Worksheet Instructions
1. Please do not modify any of the formulas within the Speadsheet.
2. Please only input the Unit/Hourly/Daily/Liter Rates on the left side of the Spreadsheet. The Right side should Auto fill once you input your Rates.
3. Please do not modify the quantities listed.
4. Please do not modify the amount listed in the Reimbusable Expense Line. This amount is a plug figure so all proposals have the same amount.
5. The Proposed rate inputted in the Supplemental Base Fee will be the cost that will be evaluated. Since the location of the helicopters are unknown each day, this CLIN will be invoiced IAW PWS Appendix 2, Para 4.1.. This CLIN will be funded for 244 days based off the rates proposed.
6. Please only input your rates on the Base Year, Option Year 1, Option Year 2 and Option Year 3 Tabs. The Summary Tab will Auto fill once you complete the other tabs.
7. This worksheet will be incorporated into the contract of the winning offeror.
Summary
NWS ROTARY WING AIRLIFT CONTRACT
| Description | Base Yr | Option Yr 1 | Option Yr 2 | Option Yr 3 | Option Yr 4 | Totals |
| Transition | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Main Base Fee | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Rotary Wing Flying Hours | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Cost Riemburseable | $ 688,148.00 | $ 1,376,295.00 | $ 1,543,405.00 | $ 1,722,417.00 | $ 1,774,090.00 | $ 7,104,355.00 |
| Supplemental Base Fee | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| Rotary Wing Bulk Fuel Transfer | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| $ 688,148.00 | $ 1,376,295.00 | $ 1,543,405.00 | $ 1,722,417.00 | $ 1,774,090.00 | $ 7,104,355.00 |
Cost Summary
| Description | IGCE | % of Total |
| Transition | $ - 0 | 0.00% |
| Main Base Fee | $ - 0 | 0.00% |
| Rotary Wing Flying Hours | $ - 0 | 0.00% |
| Cost Riemburseable | $ 7,104,355.00 | 100.00% |
| Supplemental Base Fee | $ - 0 | 0.00% |
| Rotary Wing Bulk Fuel Transfer | $ - 0 | 0.00% |
| Total | $ 7,104,355.00 | 100% |
Base Year Base Period (1 Oct 15 - 31 Mar 16) - Estimated Cost Summary
| CLIN | Description | IGCE | % of Total |
| 0001 | Transition | $ - 0 | 0.00% |
| 0002 | Main Base Fee | $ - 0 | 0.00% |
| 0003 | Rotary Wing Flying Hours | $ - 0 | 0.00% |
| 0004 | Cost Riemburseable | $ 688,148.00 | 100.00% |
| 0005 | Supplemental Base Fee | $ - 0 | 0.00% |
| 0006 | Rotary Wing Bulk Fuel Transfer | $ - 0 | 0.00% |
| Total | $ 688,148.00 | 100% |
CLIN 0001 FFP
| Transition | | | | | FFP Amount | | | |
| Description | QTY | Unit | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Transition | 2 | Months | $ - 0 | $ - 0 | 2 | Months | $ - 0 | $ - 0 |
| Transition Total | | | $ - 0 | | | | $ - 0 |
| CLIN 0002 FFP | | | | | | | | |
| Main Base Fee | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Base fee Zone 1 - Inuvik | 6 | Months | $ - 0 | $ - 0 | $ - 0 | 6 | Months | $ - 0 | $ - 0 |
| Base fee Zone 2 -Cambridge Bay | 6 | Months | $ - 0 | $ - 0 | $ - 0 | | | | $ - 0 |
| Base fee Zone 3 - Hall Beach | 6 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 4 - Iqaluit | 6 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 5 - Goose Bay | 6 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Totals | | | | $ - 0 | | | | |
| CLIN 0003 FFP | | | | | | | | | |
| Rotary Wing Flying Hours | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Hourly Rate | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Wing Flying Hours | 1100 | Hours | $ - 0 | $ - 0 | $ - 0 | 6 | Months | $ - 0 | $ - 0 |
| Totals | | | | $ - 0 | | | | $ - 0 |
| CLIN 0004 CR | | | | | | | | | |
| Cost Reimburseable | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price | Extended Amount | QTY | Unit | Unit Price | Total |
| Contingency Flying Hours | 550 | Hours | $ - 0 | $ - 0 | $ 688,148.00 | Lot | $ 1.00 | $ 688,148.00 |
| Contingency Rotary Bulk Fuel Transfer Liters | 0 | Liters | $ - 0 | $ - 0 | | | | $ 688,148.00 |
| Reimburseable Expenses | $ 688,148.00 | Lot | $ 1.00 | $ 688,148.00 | | | | |
