Attachment_12_Q&A_(27-Mar-17).pdf

PDF 977 KB Posted

Attached to
JBER MACC Federal contract opportunity
Solicitation number
FA5000-17-R-0007
Issued by
Department of the Air Force Pacific Air Forces

About this file

Add Attachment 12 Q & A. Provides answers to contractor submitted questions (Numbers 1-6).

View the file

Other files for this federal contract opportunity

Other files attached to JBER MACC, newest first.
File Type Posted
Attachment_1_Wage_Determinations.pdf PDF
Q&A_(12_Apr_2017).pdf PDF
Attachment_10_PPI_Tool_(6_Apr_2017).pdf PDF
Attachment_4_Seed_Project_(17_April_2017).pdf PDF
FA5000-17-R-0007-0004.pdf PDF
FA5000-17-R-0007-0003.pdf PDF
Pre-Proposal_Slides_&_List_of_attendees.pdf PDF
FA5000-17-R-0007-0002.pdf PDF
Attachment_9_Reserved.pdf PDF
Attachment_1_Wage_Determinations.pdf PDF
Attachment_4_Seed_Project.pdf PDF
FA5000-17-R-0007-0001.pdf PDF
Attachment_4_Seed_Project_v2.pdf PDF
ppi_tool.accdb —
Attachment_2_Weather_Data.pdf PDF
Attachment_5_Price_Schedule.pdf PDF
Attachment_7_PPQ.pdf PDF
Attachment_4_Seed_Project.pdf PDF
Attachment_1_Wage_Determinations.pdf PDF
Attachment_11_NAFI_GENERAL_PROVISIONS.pdf PDF
FA5000-17-R-0007_JBER_MACC.pdf PDF
Attachment_10_PPI_Tool.pdf PDF
Attachment_8_Financial_Data_Form.pdf PDF
Attachment_9_Teaming_consent_form.pdf PDF
Attachment_6_PPCL.pdf PDF
Attachment_3_SOW.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION # PAGE # REFERENCE QUESTION/COMMENT ANSWER/RESPONSE

1 44 Solicitation Section L (B)(2)(b)/Solicitation Attachment 7

Please clarify if PPQs previously completed by reference POCs can be used and submitted to robert.peters.11@us.af.mil <mailto:robert.peters.11@us.af.mil> and jonathan.roddy@us.af.mil <mailto:jonathan.roddy@us.af.mil> ?

No. Section L (B)(2)(b) of the Proposal Prep Instructions states the filled out PPQ’s must come directly from the POC. Solicitation Attachment 7 Past Performance Questionnaires are specific to this acquisition.

2 32 Solicitation Section J Attachment 9

Section L.B.2(d), the evaluation of past performance information, (iv) will not take into account past performance regarding subcontractors. Please clarify the intent, need, and definition of Teaming Partner relative to Attachment 9, Teaming Partner Consent Form.

Amendment 01 Removed Teaming Consent Form. We will not be evaluating the past performance of subcontractors.

3 Please clarify where in the Past Performance Proposal offerors are to place Attachment 9, Teaming Consent Form.

See Section J Attachment 9 Teaming consent form has been removed and no longer part of this solicitation. However, the “roadmap” submitted with the proposal should describe the company to include any Joint Venture information.

4 48 Solicitation Section M (A)

Section M.A states “The offeror’s TEP will be determined by multiplying the quantities identified on the price schedule (attachment 5 Price Schedule) by the unit price, limited to two decimal places, for each Contract Line Item Number (CLIN) to confirm the total cost for each CLIN; the sum of all total cost amounts will be the offeror’s total proposed price.” Please verify there is only one CLIN as per the Price Schedule Attachment 5.

Verified. There is only one CLIN.

Section L.B.1(d) states “The Price Schedule shall be the only place in the RFP that a price will be written.” Attachment 5, Price Schedule also states “An offer which does not contain separately-priced schedules will not be considered and the price on each schedule shall include an approximate apportionment of all estimated direct costs, allocable indirect costs, and profit.” Please clarify what information is requested and if additional estimated direct costs, allocable indirect costs, and profit are to be submitted that it shall be in submitted in PDF format in accordance with Section L.C.4(h).

Only the total price for CLIN 0001 is requested.

Attachment 4, Seed Project_v2 states “Award shall be made to the lowest priced offeror who receives a contract, based upon the total construction cost for CLIN 0001 determined to have met the solicitation requirement and whose price can be determined fair and reasonable. Technical proposals or other narratives are not requested and will not be considered.” Please verify if offerors may prepare cost assumptions in lieu of providing a technical proposal in the apportionment of estimated costs.

Only the total price input on the Price Schedule (Attachment 5) will be evaluated. A “cost assumption” is not requested and will not be considered.

Solicitation Section J Attachment 5

Solicitation Amendment 01

Solicitation Amendment 01