STATEMENT OF WORK DWTP 4.pdf

PDF 245 KB Posted

Attached to
Luke AFB Well Maintenance
Solicitation number
FA488726Q0051
Issued by

About this file

This is a Statement of Work (SOW) for the overhaul and rehabilitation of a deep well turbine pump system at Luke Air Force Base in Arizona.

The Contractor shall extract, overhaul, and reinstall one 150 HP Deep Well Turbine Pump (DWTP) set at approximately 560 feet depth. The system specifications include an 18-inch casing, 560-foot pump setting, design capacity of 800 to 1050 GPM at 580 feet Total Dynamic Head (TDH), static water level of 380 feet, and pumping level of 450 feet with 70 feet drawdown. Work scope encompasses all labor, materials, heavy rigging/crane operations, and engineering supervision. Applicable standards include DoD UFC 3-230-02, Air Force AFI 32-1067, USACE EM 385-1-1, AWWA A100, and AWWA E101.

Technical tasks include: (1) mobilization with certified crane rigging and electrical LOTO coordination; (2) extraction with match-marking of all couplings and joints; (3) 150 HP motor overhaul including Megger testing, VPI re-varnishing, bearing replacement, and discharge head sandblasting/epoxy coating; (4) subsurface equipment overhaul including line shaft straightness verification and new bowl assembly installation; (5) 18-inch wellbore rehabilitation with pre/post camera surveys, cleanout, and mechanical screen brushing; and (6) reinstallation with precise plumbness, motor shaft runout verification (maximum 0.002 inches), shaft elongation calculations, and dynamic vibration testing. Vibration acceptance criteria per HI 9.6.4 and AWWA E101 are: 0.15 inches/second for horizontal axes and 0.10 inches/second for vertical axis. Deliverables include rigging/critical lift plan (10 days prior to mobilization), motor overhaul and Megger report (5 business days prior to reinstallation), pre/post video surveys (5 days after completion), certified pump curve with as-built diagram and test results (3 days after commissioning), and Total Coliform/E. coli lab results (prior to system tie-in). The highest identified risk is bearing failure due to improper shaft alignment or incorrect lateral adjustment at the 580-foot depth with high horsepower operation.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW) R1

Project: Heavy-Duty Deep Well Turbine Pump Overhaul and 18” Wellbore Rehabilitation System Specifications: 18" Casing, notional 150 HP Motor, 560' Pump Setting, and 800 to 1050 GPM @ 580' TDH, Static Water Level = 380 ft, and Pumping Level = 450 ft, Drawdown = 70 ft.

Location: Luke AFB AZ, Water Well Number 12

1.0 OBJECTIVE & SCOPE

The Contractor shall furnish all labor, materials, heavy rigging (crane operations), and engineering supervision necessary to extract, overhaul, and reinstall one (1) Deep Well Turbine Pump (DWTP) set at approximately 560 feet. The Contractor shall rebuild the 150 HP surface motor, overhaul the bowl assembly to meet the design point of 800 to 1050 GPM at 580 feet Total Dynamic Head (TDH), rehabilitate the 18-inch wellbore, and commission the system to Department of War (DoW) and Air Force standards.

2.0 APPLICABLE PUBLICATIONS & TECHNICAL STANDARDS

All work shall comply with the latest editions of:

Authority Standard Title / Subject

DoD UFC 3-230-02 O&M: Water Supply Systems

Air Force AFI 32-1067 Water and Fuel Systems

USACE EM 385-1-1 Safety & Health Requirements Manual (Rigging & LOTO)

AWWA AWWA A100 Standard for Water Wells

AWWA AWWA E101 Vertical Turbine Pumps - Line Shaft Types

3.0 TECHNICAL TASK REQUIREMENTS

🏗🏗 Task 1: Mobilization, Crane Rigging, and Safety (LOTO)

• Heavy Rigging: Due to the suspended weight of 580 feet of column pipe, line shaft, and bowl assembly, the Contractor shall utilize a certified crane or heavy-duty pump hoist rated for the total static and dynamic extraction load. A critical lift plan must be submitted if required by Base Safety per EM 385-1-1.

• Electrical LOTO: Coordinate with Base Civil Engineering (BCE) to disconnect and physically Lockout/Tagout the 150 HP motor control center (MCC).

• Add “Notification to the FAA” attached.

🪝🪝 Task 2: Extraction and Inspection

• Extract the 150 HP motor, discharge head, 580 feet of column pipe, line shafting, and the pump bowl assembly.

