JA-2_Specs.pdf
PDF 9 MB Posted
- Attached to
- CHPP Phase A Federal contract opportunity
- Solicitation number
- FA5004-18-B-C004
About this file
JA-2 Specs for CHPP Phase A - Eielson AFB AK
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Phase_A_Bidder_Q&A.pdf | ||
| FA500418BC0040001.pdf | ||
| JA-5_Drawings.pdf | ||
| FA500418BC004.pdf | ||
| JA-1_SOW.pdf | ||
| JA-4_Wage_Determination.pdf | ||
| JA-3_AF_Form_66.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FTQW 18-0504
REPAIR CENTRAL
HEAT & POWER PLANT
ELECTRIC PANELS & CIRCUITS,
PHASE A
Technical Specifications
Prepared for:
Department of the Air Force
Eielson AFB, Alaska
Prepared by:
3305 Arctic Blvd., Suite 201 Anchorage, AK 99503
(907) 349-6653
January 2018
This page intentionally left blank.
Repair CH&PP Electric Panels & Circuits, Phase A Eielson AFB, Alaska TECHNICAL SPECIFICATIONS
FTQW 18-0504 TABLE OF CONTENTS
Construction Documents TOC - 1 January, 2018
Division Section Title Pages
DIVISION 1 - GENERAL REQUIREMENTS
01010 Description of Work and Coordination 01030 Safety, Environmental Protection, Regulations, and Codes Appendix A - G
01045 Cutting and Patching 01073 Explanations: Drawings and Specifications 01080 Existing Utilities
01120 Alteration Project Procedures 01300 Submittals 01400 Quality Control
01500 Construction Facilities and Temporary Controls 01600 Products and Substitutions 01700 Record Documents, Inspections, and Closeout
DIVISION 2 - SITE CONSTRUCTION
02055 Selective Demolition
Hazardous Materials Investigation Report………………………………………
02075 Asbestos Awareness and Removal 02084 Lead Handling Procedures
DIVISION 16 - ELECTRICAL
16060 Grounding and Bonding 16073 Hangers and Supports for Electrical Systems 16074 Vibration and Seismic Controls for Electrical Systems
16075 Electrical Identification 16120 Conductors and Cables 16130 Raceways and Boxes
16265 Central Battery Equipment for Emergency Lighting 16410 Enclosed Switches and Circuit Breakers 16415 Transfer Switches
16442 Panelboards 16461 Low-Voltage Transformers 16511 Interior Lighting
END OF TABLE OF CONTENTS
Eielson AFB, Alaska TECHNICAL SPECIFICATIONS
FTQW 18-0504 TABLE OF CONTENTS
Construction Documents TOC - 2 January, 2018
Eielson AFB, Alaska SECTION 01010
FTQW 18-0504 DESCRIPTION OF WORK AND COORDINATION
Construction Documents 01010 - 1 January, 2018
SECTION 01010 - DESCRIPTION OF WORK AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings, Agreement, including General Provisions of Contract, General and Supplementary Conditions and Division 1 General Requirements apply to the work of this Section.
1.2 SCOPE OF THIS SECTION
A. Related Requirements B. Synopsis of Contract Work C. Government Occupancy D. Contractor Use of Premises E. Field Engineering F. Reference Standards G. Work by Others H. Coordination I. Notification J. Security and Access K. Existing Features
1.3 RELATED REQUIREMENTS
A. Section 01073 – Explanations: Drawings and Specifications.
1. Contracting Officer: Contracting Officer means Contracting Officer or Contracting Officer’s Representative.
2. Owner: Owner means Government.
1.4 SYNOPSIS OF CONTRACT WORK
A. BASIC ITEM 1: Item includes, but are not limited to, the following:
1. DEMOLITION. The Work consists of providing all materials, labor and ancillary work required to complete the demolition of existing electrical distribution and light systems in the CH&PP prior to or in conjunction with the construction of new systems as specified, as indicated on the project drawings, to include:
a. Removal of light fixtures;
b. Removal of unused junction boxes, conduit, and wiring devices associated with the light fixtures;
c. Removal of all lighting circuit conductors;
Construction Documents 01010 - 2 January, 2018
d. Removal and disposal of hazardous materials as may be present in the electrical equipment, or other existing hazardous materials as may be disturbed during the performance of the work;
e. Separation, storage and disposal of hazardous and non-hazardous materials.
f. All required coordination;
g. All required temporary systems or lighting as may be required to maintain
CH&PP operations;
h. Related electrical work;
i. Other work noted on the drawings.
j. Demolition requires the indicated items be removed. Existing materials may not be abandoned in place or left to remain.
k. Separation, storage and disposal of hazardous and non-hazardous materials.
2. POWER DISTRIBUTION. The work consists of providing all materials, labor and ancillary work to construct new and fully functional power distribution systems in the CH&PP to support the new lighting systems, as indicated on the project drawings, to include:
a. Furnishing and installing distribution and branch panelboards of various sizes and ratings;
b. Transformers;
c. Emergency lighting central inverter system;
d. Associated feeders and conduits;
e. Relocating existing, non-lighting branch loads and circuits to the new panelboards;
f. All required coordination;
g. Related electrical work;
h. Other work as noted on the drawings.
3. LIGHTING SYSTEMS. The work consists of providing all materials, labor, and ancillary work required to construct new and fully functional lighting systems in the CH&PP as indicated on the project drawings, to include:
a. Furnishing and installing light fixtures;
b. Lighting circuits and controls;
c. All required coordination;
d. Related electrical work;
e. Other work as noted on the drawings.
