Questions and Answers dated 30 June 2016. The Government can no longer guarantee a timely response to any further questions.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_FA4890-15-R-0019-0002.pdf | ||
| Conformed_Copy_Solicitation_FA4890-15-R-0019-0002.pdf | ||
| Attachment_2_-_Performance_Work_Statement_19_Aug_16.pdf | ||
| FA4890-15-R-0019_Qs As.pdf | ||
| REVISION__1_Attachment_1_-_Subfactor_3_Scenario_16Jun16.pdf | ||
| REVISION__1_Attachment_2_-_Performance_Work_Statement_16Jun16.pdf | ||
| REVISION__1_FINAL_RFP_Jeep_J8_16Jun16.pdf | ||
| Jeep_J8_Pre-Proposal_Conference_Participants_16Jun16.xlsx | XLSX spreadsheet | |
| Attachment_2_-_Performance_Work_Statement.pdf | ||
| Attachment_1_-_OCONUS_Scenario.pdf | ||
| FINAL_RFP_Jeep_J8_6Jun16.pdf | ||
| Attachment_4_-_PWS_Appendix_D.pdf | ||
| Jeep_J8_Redacted_J A.pdf | ||
| Attachment_3_-_PWS_Appendix_C.pdf | ||
| Sources_Sought_Notification_11Feb16.docx | DOCX document | |
| Draft_PWS_Jeep_J8_11_Feb_15.docx | DOCX document | |
| Draft_PWS_Jeep_J8_RFI.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4890-15-R-0019: Questions and Answers
Question
No.
Ref. Question/Comment Government Response
Instruction for
Volume II, Pricing Factor
2 (page 42)
Instruction for Volume II, Pricing
Factor 2 (page 42) states: The offeror shall complete Schedule B of the solicitation (Schedule of
Supplies and Services (CLINS)) by inserting the price elements (unit price and extended amount) for all
Firm Fixed Price (FFP) contract line item numbers (CLINS) for all ordering periods.
Question: Is Schedule B a separate attachment, or are we to create a spreadsheet or just complete pages
3-35 with the unit price and max amount?
The offeror will create a spreadsheet, titled Schedule B, and will complete pages 3-35 with the unit price and max amount.
Page 50 of the
RFP
Page 50 of the RFP states: “Place of manufacture” means the place where an end product is assembled out of components, or otherwise made or processed from raw materials into the finished product that is to be provided to the
Government. If a product is disassembled and reassembled, the place of reassembly is not the place of manufacture.
Question: Does the USG have an issue if the “place of Manufacture” is outside the United States but in a friendly country?
No, but the USG needs to know the place of manufacture.
Ref. Question/Comment Government Response
Attachment 1
(OCONUS
Scenario)
Attachment 1 (OCONUS Scenario) states: FOB: Destination.
Question: Should we use the port as the final destination for this scenario or is there a specific location that should be used?
A specific location will be used:
Physical Address of Delivery:
Embajada De Los Estados
Unidos De America
Attn: MILGRP
Avenida Reforma 7-01, Zona 10
Guatemala, Guatemala 01010
Shipment Consignee:
Embajada De Los Estados
Unidos De America
Attn: MILGRP
Avenida Reforma 7-01, Zona 10
Guatemala, Guatemala 01010
Shipment Point of Contact: Mr.
Kevin P. Koob
Page 40 of the
RFP
Page 40 of the RFP (pages Not include in Page Count) states: The organizational chart, acronym list, ISO registration verification, and overview section (for exceptions) will not be included in the page count.
Question: Is it acceptable to provide a company overview outside of the page count?
No, a company overview will be included in the page count.
Ref. Question/Comment Government Response
Page 20 of the
PWS
The Performance Work Spec
(PWS) on page 20 states: the
Management Plan will be submitted as part of the contract proposal and will be incorporated into the contract. It is also covered in
Deliverable 1’s requirements. This requirement was not covered in the
Instructions for Volume 1, Technical on page 41 of the RFP or the evaluation factors on page 48.
Question: Should the management plan as outlined in the PWS be covered in Subfactor 3 (OCONUS
Scenario) and what will be the criteria for evaluation?
The Government has removed the requirement for a
Management/Staffing Plan
(Deliverable 01) from PWS
Table 2 and Paragraph 7.4.1.