• Match-mark and thread-gauge all line shaft couplings and column pipe joints during extraction.

⚙ Task 3: Surface Equipment Overhaul (150 HP Motor)

• Transport the 150 HP Vertical Hollow Shaft (VHS) motor to a reputable local motor rebuild shop.

• Perform a Megger test, clean, bake, and perform Vacuum Pressure Impregnation (VPI) or re-varnish the stator windings.

• Replace upper thrust bearings (must be rated for the extreme down-thrust of 580' of shaft and 800 to 1050 GPM hydraulic load) and lower guide bearings.

• Sandblast and epoxy-coat the interior of the discharge head (NSF 61). Replace stuffing box packing/mechanical seal and shaft sleeve.

🔧🔧 Task 4: Sub-surface Equipment Overhaul (560' Setting)

• Line Shafting: Check all line shafts on a lathe for straightness (critical for a 580' shaft to prevent vibration). Replace all line shaft bearings/sleeves.

• Bowl Assembly: Install new bowl assembly capable of delivering 800 to 1050 GPM at 580 ft TDH. Coat bowls with friction-reducing epoxy.

🕳🕳 Task 5: 18" Wellbore Rehabilitation

• Pre-Rehab Camera Survey: Conduct a color video survey of the 18" casing down to the total drilled depth (well past the 560' pump setting).

• Cleanout & Sump Bailing: Bail or airlift accumulated sand/debris from the bottom of the well.

• Rehabilitation: Mechanically brush the well screens based on the camera survey findings to restore specific capacity.

• Post-Rehab Camera Survey: Conduct a final video survey to verify casing integrity and screen cleanliness.

🚀🚀 Task 6: Reinstallation, Calibration, and Commissioning

6.1 Plumbness and Mechanical Alignment

• Discharge Head Leveling: The Contractor shall ensure the pump discharge head is installed perfectly plumb and level over the well casing. Shimming shall be done with machined stainless-steel plates; the use of wedges or temporary spacers is strictly prohibited.

• Motor Shaft Runout: Prior to coupling the motor to the top line shaft, the Contractor shall use a dial indicator to verify the motor shaft runout. Maximum allowable runout at the motor coupling shall not exceed 0.002 inches.

6.2 Lateral Adjustment and Shaft Elongation (Stretch)

• Engineering Calculation: Due to the 560-foot pump setting and the hydraulic down-thrust generated by pumping 800 to 1050 GPM at 580 feet TDH, the Contractor must calculate the exact line-shaft elongation (stretch).

• Impeller Clearance: The adjusting nut on the 150 HP Vertical Hollow Shaft (VHS) motor shall be set to lift the impellers off the bowl seats, compensating for the calculated shaft stretch plus the OEM-recommended running clearance.

The Contractor shall document this calculation and the final nut adjustment (measured in turns/fractions of an inch) in the final commissioning report.

6.3 Dynamic Vibration Testing & Tolerances

• Baseline Measurement: Upon startup and stabilization at the design duty point (800 to 1050 GPM), the Contractor shall perform a certified vibration analysis using a calibrated vibration meter.

• Test Points: Readings shall be taken at the top motor bearing housing in three independent axes: Horizontal (Parallel to discharge), Horizontal (Perpendicular to discharge), and Vertical (Axial).

• Acceptance Criteria: Vibration levels shall not exceed the maximum allowable limits set forth by the Hydraulic Institute (HI 9.6.4) and AWWA E101 for a 150 HP vertical turbine pump. The overall unfiltered vibration must strictly adhere to the following limits:

Measurement Axis Maximum Allowable Vibration (Peak Velocity)

Condition / Standard

Horizontal (Parallel) 0.15 inches/sec (3.8 mm/sec) HI 9.6.4 / AWWA E101

Horizontal (Perpendicular)

0.15 inches/sec (3.8 mm/sec) HI 9.6.4 / AWWA E101

Vertical (Axial) 0.10 inches/sec (2.5 mm/sec) HI 9.6.4 / AWWA E101

6.4 Corrective Action for Out-of-Tolerance Performance

• If vibration readings exceed the maximum allowable limits, or if motor amperage indicates phase imbalance/mechanical binding, the Contractor shall immediately shut down the pump.

• The Contractor shall diagnose and correct the root cause (e.g., bent line shaft, improper lateral adjustment, or baseplate misalignment) at no additional cost to the Government. The system will not be accepted until dynamic vibration testing falls within the specified tolerances.