B. The work environment includes confined spaces and exposure to biohazards associated with lead and asbestos containing materials.
1.5 GOVERNMENT OCCUPANCY
A. The Government will occupy premises during entire period of construction for the conduct of its normal operations.
Construction Documents 01010 - 3 January, 2018
B. The Contractor shall perform the work under this contract in such a manner that adjacent Air Force activities may proceed unhindered. Prior to beginning on-site work the Contractor shall meet with the Contracting Officer and technical representatives from Base Civil Engineering to schedule the work of this contract.
C. The Contractor shall not interfere with, nor prevent in any manner, access to or exiting from any room or area without prior approval from the Contracting Officer.
D. Maintain IBC complying access to and through corridors, stairways, and building exits at all times.
E. Cooperate with Government to minimize conflict and to facilitate its operations. In case of conflict accept Contracting Officer's direction as final and adjust use of premises accordingly.
F. Coordinate Work in and use of premises with the Government.
G. The Contractor shall clean and have ready for use all areas of work that will be used by the Government between work periods
H. Limitations on Performing and Scheduling of Work:
1. Lighting and panel work shall be conducted such that no area will be without lighting during construction. New lighting panels shall be provided before removing existing lighting; new lighting shall be provided before removing old lighting, or suitable temporary lighting may be provided subject to approval of the Government.
1.6 CONTRACTOR USE OF PREMISES
A. Limit use of premises for Work and for construction operations only.
B. Limit on site storage of materials to government authorized staging areas. Contractor is responsible for security of stored materials and equipment.
C. Contractor shall take reasonable and adequate precautions to protect government property from damage during demolition, construction, clean-up, and exposure to the elements. Protect systems susceptible to freezing. Protect existing utility and communication systems while working in utilidors. Damaged items shall be repaired or replaced prior to final inspection.
D. Smoking is prohibited in all base facilities.
E. Limit construction access to the areas where work is indicated on the drawings.
F. Move owner tools, equipment, shelving, stored materials, etc., as required to accomplish Work. Return to original location as soon as possible.
G. Protect Owner tools, equipment, shelving, stored materials, and equipment, etc., from Work.
Construction Documents 01010 - 4 January, 2018
1.7 FIELD ENGINEERING
A. Field engineering required to locate new equipment.
B. Structural design for equipment as required by Section 16074 - Vibration and Seismic Controls for Electrical Systems.
1.8 REFERENCE STANDARDS
A. For products specified by association or trade standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes or military requirements.
B. Obtain a copy of standards referenced. Maintain a copy at the jobsite during execution of Work to which the standard applies.
C. The date of the standard is that in effect as of the project advertisement date, or effective date of the contract when there was no advertisement, except when a specific date is specified.
1.9 WORK BY OTHERS
A. The Contracting Officer may undertake additional work or award other contracts for additional work for this Project Site and during this Contract Period. The Contractor shall fully cooperate with Government personnel and the other contractors. He shall carefully fit his own work to the additional work as he may be directed by the Contracting Officer.
B. The Contractor shall not commit, nor permit, any act by his personnel which would interfere with the performance of work by any other contractor or by Government employees.
1.10 COORDINATION
A. Coordinate Work of the various Sections of Specifications prior to ordering materials and fabrication to assure efficient and orderly sequence of installation of construction elements, with provisions for accommodating items installed later. Notify Contracting Officer of conflicts between elements prior to installation of any element.
B. Verify characteristics of elements of interrelated operating equipment are compatible;
coordinate Work of various Sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.
C. Coordinate space requirements and installation of electrical Work. Follow routing shown for ducts and conduits as closely as practical. Make piping, duct, and conduit runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.
D. After Owner acceptance of Work, coordinate access to site by various trades for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner and provide access to the Owner for this Work.
Construction Documents 01010 - 5 January, 2018
E. After Substantial Completion, the Owner may install equipment and furnishings.
Cooperate with the Owner and provide access to Owner for this work.
1.11 NOTIFICATION OF COMMENCEMENT OF WORK
A. Prior to commencing work on-site, the contractor shall coordinate with all of the organizations listed on AF Form 103, Base Civil Engineering Work Clearance Request.
The completed form shall be submitted to the Contracting Officer and a copy shall be kept at the work site at all times.
B. The Contractor shall notify the Contracting Officer that work will begin a minimum of seven (7) days prior to commencing work.
1.12 ACCESS TO CONTROLLED AREAS
A. The Contractor shall comply with all Eielson AFB security and access to controlled area procedures and requirements. Initial procedures and requirements will be provided to the Contractor at the Pre-Construction Conference.