| Totals | | | $ 688,148.00 | | | | |
| CLIN 0005 CR | | | | | | | | |
| Supplemental Base Fee | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Extended Amount | QTY | Unit | Unit Price | Total |
| Supplemental Base Fee Zone 1 - Inuvik | 48.8 | Days | $ - 0 | $ - 0 | 0 | Lot | $ 1.00 | $ - 0 |
| Supplemental Base fee Zone 2 - Cambridge Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | $ - 0 |
| Supplemental Base Fee Zone 3 - Hall Beach | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 4 - Iqaluit | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 5 - Goose Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Totals | | | $ - 0 | | | | |
| CLIN 0006 FFP | | | | | | | | |
| Rotary Wing Bulk Fuel Transfer | | | | | FFP Amount | | | |
| Description | AVERAGE QTY | Unit | Unit Price per Liter | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Bulk Fuel Transfer | 1,500,000 | Liters | $ - 0 | $ - 0 | 0 | Liters | $ - 0 | $ - 0 |
| Totals | | | $ - 0 | | | | $ - 0 |
Option Year 1 Option Year 1 (1 Apr 16 - 31 Mar 17) - Estimated Cost Summary
| CLIN | Description | IGCE | % of Total |
| 1001 | Main Base Fee | $ - 0 | 0.00% |
| 1002 | Rotary Wing Flying Hours | $ - 0 | 0.00% |
| 1003 | Cost Riemburseable | $ 1,376,295.00 | 100.00% |
| 1004 | Supplemental Base Fee | $ - 0 | 0.00% |
| 1005 | Rotary Wing Bulk Fuel Transfer | $ - 0 | 0.00% |
| Total | $ 1,376,295.00 | 100% |
CLIN 1001 FFP
| Main Basing Fee | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Base fee Zone 1 - Inuvik | 12 | Months | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Base fee Zone 2 -Cambridge Bay | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | $ - 0 |
| Base fee Zone 3 - Hall Beach | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 4 - Iqaluit | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 5 - Goose Bay | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Totals | | | | $ - 0 | | | | |
| CLIN 1002 FFP | | | | | | | | | |
| Rotary Wing Flying Hours | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Hourly Rate | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Wing Flying Hours | 2200 | Hours | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Totals | | | | $ - 0 | | | | $ - 0 |
| CLIN 1003 CR | | | | | | | | | |
| Cost Reimburseable | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price | Extended Amount | QTY | Unit | Unit Price | Total |
| Contingency Flying Hours | 1100 | Hours | $ - 0 | $ - 0 | $ 1,376,295.00 | Lot | $ 1.00 | $ 1,376,295.00 |
| Contingency Rotary Bulk Fuel Transfer Liters | 500000 | Liters | $ - 0 | $ - 0 | | | | $ 1,376,295.00 |
| Reimburseable Expenses | $ 1,376,295.00 | Lot | $ 1.00 | $ 1,376,295.00 | | | | |
| Totals | | | $ 1,376,295.00 | | | | |
| CLIN 1004 CR | | | | | | | | |
| Supplemental Base Fee | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Extended Amount | QTY | Unit | Unit Price | Total |
| Supplemental Base Fee Zone 1 - Inuvik | 48.8 | Days | $ - 0 | $ - 0 | $ - 0 | Lot | $ 1.00 | $ - 0 |
| Supplemental Base fee Zone 2 - Cambridge Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | $ - 0 |
| Supplemental Base Fee Zone 3 - Hall Beach | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 4 - Iqaluit | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 5 - Goose Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Totals | | | $ - 0 | | | | |
| CLIN 1005 FFP | | | | | | | | |
| Rotary Wing Bulk Fuel Transfer | | | | | FFP Amount | | | |
| Description | AVERAGE QTY | Unit | Unit Price per Liter | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Bulk Fuel Transfer | 1,500,000 | Liters | $ - 0 | $ - 0 | 1,500,000 | Liter | $0.00 | $ - 0 |
| Totals | | | $ - 0 | | | | $ - 0 |
Option Year 2 Option Year 2 (1 Apr 17 - 31 Mar 18) - Estimated Cost Summary
| CLIN | Description | IGCE | % of Total |
| 2001 | Main Base Fee | $ - 0 | 0.00% |
| 2002 | Rotary Wing Airlift Hours | $ - 0 | 0.00% |
| 2003 | Cost Riemburseable | $ 1,543,405.00 | 100.00% |
