JA-1_SOW.pdf
PDF 9 KB Posted
- Attached to
- CHPP Phase A Federal contract opportunity
- Solicitation number
- FA5004-18-B-C004
About this file
JA-1 SOW for CHPP Phase A- Eielson AFB AK
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Phase_A_Bidder_Q&A.pdf | ||
| FA500418BC0040001.pdf | ||
| JA-5_Drawings.pdf | ||
| FA500418BC004.pdf | ||
| JA-2_Specs.pdf | ||
| JA-4_Wage_Determination.pdf | ||
| JA-3_AF_Form_66.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SYNOPSIS OF WORK
PROJECT TITLE: REPAIR CH&PP ELECTRIC PANELS & CIRCUITS, PHASE A
LOCATION: EIELSON AFB, ALASKA
PROJECT: FTQW 18-0504
DESCRIPTION OF WORK:
Work includes upgrading and modifying the low voltage electrical and lighting systems at Eielson’s Central Heat & Power Plant (CH&PP). the Contractor shall provide new automatic transfer switch, and dedicated lighting transformer; provide an emergency lighting inverter with battery back-up, and an emergency lighting panel; and provide new light fixtures, conduit, conductors boxes and appurtenances to replace the light fixtures in the basement and on the first floor of the CH&PP. Demolish the existing light fixtures and associated conduit, conductors and appurtenances in the basement and on the first floor of the CH&PP. Provide temporary services and lighting as necessary to maintain CH&PP operations throughout the construction period.
Surfaces within the plant are covered in settled dust. Much of the dust contains silica and heavy metals. Many of the surfaces in the plant are coated with lead-based paint and there are asbestos containing materials within the plant. The contractor shall take appropriate measures to avoid exposing his workers to unacceptable hazards.
Estimated Project Cost is between $1,000,000 and $2,000,000.
END OF SYNOPSIS