1.13 EXISTING FEATURES
A. Refer to the General Contract Clauses for requirements for protection of existing vegetation, structures, equipment, utilities, and improvements.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01010
Repair CH&PP Electric Panels & Circuits, Phase A SECTION 01030
EIELSON AFB, ALASKA SAFETY, ENVIRONMENTAL PROTECTION,
FTQW 18-0504 REGULATIONS, AND CODES
Construction Documents 01030 - 1 January, 2018
SECTION 01030 – SAFETY, ENVIRONMENTAL PROTECTION, REGULATIONS, AND CODES
PART 1 GENERAL
1.1 REQUIREMENTS INCLUDED
A. Reference Standards B. Licenses and Permits C. Safety D. Construction Operation and Safety Plan E. Accident Prevention Plan F. Safety and Health Program G. Fire Safety H. Use of Ionizing Radiation I. Use of Lasers J. Radioactive Materials K. Use of Radio Frequency Radiation L. Use of Ultraviolet Radiation M. Protection of Nesting Birds N. Discovery of Historical or Cultural Artifacts O. Sustainable Procurement Program P. Environmental Protection Q. Environmental Protection Plan R. Hazardous Material Management S. Hazardous Waste T. Hazardous Waste Testing U. Ozone Depleting Substances V. Lead Base Paint W. Asbestos Containing Materials X. Suspected Hazardous Materials Y. PCBs & Oil-Filled or Impregnated Electrical Components Z. Spill Reporting, Contaminant Discovery and Clean-up
Construction Documents 01030 - 2 January, 2018
1.2 COMMONLY USED ACRONYMS
ACM Asbestos Containing Material ADEC Alaska Department of Environmental Conservation A F B Air Force Base AOO Asbestos Operations Officer APDES Alaska Pollutant Discharge Elimination System APO Asbestos Program Officer CO Contracting Officer EPA Environmental Protection Agency EMS Environmental Management System EPCRA Emergency Planning and Community Right-to-Know Act EPP Environmental Protection Plan ESOHTN Environmental, Safety, and Occupational Health Training Network HAZMAT Hazardous Material HAZMART Hazardous Material Pharmacy IRP Installation Restoration Program NOI Notice of Intent NOT Notice of Termination NTP Notice to Proceed PCB Polychlorinated Biphenyl PID Photo Ionization Detector RCRA Resource Conservation Recovery Act RSO Radiation Safety Officer SAP Sampling and Analysis Plan SDS Safety Data Sheet TCLP Toxicity Characteristic Leaching Procedure
1.3 REFERENCE STANDARDS
A. Comply with all applicable laws, building and construction codes and applicable requirements of any governmental agency under whose jurisdiction this Work is being performed.
B. Federal, state and local codes and ordinances take precedence over these specifications and drawings where conflicts occur, unless the drawings or
Construction Documents 01030 - 3 January, 2018 specifications call for more stringent requirements. Notify the Contracting Officer in writing of conflicts.
C. Obtain a copy of standards referenced in the various specification sections.
Maintain a copy at the jobsite during execution of portion of the work to which the standard applies.
D. All work shall be governed by the more stringent provisions of these contract document requirements or the latest published edition or statute- adopted edition, of the following applicable codes, regulations and standards:
ADA Americans with Disabilities Act Accessibility Guidelines AFI Air Force Instructions AS Alaska Statutes AAC Alaska Administrative Code ASTM American Society of Testing and Materials CFR Code of Federal Regulations COE U.S. Army Corps of Engineers COE EM Corps of Engineers Manuals COE ER Corps of Engineers Regulations CSC Alaska Department of Labor Construction Safety Code FAR Federal Acquisition Regulations FWI Fighter Wing Instructions NEC National Electrical Code: NFPA 70 OSHA Occupational Safety and Health Act - Federal and Alaska Regulations
Other applicable codes and standards as applicable or as referenced by the individual specification Sections.
1.4 SUBMITTALS
A. The following applicable items shall be submitted in accordance with Section
01300 – Submittals (Submit hard copies and a pdf copy for each where applicable):
1. Construction Operation and Safety Plan
2. Accident Prevention Plan
3. Safety and Health Program
4. Request for use of Ionizing Radiation (if applicable)
5. Request for use of Lasers (if applicable)
Construction Documents 01030 - 4 January, 2018
6. Request for use of Radioactive Materials (if applicable)
7. Request for use of Radio Frequency radiation (if applicable)
8. Request for use of Ultraviolet Radiation (if applicable)
9. Environmental Protection Plan
10. Solid Waste Weight Tickets
11. Hazardous Materials Inventory (Initial, quarterly & final)
12. Hazardous Waste Accumulation Log (Initial, quarterly & final)
13. Laboratory Test Results (as applicable)
14. NOI for asbestos abatement (if required)
15. Report and Drawings indicating nature and extent of abatement
1.5 LICENSES AND PERMITS
A. The contractor shall obtain and maintain current for the duration of this contract, all required federal, state, and local licenses and permits. All associated fees and taxes shall be paid by the contractor without additional cost to the government.
B. The contractor shall obtain any additional Eielson AFB required permits.
Current base permit requirements shall be provided to the contractor at the preconstruction conference.
1.6 SAFETY
A. Comply with all Federal and State regulations concerning safety of personnel and equipment. Contractors are responsible to provide and ensure personnel have the appropriate personal protective equipment. All Contractor personnel shall wear hard hats and steel toe safety shoes while on the project site. All personnel shall wear hearing protection (ear muffs or ear plugs) when inside the power plant, excluding office areas, rest rooms, break rooms and other “quiet” areas. In addition, comply with the requirements of the U.S. Army Corps of Engineers’ manual, Safety and Health Requirements Manual, EM 385-1-1 and applicable OSHA Standards.
B. Ensure that lock out, tag out procedures are established and used as directed by
29 CFR 1910.145. Comply with lock-out tag-out procedures in use by CH&PP personnel. Ensure that contractor’s personnel on-site are trained on the government’s procedures.
C. Comply with all safety, traffic and protection requirements in effect on Eielson
AFB. The government shall brief the contractor on these requirements at the preconstruction conference.