These sections are marked as
“Reserved.” The contractor’s proposal shall address its management and staffing approach used to satisfy PWS requirements under Sub-Factors
1 through 3, as applicable. The
Government will provide a revised PWS in a RFP amendment.
(Deliverable
9) of the PWS
Page 21 (Deliverable 9) of the PWS states: The Equipment
Composition List will be submitted with the initial proposal. This requirement was not covered in the
Instructions for Volume 1, Technical on page 41 of the RFP or the evaluation factors on page 48.
Question: Should the Equipment
Composition Listing be covered in
Subfactor 2 (MOST), and we would like to clarify what sections of the
Deliverable 9 should be included in the proposal?
The equipment composition list will be evaluated under Factor 2, Price. All three sections of
Deliverable 09, as identified in
PWS, Paragraph 7.4.9 shall be included in the proposal. The
Government revised the PWS, Paragraph 7.4.9 to update
Equipment Composition Listing
(D09) information requirements.
The Equipment Composition
Listing (D09), Sections 1, 2, and
3 will be evaluated as part of
Factor 2, Price; however, the contractor shall use the
Government-provided, not to exceed, plug number to build its total evaluated price.
Ref. Question/Comment Government Response
Volume 2, Pricing Factor
2.
CLIN 1009
We would like to be absolutely sure of the specific information you require with reference to Volume 2, Pricing Factor 2.
Starting with CLIN 1009:
Is it sufficient to provide the list of our recommended parts along with the individual part prices? Or do we have to put in a unit price for the whole kit? Because the Parts and Tool Kits will vary from variant to variant. Obviously the kits for an armored vehicle will differ to those for a Troop Carrier, for example.
This question was answered partially in a previously response to question 6.
In our response we stated “The equipment composition list will be evaluated under Factor 2, Price. All three sections of
Deliverable 09, as identified in
PWS, Paragraph 7.4.9 shall be included in the proposal. The
Government revised the PWS, Paragraph 7.4.9 to update
Equipment Composition Listing
(D09) information requirements.
The Equipment Composition
Listing (D09), Sections 1, 2, and
3 will be evaluated as part of
Factor 2, Price; however, the contractor shall use the
Government-provided, not to exceed, plug number to build its total evaluated price.” Also as part of the response to the above question a revised PWS was posted to FED Biz Ops on 16
Jun 2016. In the revised PWS states under paragraph 7.4.9.2
Section 2 – “Composition of the spares kits specified in PWS
Paragraph 3.2. This listing shall include the OEM part number, item description, unit of issue, unit price, and quantity for all parts provided in each spares kit.
The listing shall also identify the total cost for each spares kit.”
Please ensure that for all spares kits proposed paragraph 7.4.9.2 is followed and the total cost for each kit is identified.
Ref. Question/Comment Government Response
Volume 2, Pricing Factor
2.
CLIN 1010
Similarly, with CLIN 1010 is it sufficient to have a fully comprehensive list of part numbers and prices, or do we list one price for all? (Because not all parts would be required for every variant. For example, armored glass would only be required for armored vehicles)
See response to question 7.
Volume 2, Pricing Factor
2.
CLINS 1012,
1013, and
Can you confirm we are not expected to put in a unit price?
(Because quantities are unknown at this stage)
In your proposal please use the
NTE plugged cost of $500,000 for CLIN 1012, $140,000 for
CLIN 1013, and $27,000 for
CLIN 1014 that is in the RFP.
PWS para
3.2.2
Page 12, para 3.2.2 of the
Performance Work Spec states:
Each spares kit shall provide sufficient quantities to support 10 vehicles for 12 months of operation.
The spares kits shall support both scheduled and unscheduled maintenance.
Question: Does the 10 vehicles for
12 months apply to each variant when constructing the spares kit?
The only requirement as identified in paragraph 3.2.2 of the PWS was that the spares kits be built by system. It is up to the contractor whether or not those systems kits are built by each of the different J8 configurations identified in Table 1 of the
PWS. Please ensure the spares kits are provided in the format identified for the equipment composition listing identified in paragraph 7.3.9 of the PWS.
PWS para
3.2.2
How should we define how much unscheduled maintenance will occur so we can identify the quantities for each spares kit?
The quantity of spares identified for unscheduled maintenance should be based on the contractor’s past experience with supporting Jeep J8’s in the field, similar to or in the
SOUTHCOM AOR.