| 2004 | Supplemental Base Fee | $ - 0 | 0.00% |
| 2005 | Rotary Wing Bulk Fuel Transfer | $ - 0 | 0.00% |
| Total | $ 1,543,405.00 | 100% |
CLIN 2001 FFP
| Main Base Fee | | | | | | Monthly FFP Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Base fee Zone 1 - Inuvik | 12 | Each | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Base fee Zone 2 -Cambridge Bay | 12 | Each | $ - 0 | $ - 0 | $ - 0 | | | | $ - 0 |
| Base fee Zone 3 - Hall Beach | 12 | Each | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 4 - Iqaluit | 12 | Each | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 5 - Goose Bay | 12 | Each | $ - 0 | $ - 0 | $ - 0 | | | | |
| Totals | | | | $ - 0 | | | | |
| CLIN 2002 FFP | | | | | | | | | |
| Rotary Wing Flying Hours | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Hourly Rate | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Wing Flying Hours | 2200 | Hours | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Totals | | | | $ - 0 | | | | $ - 0 |
| CLIN 2003 CR | | | | | | | | | |
| Cost Reimburseable | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price | Extended Amount | QTY | Unit | Unit Price | Total |
| Contingency Flying Hours | 1100 | Hours | $ - 0 | $ - 0 | $ 1,543,405.00 | Lot | $ 1.00 | $ 1,543,405.00 |
| Contingency Rotary Bulk Fuel Transfer Liters | 500000 | Liters | $ - 0 | $ - 0 | | | | $ 1,543,405.00 |
| Reimburseable Expenses | $ 1,543,405.00 | Lot | $ 1.00 | $ 1,543,405.00 | | | | |
| Totals | | | $ 1,543,405.00 | | | | |
| CLIN 2004 CR | | | | | | | | |
| Supplemental Base Fee | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Extended Amount | QTY | Unit | Unit Price | Total |
| Supplemental Base Fee Zone 1 - Inuvik | 48.8 | Days | $ - 0 | $ - 0 | $ - 0 | Lot | $ 1.00 | $ - 0 |
| Supplemental Base fee Zone 2 - Cambridge Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | $ - 0 |
| Supplemental Base Fee Zone 3 - Hall Beach | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 4 - Iqaluit | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 5 - Goose Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Totals | | | $ - 0 | | | | |
| CLIN 2005 FFP | | | | | | | | |
| Rotary Wing Bulk Fuel Transfer | | | | | FFP Amount | | | |
| Description | AVERAGE QTY | Unit | Unit Price per Liter | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Bulk Fuel Transfer | 1,500,000 | Liters | $ - 0 | $ - 0 | 1,500,000 | Liter | $ - 0 | $ - 0 |
| Totals | | | $ - 0 | | | | $ - 0 |
Option Year 3 Option Year 3 (1 Apr 18 - 31 Mar 19) - Estimated Cost Summary
| CLIN | Description | IGCE | % of Total |
| 3001 | Main Base Fee | $ - 0 | 0.00% |
| 3002 | Rotary Wing Flying Hours | $ - 0 | 0.00% |
| 3003 | Cost Riemburseable | $ 1,722,417.00 | 100.00% |
| 3004 | Supplemental Base Fee | $ - 0 | 0.00% |
| 3005 | Rotary Wing Bulk Fuel Transfer | $ - 0 | 0.00% |
| Total | $ 1,722,417.00 | 100% |
CLIN 3001 FFP
| Main Base Fee | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Base fee Zone 1 - Inuvik | 12 | Months | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Base fee Zone 2 -Cambridge Bay | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | $ - 0 |
| Base fee Zone 3 - Hall Beach | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 4 - Iqaluit | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 5 - Goose Bay | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Totals | | | | $ - 0 | | | | |
| CLIN 3002 FFP | | | | | | | | | |
| Rotary Wing Flying Hours | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Hourly Rate | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Wing Flying Hours | 2200 | Hours | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Totals | | | | $ - 0 | | | | $ - 0 |
| CLIN 3003 CR | | | | | | | | | |
| Cost Reimburseable | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price | Extended Amount | QTY | Unit | Unit Price | Total |
| Contingency Flying Hours | 900 | Hours | $ - 0 | $ - 0 | $ 1,722,417.00 | Lot | $ 1.00 | $ 1,722,417.00 |