Construction Documents 01030 - 5 January, 2018
D. Work areas in this Project may be classified as “permit-required confined spaces” or “non-permit required confined spaces.” The contractor’s certified industrial hygienist shall determine the confined space status of the project areas. Regulations and procedures for entry into “permit- required confined spaces” are contained in 29 CFR 1910.146 and 8 AAC 61.010.14. The contractor is responsible for ensuring the safety of his employees in confined spaces according to these regulations.
E. Confined Space Permit: (Include only if applicable.)
1. Provisions for confined space are outlined in 29CFR 1910.146 and ANSI
Z117.1 1989 and shall be followed throughout Project.
2. Base Contact for information regarding confined Space issues is Ground Safety (354 FW/SEG, 377-4260). However, the Contractor shall process any permits required for confined space through his own safety Manager and Permit Space Program.
F. Provide safety barriers around open excavations, openings in floors and other hazards created by the contractor’s activities.
G. The Contracting Officer (CO), or the Contracting Officer’s designee may direct the contractor to cease activities which, in their opinion, are unsafe or which jeopardize operations. However, this provision does not relieve contractor of sole responsibility for safety for project activities.
H. The contractor shall protect base residents and the general public from harm in the construction area.
1.7 CONSTRUCTION OPERATION AND SAFETY PLAN
A. Contractor shall provide a Construction Operation and Safety Plan (COSP) for all construction operations.
B. The COSP shall include the following:
1. Detailed construction schedule and work phasing with dates of operation for work elements.
2. Route maps to and from construction sites for workers and equipment and hazardous material transport routes. Route maps shall include FOD fence locations and requirements.
3. Accident Prevention Plan
4. Safety and Health Program documents.
Construction Documents 01030 - 6 January, 2018
5. The COSP shall be submitted to the Contracting Officer at least 30 days prior to start of construction.
1.8 ACCIDENT PREVENTION PLAN
A. Submit a comprehensive Accident Prevention Plan (APP). The APP shall be similar to the example given in Appendix A of the Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1.
B. The APP shall be job specific and should include work to be performed by subcontractors. The APP shall address measures to be taken to control hazards associated with all operations, materials, services or equipment associated with the Work.
C. The Plan shall include the following sections, as applicable:
1. Name of plan preparer and approving company officer
2. Contractor, contract name & number
3. Copy of current company safety and health policy
4. Responsibilities and lines of authority. Explain who is responsible for site safety and for each specific operation, whether performed by the prime or a subcontractor. Discuss frequency of inspections and documentation.
5. List subcontractors and means of coordinating safety activities.
6. Describe initial new employee training, and periodic safety training. Any specific training required for particular categories of employees. And specific training or meetings occurring prior to specific hazardous activities.
Identify who leads the training or meetings.
7. Describe personal protective equipment (PPE) required for each hazardous work activity.
8. Accident reporting procedures
9. Plans programs and procedures: Address all applicable occupational risks and compliance plans. Plans may include, but are not limited to, the following:
a. Spill plan
b. Fire response plan
c. Posting of emergency phone numbers
Construction Documents 01030 - 7 January, 2018
d. Medical support – on-site and off-site medical support
e. Site sanitation
f. Respiratory protection plan
g. Health hazard control
h. Hazard communication program
i. Lead abatement plan
j. Asbestos abatement plan
k. Fire prevention plan
l. Hazardous energy control plan
m. Critical lift plan
n. Site-specific fall protection and prevention plan
o. Demolition plan
p. Site Safety and Health Plan for hazardous, toxic and radioactive waste work. Hazardous waste site cleanup operations require development and implementation of an SSHP (Site Safety and Health Plan) that shall be attached as an appendix to the APP.
General information adequately covered in the APP need not be duplicated in the SSHP.
q. Confined space plan
10. Risk management for specific project related activities. Provide an Activity
Hazard Analysis (AHA) for project specific hazards and controls that are not covered or are not sufficiently covered by the plans and programs described above.
D. Before beginning each work activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform the work, the Contractors performing the work activity shall prepare an Activity Hazard Analysis (AHA).
E. Each AHA shall define the activities being performed, the work sequence, specific anticipated hazards and control measures to be implemented to eliminate or reduce each hazard to an acceptable level.
F. Work shall not begin until the AHA has been discussed with all engaged in the activity
Construction Documents 01030 - 8 January, 2018
G. AHAs shall be modified as necessary to address changing site conditions.
1.9 SAFETY AND HEALTH PROGRAM
A. The contractor shall have a developed and maintained written Safety and Health Program (SHP) in compliance with the requirements of OSHA standard 29 CFR 1910.120(b) (1) through (b) (4). Relevant portions of 29 CFR 1910 Subpart Z – Toxic and Hazardous Substances; 29 CFR 1926 Subparts 21(b), 651(g), and 800(h) & (i); 8 AAC 61 Subchapter 10; 118 AAC 75; COE ER 385-1- 92; and COE EM 385-1-1. The level of detail provided in the SHP shall be tailored to the type of work, complexity of operations to be accomplished, and the hazards anticipated.
The program shall be designed to identify, evaluate, and control safety and health hazards, and provide for emergency response for hazardous waste operations.
The SHP shall be reviewed and signed by a Certified Industrial Hygienist or Certified Safety Professional. All subcontractors shall comply with the prime contractor’s SHP unless the subcontractor has submitted a separate SHP through the prime contractor. The SHP shall be updated as required. The SHP shall be submitted in its entirety to the contracting officer prior to any work on the site.
