PWS_and_RFP_questions_and_answers_response.docx

DOCX document 120 KB Posted

Attached to
Operation and Maintenance of the BMGR and Gila Bend AFAF, AZ
Solicitation number
FA488714R0002
Issued by

About this file

Attached are the answers to the questions that were received concerning the Performance Work Statement (PWS). The PWS has been revised and attached to the solicitation issued 27 Oct 14. Ensure that PWS rev 1 dated 26 Sep 14 is used when preparing proposals.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4887-14-R-0002

Operation and Maintenance of the Barry M. Goldwater Range and Gila Bend Air Force Auxiliary Field

PWS Questions and Answers Section 5 Airfield Services

Question: 5.4. The MOA 15-86 between 25 OWS and 56 RMO is not listed in the publications section.

Please provide the tasking’s under this MOA.

Question: 5.4. Is it the intent the government for the contractor to repair the TMQ-53 and if so is the contractor responsible for the cost of part?

Answer: See paragraph 5.4

What technical qualifications are required for personnel performing the repairs?

Answer: The contractor completing the installation of the new TMQ-53 weather system will provide one time training to personnel on site. See para 5.4

Will the government provide a workload estimate for parts and maintenance requirements?

Answer: This is a fixed price contract. It is expected that your projected parts and materials are built into your monthly cost for both unscheduled and scheduled maintenance. See para 1 and 5.4

Question: 5.4.7. Would the government provide a listing of required items for the MOS and are they government furnished?

Answer: All items are contractor furnished. See para 5.4

Section 5 Meteorological/TA Services

Question: 5.6. “The contractor shall utilize an aircraft tug and backup tug capable of towing an aircraft weighing up to 160,000 lbs.” Are aircraft tugs government-furnished or contractor provided? Please clarify Answer: A/C tugs are contractor provided. See para 1 and 5.6 Question: Is the “Follow Me” vehicle and associated lighting contractor provided? Please clarify.

Answer: Yes it is contractor provided. See para 1 and 5.6.1.2

Question: 5.6.1.2. Are engine oil and hydraulic fluid contractor furnished materials? Section V Technical Exhibits does not indicate quantities required.

Answer: Yes they are contractor provided. See para 1 Question: 5.6.2. Please provide quantities and clarify requirement.

Answer: Use your expertise as an O&M contractor to determine quantities. See para 1 Question: 5.6.5. “AGE Equipment.” AGE equipment is listed on page 237 as GFE, on-loan from Luke AFB. Information further confirms that Luke AFB maintains and rotates the AGE periodically via coordination with the contractor.

Is the list of AGE on page 237 all that is required and/or is the contractor responsible for furnishing any other AGE not listed? Please clarify.

Answer: AGE equipment is provided by Luke AFB. Contractor is not required to provide AGE equipment.

Question: 5.6.11.4. “The contractor shall coordinate/provide a vehicle and operator from transportation to on or off load support equipment and aircraft components from vehicles.”

We assume that support equipment and aircraft components come from Luke or Davis Monthan AFBs.

What type of support equipment (jacks, maintenance stands, etc.) or aircraft components (tires, engines, etc.) will be transported to GBAF and what type of vehicle or MHE will be required?

Answer: Support equipment can come from anywhere. Maintenance personnel from the unit who owns the aircraft will bring whatever components are required to provide service and repair. GBAFAF is capable of handling aircraft up to and including a C-5, thus the contractor shall provide a vehicle capable of lifting these items IAW 5.6.11.4.

Are vehicle and MHE contractor provided? Please clarify.

Answer: Yes. The contractor shall provide equipment/vehicles, motorized heavy equipment, and a trained operator to unload these components. See para 1 and 5.6.11.4.

Section 6 Civil Engineering Services

Reference PWS Paragraph 6.0. Throughout the Civil Engineering Section, the words “maintain, repair, minor maintenance and preventive maintenance” are used to describe work requirements. However, these terms are not defined in the PWS text or in the Acronyms/Abbreviations and Definitions Section (Section 8). Paragraph 6.3.1 refers to a “Service Call” and the requirement to operate a service call desk to facilitate customer support. However, a “service call” is not defined. Paragraph 6.3.3 describes management processes and procedures for AF 332s. AF 332s cover minor and major project/construction work, which the contractor must execute, when approved. Paragraphs 2.4, 2.5 and 2.6 refer to reimbursements and call-outs for services that are additional or required for visiting activities. However, it is unclear how the provisions addressed in 2.4, 2.5 and 2.6 interact with CE maintenance and repair work. In other words, the concept of out of scope work or call-outs does not appear to apply to maintenance and repair work.

Please be advised that it is not possible for contractors to bid and assume unlimited liability under a firm fixed price contract for the performance of CE work at GBAF, especially when no workload data or lists of equipment have been provided. Workload data is presented in terms of labor hours only. Is this direct labor hours? More information is required if unlimited repair, replacement or construction liability for facilities, equipment or projects is assumed.