• Reinstall the overhauled system.

• Shaft Elongation Calibration: The Contractor must calculate the shaft stretch

(elongation) caused by the hydraulic weight of pumping 800 to 1050 GPM from 560 feet pump setting. The top adjusting nut must be set with precise lateral clearance to ensure the impellers do not drag on the bowls during operation.

• Disinfection: Chlorinate the well per AWWA C654.

• Testing: Conduct a step-drawdown test to verify the pump meets the design 800 to 1050 GPM at 580' TDH performance requirement. Monitor 150 HP motor amperage and vibration at the discharge head.

4.0 DELIVERABLES AND QUALITY ASSURANCE

Deliverable Description Timeline

DEL-01 Rigging/Critical Lift Plan 10 days prior to mobilization

DEL-02 150 HP Motor Overhaul & Megger Report 5 business days prior to reinstallation

DEL-03 Pre/Post 18" Casing Video Surveys 5 days after survey completion

DEL-04 Submittals: Certified Pump Curve & pumping results As-built" diagram of the installation, showing pump setting depth, static water level, pumping level and all component details.

Results from all field tests, including the step-drawdown test and water quality analysis report

3 days after commissioning

DEL-05 Total Coliform / E. coli Lab Results Prior to system tie-in

Because of the depth (580 feet) and high horsepower, bearing failure due to improper shaft alignment or incorrect lateral adjustment is the highest risk during re-commissioning.

END OF SOW

STATEMENT OF WORK (SOW) R1
1.0 OBJECTIVE & SCOPE
2.0 APPLICABLE PUBLICATIONS & TECHNICAL STANDARDS
3.0 TECHNICAL TASK REQUIREMENTS
🏗️ Task 1: Mobilization, Crane Rigging, and Safety (LOTO)
🪝 Task 2: Extraction and Inspection
⚙️ Task 3: Surface Equipment Overhaul (150 HP Motor)
🔧 Task 4: Sub-surface Equipment Overhaul (560' Setting)
🕳️ Task 5: 18" Wellbore Rehabilitation
🚀 Task 6: Reinstallation, Calibration, and Commissioning
6.1 Plumbness and Mechanical Alignment
Discharge Head Leveling: The Contractor shall ensure the pump discharge head is installed perfectly plumb and level over the well casing. Shimming shall be done with machined stainless-steel plates; the use of wedges or temporary spacers is strictly...
Motor Shaft Runout: Prior to coupling the motor to the top line shaft, the Contractor shall use a dial indicator to verify the motor shaft runout. Maximum allowable runout at the motor coupling shall not exceed 0.002 inches.
6.2 Lateral Adjustment and Shaft Elongation (Stretch)
Engineering Calculation: Due to the 560-foot pump setting and the hydraulic down-thrust generated by pumping 800 to 1050 GPM at 580 feet TDH, the Contractor must calculate the exact line-shaft elongation (stretch).
Impeller Clearance: The adjusting nut on the 150 HP Vertical Hollow Shaft (VHS) motor shall be set to lift the impellers off the bowl seats, compensating for the calculated shaft stretch plus the OEM-recommended running clearance. The Contractor sha...
6.3 Dynamic Vibration Testing & Tolerances
Baseline Measurement: Upon startup and stabilization at the design duty point (800 to 1050 GPM), the Contractor shall perform a certified vibration analysis using a calibrated vibration meter.
Test Points: Readings shall be taken at the top motor bearing housing in three independent axes: Horizontal (Parallel to discharge), Horizontal (Perpendicular to discharge), and Vertical (Axial).
Acceptance Criteria: Vibration levels shall not exceed the maximum allowable limits set forth by the Hydraulic Institute (HI 9.6.4) and AWWA E101 for a 150 HP vertical turbine pump. The overall unfiltered vibration must strictly adhere to the follow...
6.4 Corrective Action for Out-of-Tolerance Performance
If vibration readings exceed the maximum allowable limits, or if motor amperage indicates phase imbalance/mechanical binding, the Contractor shall immediately shut down the pump.
The Contractor shall diagnose and correct the root cause (e.g., bent line shaft, improper lateral adjustment, or baseplate misalignment) at no additional cost to the Government. The system will not be accepted until dynamic vibration testing falls w...

4.0 DELIVERABLES AND QUALITY ASSURANCE