B. The SHP shall provide evidence of related safety and health training received by the supervisors and employees. Supervisors’ and employees’ qualifications shall be submitted to the Contracting Officer for review. At least one person certified in first aid and CPR by the Red Cross, or equivalent agency, shall be present on site during all field operations.
C. The Site-Specific Safety and Health Plan part of the SHP shall be prominently displayed at the job site. Alaska Statutes 18.60.066 - .068 shall also be displayed at the same location.
D. NOTE: Safety and health programs developed and implemented to meet other federal, state, or local regulations are considered acceptable in meeting this requirement if they cover or are modified to cover the topics required in this paragraph. An additional or separate safety and health program is not required.
E. The written safety and health program shall incorporate the following:
1. An organizational structure;
2. A comprehensive work plan;
3. A site-specific safety and health plan which need not repeat the employer's standard operating procedures;
4. The safety and health training program;
5. The medical surveillance program;
6. The employer's standard operating procedures for safety and health; and
Construction Documents 01030 - 9 January, 2018
7. Any necessary interface between general program and site specific activities.
F. Contractors and sub-contractors. An employer who retains contractor or sub-contractor services for work in hazardous waste operations shall inform those contractors, sub-contractors, or their representatives of the site emergency response procedures and any potential fire, explosion, health, safety or other hazards of the hazardous waste operation that have been identified by the employer's information program.
G. Program availability. The written safety and health program shall be made available to any contractor or subcontractor or their representative who will be involved with the hazardous waste operation; to employees; to employee designated representatives; to OSHA personnel, and to personnel of other Federal, state, or local agencies with regulatory authority over the site.
H. Organizational structure part of the site program.
1. The organizational structure part of the program shall establish the specific chain of command and specify the overall responsibilities of supervisors and employees. It shall include, at a minimum, the following elements:
a. A general supervisor who has the responsibility and authority to direct all hazardous waste operations.
b. A site safety and health supervisor who has the responsibility and authority to develop and implement the site safety and health plan and verify compliance.
c. All other personnel needed for hazardous waste site operations and emergency response and their general functions and responsibilities.
d. The lines of authority, responsibility, and communication.
2. The organizational structure shall be reviewed and updated as necessary to reflect the current status of waste site operations.
I. Comprehensive work plan part of the site program. The comprehensive work plan part of the program shall address the tasks and objectives of the site operations and the logistics and resources required to reach those tasks and objectives.
1. Address anticipated clean-up activities as well as normal operating procedures which need not repeat the employer's procedures described elsewhere.
2. Define work tasks and objectives and identify the methods for accomplishing those tasks and objectives.
Construction Documents 01030 - 10 January, 2018
3. Establish personnel requirements for implementing the plan.
4. Provide for the implementation of the required training.
5. Provide for the implementation of the required informational programs.
6. Provide for the implementation of the medical surveillance program.
J. Site-specific Safety and Health Plan (SSHP) part of the program. (Refer to SSHP requirements in 02055 Selective Demolition)
K. Pre-entry briefing. The site-specific safety and health plan shall provide for pre-entry briefings to be held prior to initiating any site activity, and at such other times as necessary to ensure that employees are apprised of the site safety and health plan and that this plan is being followed. The information and data obtained from site characterization and analysis shall be used to prepare and update the site safety and health plan.
L. Effectiveness of site safety and health plan. Inspections shall be conducted by the site safety and health supervisor or, in the absence of that individual, another individual who is knowledgeable in occupational safety and health, acting on behalf of the employer as necessary to determine the effectiveness of the site safety and health plan. Any deficiencies in the effectiveness of the site safety and health plan shall be corrected by the employer.
M. Written hazard communication program. Employers shall develop, implement, and maintain at each workplace, a written hazard communication program which at least describes how the criteria for labels and other forms of warning, safety data sheets, and employee information and training will be met, and which also includes the following:
1. A list of the hazardous chemicals known to be present using a product identifier that is referenced on the appropriate safety data sheet (the list may be compiled for the workplace as a whole or for individual work areas); and,
2. The methods the employer will use to inform employees of the hazards of non-routine tasks (for example, the cleaning of reactor vessels), and the hazards associated with chemicals contained in unlabeled pipes in their work areas.
N. Multi-employer workplaces. Employers who produce, use, or store hazardous chemicals at a workplace in such a way that the employees of other employer(s) may be exposed (for example, employees of a construction contractor working on-site) shall additionally ensure that the hazard communication program includes the following:
1. The methods the employer will use to provide the other employer(s) on-site access to safety data sheets for each hazardous chemical the other employer(s)' employees may be exposed to while working;
Construction Documents 01030 - 11 January, 2018
2. The methods the employer will use to inform the other employer(s) of any precautionary measures that need to be taken to protect employees during the workplace's normal operating conditions and in foreseeable emergencies;
and,
3. The methods the employer will use to inform the other employer(s) of the labeling system used in the workplace.
O. The employer may rely on an existing hazard communication program to comply with these requirements.
P. The employer shall make the written hazard communication program available, upon request, to employees, in accordance with the requirements of 29 CFR
1910.1020 (e).
Q. Where employees must travel between workplaces during a work shift, i.e., their work is carried out at more than one geographical location, the written hazard communication program may be kept at the primary workplace facility.