To mitigate the governments and the contractors risk will the government establish clear definitions and reasonable bounds for “service calls, minor maintenance, major maintenance and related repair or replacement and construction actions”?

Answer: This is a fixed price contract. It is expected that your projected materials and supplies are built into your monthly cost for both unscheduled and scheduled maintenance. The government has already identified facility repairs that are above and beyond this contract and will pursue them through other means as funds become available. There is no dollar threshold for application of the SCA. See para 1 Question: 6.2. “The contractor shall furnish all necessary parts and materials for the performance of this contract at his expense.” The workload data does not provide any historical data concerning parts and materials costs.

Will the government provide historical information concerning parts and materials costs on an annual basis?

Answer: This is and has been a fixed price contract for the past 20 years. Therefore all historical costs are proprietary. As the offerer you shall utilize your expertise as an O&M contractor to determine parts and materials for the facilities and equipment supported. It is expected that projected parts and material costs are built into your monthly cost for both unscheduled and scheduled maintenance. See para 1.

Question: 6.6. Can the Government please provide dates when the last inspections were completed on Well #3-4, and the Range 1 water well?

Answer:

Well 3- Inspected/Rebuilt July 2012 Well 4 – Inspected/Rebuilt July 2014 Range 1 – Inspected/Rebuilt Dec 2013

Question: 6.6. How many water wells require maintenance?

Answer: Three, See paragraph 6.6.

When were they installed?

Answer:

Well 3- Installed 1964 Well 4 – Installed 1973 Range 1 –Installed 1976

Question: 6.6. What was the most recent year in which each was pulled for casing inspection, motor and impeller inspection/rebuild/refurbishment?

Answer:

Well 3- Inspected and Rebuilt July 2012 Well 4 – Inspected and Rebuilt July 2014 Range 1 – Inspected and Rebuilt Dec 2013

Question: 6.6. What is the depth of each water well?

Answer:

Well 3- Cased to 608’, Static level is 304’ Well 4 – Cased to 594’, Static level is 314’ Range 1 – Cased to 503’, Static level is 187’

Question: 6.7. The referenced PWS requires the contractor to provide ½ liter water bottles for Gila Bend personnel (contractor, government, tenants, users, etc.). The workload information states “Maintain Drinking Water- 22,500 gal per year.”

Is this the correct workload data for the ½ liter water bottles? Please clarify.

Answer: Yes: 22,500 gallons is equivalent to 170,344 half liter bottles. See 6.7

Question: 6.8. What is the quantity and capacity of grease traps on GBAF?

Answer:

1. 1 Grease Trap at facility 4300 (Lodging)

2. Typical size for a kitchen capable of feeding 100 personnel

Is pumping required?

Answer: Yes

If so, at what frequency?

Answer: Kitchen is used intermittently and pumped no more than 3 times per year

Question: 6.10.8. Please identify fire detection/suppression systems by type and facility.

Answer: Facilities 18, 22 & 326 (NGA warehouses) have fire suppression systems. All facilities on GBAFAF have smoke or heat detection systems.

Question: 6.10.8. Please identify UPS systems by type, size and purpose.

Answer: UPS type/size….Monaco Fire alarm and reporting system and an ADVANTOR Intrusion Detection System.

Question: 6.21.1. Can the Government please clarify the acreage of improved grounds, there are two different numbers in this paragraph 30 and 2001 acres.

Answer: IAW 6.21.1: Out of a total acreage of 2001: 30 acres are planted in Bermuda or winter rye in their respective seasons, irrigated and maintained. 720 of the 2001 acres are located around the airfield and maintained as Semi-Improved grounds. The remaining 1251 acres are not irrigated; however they must be maintained to the same standards. PWS will be amended.

Question: 6.21.3. Does the USAF own all the property on the outside of the 7.5 mile boundary fence surrounding GBAFAF?

Answer: Yes

If not are the land owners responsible for cutting the vegetation on their property away from GBAFAF's fence line?

Answer: N/A

Question: 6.21.5. Can the Government please provide an estimated number of trees and shrubs that were replaced due to storm damage yearly?

Answer:

No more than 3 trees annually.

No more than 6 shrubs annually.

Question: 6.23. Does the Government supply the regenerative air type vacuum truck to sweep the airfield?

Answer: No. Contractor supplied IAW para 1 and 6.23.

Question: 6.23. States that the contractor is responsible for removal and replacement of sections.

Is this referring to sections of concrete and asphalt?

Answer: Yes IAW 6.24

If so would this fall under Construction and not Maintenance? Please clarify.

Answer: Maintenance. The contractor is responsible for replacing sections of asphalt and concrete up to 10’ X 10’ sections per location. See para 6.24

Question: 6.24. States that the removal and replacement of sections up to 10'x10' to maintain safe walking and proper water drainage.