| Contingency Rotary Bulk Fuel Transfer Liters | 500000 | Liters | $ - 0 | $ - 0 | | | | $ 1,722,417.00 |
| Reimburseable Expenses | $ 1,722,417.00 | Lot | $ 1.00 | $ 1,722,417.00 | | | | |
| Totals | | | $ 1,722,417.00 | | | | |
| CLIN 3004 CR | | | | | | | | |
| Supplemental Base Fee | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Extended Amount | QTY | Unit | Unit Price | Total |
| Supplemental Base Fee Zone 1 - Inuvik | 48.8 | Days | $ - 0 | $ - 0 | $ - 0 | Lot | $ 1.00 | $ - 0 |
| Supplemental Base fee Zone 2 - Cambridge Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | $ - 0 |
| Supplemental Base Fee Zone 3 - Hall Beach | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 4 - Iqaluit | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 5 - Goose Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Totals | | | $ - 0 | | | | |
| CLIN 3005 FFP | | | | | | | | |
| Rotary Wing Bulk Fuel Transfer | | | | | FFP Amount | | | |
| Description | AVERAGE QTY | Unit | Unit Price per Liter | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Bulk Fuel Transfer | 1,500,000 | Liters | $ - 0 | $ - 0 | 1,500,000 | Liter | $ - 0 | $ - 0 |
| Totals | | | $ - 0 | | | | $ - 0 |
Option Year 4 Option Year 4 (1 Apr 19 - 31 Mar 20) - Estimated Cost Summary
| CLIN | Description | IGCE | % of Total |
| 4001 | Main Base Fee | $ - 0 | 0.00% |
| 4002 | Rotary Wing Flying Hours | $ - 0 | 0.00% |
| 4003 | Cost Riemburseable | $ 1,774,090.00 | 100.00% |
| 4004 | Supplemental Base Fee | $ - 0 | 0.00% |
| 4005 | Rotary Wing Bulk Fuel Transfer | $ - 0 | 0.00% |
| Total | $ 1,774,090.00 | 100% |
CLIN 4001 FFP
| Main Base Fee | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Base fee Zone 1 - Inuvik | 12 | Months | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Base fee Zone 2 -Cambridge Bay | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | $ - 0 |
| Base fee Zone 3 - Hall Beach | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 4 - Iqaluit | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Base fee Zone 5 - Goose Bay | 12 | Months | $ - 0 | $ - 0 | $ - 0 | | | | |
| Totals | | | | $ - 0 | | | | |
| CLIN 4002 FFP | | | | | | | | | |
| Rotary Wing Flying Hours | | | | | | FFP Amount | | | |
| Description | QTY | Unit | Hourly Rate | Unit Price per Month | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Wing Flying Hours | 2200 | Hours | $ - 0 | $ - 0 | $ - 0 | 12 | Months | $ - 0 | $ - 0 |
| Totals | | | | $ - 0 | | | | $ - 0 |
| CLIN 4003 CR | | | | | | | | | |
| Cost Reimburseable | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price | Extended Amount | QTY | Unit | Unit Price | Total |
| Contingency Flying Hours | 1100 | Hours | $ - 0 | $ - 0 | $ 1,774,090.00 | Lot | $ 1.00 | $ 1,774,090.00 |
| Contingency Rotary Bulk Fuel Transfer Liters | 500000 | Liters | $ - 0 | $ - 0 | | | | $ 1,774,090.00 |
| Reimburseable Expenses | $ 1,774,090.00 | Lot | $ 1.00 | $ 1,774,090.00 | | | | |
| Totals | | | $ 1,774,090.00 | | | | |
| CLIN 4004 CR | | | | | | | | |
| Supplemental Base Fee | | | | | Cost Reimburseable Amount | | | |
| Description | QTY | Unit | Unit Price per Day | Extended Amount | QTY | Unit | Unit Price | Total |
| Supplemental Base Fee Zone 1 - Inuvik | 48.8 | Days | $ - 0 | $ - 0 | $ - 0 | Lot | $ 1.00 | $ - 0 |
| Supplemental Base fee Zone 2 - Cambridge Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | $ - 0 |
| Supplemental Base Fee Zone 3 - Hall Beach | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 4 - Iqaluit | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Supplemental Base Fee Zone 5 - Goose Bay | 48.8 | Days | $ - 0 | $ - 0 | | | | |
| Totals | | | $ - 0 | | | | |
| CLIN 4005 FFP | | | | | | | | |
| Rotary Wing Bulk Fuel Transfer | | | | | FFP Amount | | | |
| Description | AVERAGE QTY | Unit | Unit Price per Liter | Extended Amount | QTY | Unit | Unit Price | Total |
| Rotary Bulk Fuel Transfer Base Yr | 1,500,000 | Liters | $0.00 | $ - 0 | 1,500,000 | Liters | $0.00 | $ - 0 |
| Totals | | | $ - 0 | FFP Option Yr 3 | | | $ - 0 |