1.10 FIRE SAFETY
A. Comply with all fire safety and protection requirements in effect on Eielson AFB.
The government shall brief the contractor on these requirements at the preconstruction conference. For installation of fire-suppression systems that are chemical based, contact Air Quality Program Manager prior to purchase to ensure it complies with 40 CFR 82 (SNAP-approved chemical).
B. Prior to beginning any welding, use of open flame device, or any activity that produces sparks, obtain a “hot work permit” (AF Form 592, Hot Work Permit) from base Fire Department. The permit shall be renewed each day welding or open flame devices shall be used.
1. If the contract work requires numerous days of hot work, the contractor may elect to have one of his on-site personnel designated as a Permit Authorizing Individual (PAI). The contractor’s PAI may issue hot work permits at the work site, thus avoiding the requirement for daily permits issued by the Fire Department.
2. The contractor’s PAI shall be the on-site superintendent, a foreman, the contractor’s safety manager, or other individual with sufficient knowledge and experience to recognize unsafe work practices or conditions and having authority to stop work immediately if such unsafe practices or conditions are observed. To be designated as a PAI, a person must schedule and successfully complete PAI certification training offered by the base Fire Department. The PAI certification training is estimated to last 60 to 90 minutes and will be valid for the duration of the contract.
Construction Documents 01030 - 12 January, 2018
3. Fire Department personnel may periodically visit the site to ensure the contractor is complying with fire safety requirements. A PAIs certification may be revoked if the PAI has failed to issue permits on days when hot work is performed, or if unsafe practices or conditions are observed.
4. Questions concerning these requirements may be directed to Fire
Prevention Office, 354 CES/CEFT, Eielson AFB, 377-1293.
C. The contractor shall notify the Fire Department at 377-4156 and Fire Prevention Section at 377-1293 a minimum of 72 hours before, and again immediately prior to, temporarily closing any street or building access, interrupting water service to any fire hydrant or interrupting the operation of any fire detection, alarm or suppression system. The fire department shall be immediately notified upon reopening closed areas, restoration of water service to any fire hydrant, or reactivation of any detection, alarm or suppression system. Additionally, any out of service hydrants will be covered and secured with a black bag to easily identify it is “out of service”. This notification requirement is in addition to other contract requirements.
D. Provide a 10 lb, ABC fire extinguisher at all work areas.
1.11 USE OF IONIZING RADIATION (IR)
A. Submit a written request for approval at least 30 calendar days before commencement of activities which require the use of IR generating devices.
B. Submit request to the Base Radiation Safety Officer (RSO) at the Bioenvironmental Engineering Office (354 MDOS/SGOJ, Phone: 377-6687) with a courtesy copy to the Contracting Officer. Request shall include:
1. Description/Characteristics:
a. X-ray unit manufacturer.
b. Model number.
c. Serial number.
d. Maximum kVp, mA, Sec.
e. Ionizing radiation source/emitter (electron tube).
2. The part of the Air Force contract describing work to be done at the base and the inclusive dates of such work.
Construction Documents 01030 - 13 January, 2018
3. An acknowledgment that the RSO may make initial and periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel.
1.12 USE OF LASERS
commencement of activities which require the use of a laser.
B. Submit request to the RSO with a courtesy copy to the Contracting Officer. Request shall include:
1. Description/Characteristics:
a. Manufacturer.
b. Model.
c. Number of same units.
d. Serial number(s).
e. Laser medium.
f. Mode of operation (i.e. continuous wave (CW), single pulse, multiple pulse).
g. Maximum exposure time (train length).
h. Time (sec) & wavelength.
i. Energy/pulse (J) or CW power (W).
j. Pulse repetition frequency.
k. Pulse width.
l. Beam diameter (at 1/e point).
m. Beam divergence (at 1/e point).
2. The part of the Air Force contract describing work to be done and the inclusive dates of such work.
3. An acknowledgment that the RSO may make initial and periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel.
1.13 RADIOACTIVE MATERIALS (RAM):
A. Prior to bringing RAM onto Eielson AFB property, the contractor shall obtain permission from the RSO. To obtain approval, forward an application to the RSO and a courtesy copy to the Contracting Officer at least 30 calendar days before the planned date for commencement of activities on the installation. Requests shall include:
Construction Documents 01030 - 14 January, 2018
1. A description of the proposed activities on NRC Form 241, Report of Proposed Activities in Non-Agreement States, (the 180-day limitation on the form does not apply to organizations holding an NRC license). Contractors possessing Agreement State Licenses shall also submit an NRC Form 241 to NRC in compliance with 10 CFR 150.21. Contractors requiring more than 180 days of operation per calendar year on the installation shall possess an NRC license.
2. The procedures established to ensure radiological health and safety of Air Force personnel and the public while on Air Force installations on site and the name of the responsible contractor representative.
3. A current copy of the applicable NRC, or Agreement State license. Expired licenses are unacceptable. To be valid at the installation, the license must either specifically state the installation by name on the license or state approval for work at temporary job sites anywhere in the United States where the NRC or Agreement State maintains jurisdiction. DoE or DoE prime contractors must provide, in lieu of a license, written certification of their exemption from NRC licensing requirements and cite the applicable exemption of 10 CFR.
4. The part of the Air Force contract describing work to be done and the inclusive dates of such work.
5. An acknowledgment that the base RSO may make periodic checks to ensure the contractor is following applicable radiological health and safety practices which prevent unnecessary exposures to Air Force personnel and prevent potential contamination of government property.
