many locations. Does the generator belly tank need to be sized to maintain a minimum runtime duration, or is a default/standard tank size adequate?

‐ Unified Facility Criteria specifies 24‐hours of storage at full load when a reliable delivery source is available. Given the circumstances that Eielson faces in the winter, we would strongly recommend and prefer 72‐hrs of storage at full load.

14. Attachment 4 (Statement of work) does not specify any requirements for generator exhaust mufflers. Are hospital‐grade mufflers or other noise suppressors desired, or will a standard muffler suffice?

‐ Because these generators will be installed around housing and school‐age areas, noise suppression is desired. Typically, the arctic enclosures we get have sound suppression better than your standard muffler.

15. Attachment 4 (Statement of work), section 4.1, does not list UFC 3‐501‐01. Please confirm this

UFC does not apply, including Arc Flash Analysis and Protective Device Time‐Current Coordination Studies.

‐ When sizing and spec‐ing generators, we do not generally reference UFC 3‐501‐01 so this question is a little out of Power Pro’s realm. After speaking with Electrical on this matter, we have determined it would be safest to have the study conducted and included with the contract.

16. Attachment 4 (Statement of work), section 3.1, indicates that there may be hazardous materials encountered during construction. Please clarify if the Contractor is responsible for obtaining a hazardous material survey for the areas impacted by the scope of work.

‐ Yes. The two materials that may be encountered are asbestos and lead, and although neither are expected, section 3.1.1.b states “The Contractor is responsible for identifying asbestos containing material (ACM) prior to conducting maintenance, abatement, renovation, or demolition activities”. Lead paint is not expected as the housing areas served by these mech rooms were constructed in 1995, long after the ban on lead paint usage.

17. Are there any known contaminated soils within the work areas? Should a specified amount of contaminated soil be included in the bidder’s proposal?

‐ Those locations are not in areas of known contamination. The soil will just need to be field screened with a photoionization detector (PID). As long as you don't have to dewater you should not need to stockpile and conduct laboratory testing unless the PID comes back with high readings, or you notice spilled chemicals.

18. The responses to questions 7 & 10 state that there is an existing manual transfer switch (MTS) that should be replaced in place with an automatic transfer switch (ATS). Please confirm that the new ATS should match the existing MTS rating and that all upstream & downstream connections shall remain as is.

‐ Yes, essentially, the goal is to replace the mobile generators assigned to the facility with permanently installed RPIE units with an automatic transfer switch. The new ATS should match the existing MTS rating and all upstream and downstream connections in relation to the generator and transfer switch shall remain as is.

19. The responses to questions 7 & 10 state that there is an existing manual transfer switch (MTS) that should be replaced in place with an automatic transfer switch (ATS). Please confirm that only loads that are currently connected downstream of the MTS will be connected to the ATS, that no load reconfiguration is needed, and that anything that was not previously connected downstream of the MTS will not be backed up by the new ATS/generator.

‐ Accurate, no load reconfiguration is sought currently. ‐‐SSgt. Kolby Goss

20. Answer 9 states to remove the manual transfer switch (MTS) at the Glacier site. Answer 3 states to provide a double‐throw bypass switch as an alternate means of hooking up an alternate generator in the event that the primary goes down. Please confirm for each site if there is an existing manual transfer switch, if it shall remain, or if a new one shall be provided.

‐ All MTS shall be replaced with ATS – PP confirmed—MTS bypass switch for alternate generator hook‐up.

21. The response to question 8 references a “60kW 277/480 VAC generator”. Please confirm this response is officially changing the scope and that the listed generator should be priced for the Glacier site. If so, this will impact pricing efforts. Additionally, please confirm that this 60kW 480Y/277V selection will not conflict with Attachment 7, which indicates “Generator specifications must meet these exact criteria. Alternate proposals will be removed from competition” of the 40kW 208Y/120V.

‐ Based on the record review and load analysis, a 60kW 277/480 VAC generator was requested for Glacier Lift Station. This will not conflict with attachment 7 or the previous scope.

22. The responses to questions 5 & 13 indicate “United Facility Criteria specifies 24‐hours of storage

… strongly recommend and prefer 72‐hours”. Should a 72‐hour runtime or 24‐hour runtime be provided?

‐ 72 hours

23. Will a 24‐hour 100% load fuel tank be considered non‐responsive?

‐ Per UFC no, however the conditions for this state “when a reliable delivery source is available” which is often not the case during Eielson winter conditions, thus the 72‐hour recommendation and preference.

24. If a 72‐hour runtime is required, is it the Government’s desire to still have a sub‐base tank that could put the generator quite high off of the ground and less maintainable?

‐ For locations where space is an issue, sub‐base tanks, or “belly tanks” as they’re commonly known, are an option for fuel storage. We have quite a few sites with these types of tanks, and if they meet the required runtime, this should not pose an issue.

25. The responses to questions 7, 8, & 10 all reference “load studies”, but load studies were not included with the solicitation. Are these load studies available? This information may help better understand the intent of the project.

‐ No, the load study capture files were not retained after initial study was done >1yr ago.

26. Will the referenced load studies from Answers 7,8, and 10 be made available to the successful team during design?

‐ See answer to 25.

27. Answer #3 says to provide a manual transfer switch with inlet for portable generator connection. What size portable generator is intended to be connected to the manual transfer switch?

‐ This would depend on the applicable lift station site, but the portable generator hook‐up should match the installed unit’s rating.

28. SOW states ATS with double throw for bypass capability – does this mean they want an ATS with maintenance bypass switch so the ATS can be taken out of service for maintenance without interrupting power to the facility?

‐ This is what that means. It is much safer and efficient for the technician doing the ATS maintenance or troubleshooting to be able to isolate the automatic transfer switch. Thus, a bypass for the ATS is desired.

29. Is there a specific Tier rating or environmental requirement for the generator?

‐ Per power pro, it is my understanding that all new generator installs should be Tier 4 if feasible.

‐ Per environmental, the engine will need to meet the applicable emission limits in 40 CFR 60, Subpart IIII. There are no specific requirements at EAFB or exemptions from the federal requirements.

30. Fuel source to be diesel?

‐ Yes, per specifications it will be a Cummins C40D6, Diesel Genset

31. Are there as‐builts for Glacier Creek?

‐ Answered in question 11 – no.