1.14 USE OF RADIO FREQUENCY (RF) RADIATION
A. Prior to using equipment generating RF radiation in excess of seven watts peak power and a frequency of 1000 MHz or greater on Eielson AFB, the contractor shall submit a written request for approval at least 30 calendar days before commencement of activities, which require the use of the RF generating device.
B. Submit request to the RSO, with a courtesy copy to the Contracting Officer.
Submittal shall include:
1. Description.
2. Nomenclature.
3. Location of emitters.
4. Quantity.
5. Frequency (MHz).
6. Pulse width (microsecond.).
7. Pulse repetition freq. (pps).
Construction Documents 01030 - 15 January, 2018
8. Peak power (kW).
9. Antenna size (feet--horizontal/vertical).
10. Antenna bandwidth (degrees-- horizontal/vertical).
11. Antenna gain (dB).
12. Scan rate (rpm).
13. The part of the Air Force contract describing work to be done at the base and
14. An acknowledgment that the RSO may make initial and periodic checks to
1.15 USE OF ULTRAVIOLET (UV) RADIATION
commencement of activities which require the use of UV generating devices on Eielson AFB.
B. Submit request to the RSO, with a courtesy copy to the Contracting Officer.
Request shall include:
1. The part of the Air Force contract describing work to be done at the base and
2. An acknowledgment that the RSO may make initial and periodic checks to
1.16 PROTECTION OF NESTING BIRDS
A. Federal law prohibits disturbing bird nests containing eggs or birds too young to fly. Harassment of birds to force them to abandon an occupied nest is also illegal. If the contractor removes nests or harasses birds in violation of federal and state law, the contractor is responsible for any charges filed by US Fish and Wildlife Service or State of Alaska Department of Public Safety and is the liable party.
B. If an occupied bird nest is discovered, the contractor shall cease activities in the vicinity of the bird nest until the young birds are able to fly and leave the nest under their own power.
Construction Documents 01030 - 16 January, 2018
C. Cliff swallow nests are usually the greatest threat to construction projects. As a general rule, cliff swallows can begin nest construction any time between 10 May and 21 July.
D. The contractor shall be responsible for control of new nest construction after issuance of Notice to Proceed (NTP). The contractor shall survey the work area daily for new nest construction. To avoid project delays, the contractor shall remove all nests discovered before the nests have been completed and occupied.
E. The contractor shall be responsible for any increased cost or delay resulting from a nest constructed and occupied in the work area after NTP has been issued.
1.17 DISCOVERY OF HISTORICAL OR CULTURAL ARTIFACTS
A. Should any historical artifacts or cultural resources be unearthed, stop excavating and immediately notify the Contracting Officer.
1.18 SUSTAINABLE PROCUREMENT PROGRAM
A. The contractor is encouraged to recycle materials that shall be discarded as waste.
Items that can be recycled in this community are asphalt, metals (including, but not limited to aluminum, tin, and steel), antifreeze, batteries, paper/cardboard, plastics, and used oil. This list is not all inclusive.
1. Sustainable Procurement is the purchase of sustainable and environmentally preferable products and services in accordance with federally mandated "green" procurement preference programs. The purpose of the SPP is to enhance and sustain mission readiness through cost effective acquisition that achieves compliance and sound management of the AF’s financial, natural, and energy resources. Through the P2 methodology outlined below, all AF organizations making purchases or product specifications for purchases will use the SPP as a routine part of day-to-day purchasing activities to reduce resource consumption and solid and HW generation. (T-1). 6.5. P2 Methodology.
B. These standards apply to all new construction, demolition, rehabilitation, alteration, modification, repair, and maintenance of existing facilities.
1. In an effort to comply with the affirmative procurement requirements of Section 6002 of the Resource Conservation Recovery Act (RCRA) and Executive Order 13693 in addition to EO 13693, the government strongly promotes the use of the recycled and recovered materials and products identified in the Environmental Protection Agency’s Comprehensive Procurement Guidelines.
Construction Documents 01030 - 17 January, 2018
2. Recycled and recovered materials and products shall be considered first before any other materials and products shall be accepted. Recycled and recovered materials and products shall be used throughout the project unless they either do not meet the requirements of this specification, delay the progress of the work, or are cost prohibitive.
3. Detailed below are examples of some materials and products. These are recommended quantities and represent minimum compliance. The actual requirement is to use the maximum amount of recycled material possible, while meeting the performance specifications. Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials, and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit http://www.epa.gov/epawaste/conserve/tools/cpg/products for a complete list of designated products and the associated recommended content levels. Offerors must be able to demonstrate that each offered product meets minimum content levels upon request."
Type Material Recycled Material % Insulation Rock wool Slag 75 Fiberglass Glass cullet 20-25 Loose fill & spray on (cellulose) Postconsumer paper 75
Perlite composition board Postconsumer paper 23 Plastic rigid foam Recovered material 9 Foam-in place Recovered material 5 Glass fiber reinforced Recovered material 6 Phenolic rigid foam Recovered material 5 Wall Board Structural fiberboard 80-100 Laminated paperboard Postconsumer paper 100 Carpet Polyester carpet face fiber Excludes severe wear applications 25-100
Playground surfaces Rubber or plastic 90-100 Running tracks Rubber or plastic 90-100 Cement/Concret e
Concrete & cement Coal fly ash 15-35
Concrete & cement Ground granulated blast furnace (GGBF)
25-50
Flooring/Patio Patio blocks Plastic or plastic blends 90-100 Patio blocks Rubber or rubber blends 90-100 Floor tiles Rubber 90-100 Floor tiles Plastic 90-100
Construction Documents 01030 - 18 January, 2018
Recreational Surface
Playground surface Rubber or plastic 90-100
Running track Rubber or plastic 90-100
Landscaping
Paper based hydraulic mulch
Postconsumer paper 100
Wood based hydraulic mulch
Recovered wood and/or paper
Compost 100
1.19 ENVIRONMENTAL PROTECTION
A. The Contractor shall comply with all applicable federal, state, and local laws and regulations covering environmental pollution control and abatement, and the specific requirements stated elsewhere in the contract specifications. In addition, the contractor shall comply with any applicable base instructions and plans. If requirements differ between any of the regulatory agencies, the most stringent requirement applies.
B. All general construction wastes, other than those specifically allowed, or required to be disposed of on-base shall be legally disposed at an off-base sanitary landfill.
Maintain weight ticket receipts for submission to Eielson Solids Waste Manager.
Handling and disposal of hazardous materials and hazardous wastes is described later in this Section. See Appendix with procedure letters for specific materials that need to be disposed of by other methods. Battery disposal is included as part of these letters, and Lithium and Lithium ion batteries need to be separated as part of the disposal.
C. Before disposal of concrete in Spruce Lake, located on the corner of Quarry
Road and Industrial Ave., the contractor shall complete the C&D form at the end of this Section (Appendix B). For Quarry Hill, contractor must also obtain permission from 354 CES/CEIEC Solid Waste Program Manager and 354 CES/CEOHP Range. To retain concrete disposal privileges the contractor will provide reports weekly to CEIEC. These reports may be faxed to CEIEC at 377-3367.
D. Comply with the requirements of the “Eielson AFB Waste Disposal\Borrow
Pit Plan” in the appendices of this specification section.
E. Part II, Eielson AFB Waste Disposal / Borrow Pit Worksheet.
1. The contractor shall dispose of hazardous waste at appropriate on or off base facilities in properly marked containers with sample analyses provided 10 days prior to waste transport. Waste shall be properly disposed of off base unless disposal on base is specifically allowed by contract. The following rules shall be followed for disposal:
Construction Documents 01030 - 19 January, 2018
a. Off base disposal: Submit all weight tickets/manifests to 354 CES/CEIEC Solid Waste Program Manager.
1) All hazardous and non-hazardous waste manifests shall be signed by a designated Eielson POC in accordance with Eielson's current Waste Manifest Delegation of Authority Letter. Please contact the Hazardous Waste Facility at 377-1668 for signature. Copies of all manifests shall be provided to 354 CES/CEOIC, Hazardous Waste Facility Manager.
2) All non-hazardous solid waste weight tickets shall be submitted to 354 CES/CEIEC Solid Waste Program Manager, 377-1659.
b. On base disposal (if allowed by contract):
1) Concrete – Concrete shal l be screened for asbestos, POLs, LBP and glycols prior to disposal. All painted concrete shal l be screened for LBP using XRF. If results are greater than 1 mg/cm2, then a Toxic Characteristic Leaching Procedure (TCLP) test s h a l l be performed prior to disposal. At no time can the concrete contain free flowing liquids. Submit the completed C&D form prior to disposal.
2) Asbestos Containing Material: All disposal shall be coordinated through the 354 CES/CEIEA. If Eielson’s asbestos landfill is used for disposal, contact the base Insulation Shop (354 CES/CEOII). Waste shall be properly contained.
F. Comply with the Spill Reporting Procedures for both contractor caused spills and suspected contaminated soils or water found during excavation, new or not as prescribed in the Appendices. Retain signed copies at the contractor’s on-site office throughout construction.
G. Post the spill reporting placard (Example located at the end of this Section) at the on-site office in a conspicuous location. Ensure employees and subcontractor employees are aware of the location of the placard and of proper reporting procedures.
H. Comply with the Eielson AFB Fugitive Dust Emission Plan. Fugitive dust emissions
(airborne dust generated by vehicles operating on unpaved surfaces, transfer or transport of dust producing materials, soil stockpiling, etc.) shall be controlled at the construction site, along haul routes and at staging areas. Water spraying shall be conducted as necessary, determined by contracting officer, to minimize fugitive dust generation. Limit traffic speeds on all unpaved road surfaces to 15 mph. Any uncontaminated dirt or mud, which is tracked onto paved roadways shall be cleaned
Construction Documents 01030 - 20 January, 2018 away that day. Depending on conditions, the roadway will be watered before cleaning or if a street sweeper is used, it will have a water system that controls dust around the sweeper during operation. Reference the Appendices - 2001 Eielson AFB Fugitive Dust Emission Plan.
1.20 ENVIRONMENTAL PROTECTION PLAN
A. The contractor shall submit, and comply with the approved provisions of an Environmental Protection Plan.
B. Two weeks prior to commencing construction activities or delivery of materials to the site, the contractor shall submit an Environmental Protection Plan for review and approval by the Contracting Officer and the 354 CES/CEIEC. The purpose of the Environmental Protection Plan is to present a comprehensive overview of known or potential environmental issues which the contractor must address during construction. The contractor shall address each topic at a level of detail commensurate with the environmental issue and required construction task(s).
The contractor shall include environmental issues associated with the specific project.
This is the start of the file's text. The full file is on GovTribe.