Can the Government please clarify if this is for both sidewalks and roads?

Answer: Yes; applies to all base and airfield pavements See 6.24

Question: 6.25. Can the Government please provide the number, size, location of gates, and the approximate distance these gates are from the Base?

Answer: Approximately 50 gates of various sizes and distances.

Distances can be calculated by looking at a map of the BMGR.

Question: 6.25. Can the Government please provide how many feet of fence the contractor is responsible to repair off Base?

Answer: No more than 200’ annually.

Can the government provide the approximate distance required to travel from the Base to make these repairs?

Answer: Up to 300 miles round trip per day

Question: 6.26. Can the Government please provide the number, and sizes of all the signs to include the approximate distance the signs are from the Base?

Answer:

Sizes of signs vary.

Signs along the highway are spaced 500 meters apart.

Every gate has numerous signs.

Every intersection has a sign.

There are directional signs to targets and ranges.

There are boundary signs.

Most information can be determined by looking at the map.

The contractor shall replace with like signs.

Question: 6.28.1. States the contractor shall repair the three roof mounted evap coolers on the Fire Dept.

Are these the only HVAC units the contractor is required to repair? Are they currently the responsibility of the incumbent?

Answer: The contractor is responsible for all base and range HVAC units, to include the three evap coolers on the Fire Dept. See para 6.28-6.28.7.

Answer: No they are not the only units the contractor is required to repair.

Answer: No they are not the incumbent’s responsibility. See para 6.28-6.28.7.

Are these coolers currently operational?

Answer: No

If they are not operational can the Government please provide a detailed list of the repairs needed to make them operational?

Answer: Everything but the frames

Can the Government also provide the Make, Model, and Serial Number of the evap coolers?

Answer: Master Cool 9000 CFM

Question: 6.29. “The contractor shall provide minor maintenance and repair to NGA facilities 18, 22 & 326 to include inspection of equipment and replacement of filters. Repair components shall be on a reimbursable basis.”

Please define minor maintenance and repair and elaborate on how component repair reimbursement will be accomplished.

Answer: The contractor shall be responsible for air filters and belts on HVAC systems and labor on everything else. NGA will reimburse you for parts on everything else. See 6.29

Question: 6.35. The title of this paragraph is “Call Out Work for Maintenance, Repair and Refurbishment.” However, the text seems to limit the scope of call out work to “improvements” or “new work”, for example: “…minor facility improvements, roads and grounds improvements, paint plan work, fire detection/suppression systems upgrades, electrical upgrades, mechanical upgrades, environmental cleanup, identified self-help projects, or other work as coordinated through the COR…..”

Please address the following:

Question: Is call out work limited to improvements or new work? Please clarify.

Answer: Both

Question: If call out work includes “maintenance, repair or refurbishment” at what point does a repair/refurbishment work order (or service call) become a call out? Please clarify.

Answer: it does not include maintenance, repair or refurbishment. A callout applies to everything above and beyond the scope of this contract. Callouts are clearly defined throughout the PWS in these paragraphs: 2.5, 2.6, 5.5.7, 6.35, 11.2, 15.2, 15.4, 15.5.6, 15.7.1 & 16.2

Question: Call outs are limited to a ceiling of $2,000.00. This implies that all service call work under the contract is limited to a ceiling of $2,000.00. Is this interpretation correct? Please clarify.

Answer: No it is not.

Answer: There are many repair actions in this contract that exceed $2000. A callout applies to everything above and beyond the scope of this contract. Callouts are clearly defined throughout the PWS in these paragraphs: 2.5, 2.6, 5.5.7, 6.35, 11.2, 15.2, 15.4, 15.5.6, 15.7.1 & 16.2

Question: Are all AF 332s assigned to the contractor performed on a call out basis? Please clarify.

Answer: 332s are submitted to Luke AFB Civil Engineering for items not on the contract and typically include facility modifications.

They are not assigned to the contractor as a call-out: Work Orders are typically assigned to an IDIQ contractor at Luke AFB.

Section 7 Fire and Emergency Services Question: 7.1. Do you have specific current name and versions of applicable standards, guidelines, and technical implementation guides that apply to FES to include links (NFPA) etc. and will you provide such data?

Answer: Yes, standards, guidelines, and technical implementation guides that apply to FES, to include links (NFPA), are listed in the Publications and Forms section of the Performance Work Statement

Question: 7.1. Does the government provide Proximity Gear and SCBA for firefighters?

Answer: No. Per PWS, Section I, Description of Service, para 1 Scope of Work.

Question: 7.1. What kind of hazardous materials are used and stored on Gila Bend AFAF and BMGR?

Answer: There are only small quantities of general purpose (paints, solvents, etc.) and medium to large quantities of aircraft fuel (56, 000 gals), diesel fuel (8,000 gals) and regular gasoline (8,000 gals).

Question: 7.1. Will the contractor have to comply with AFI 32-2001 paragraphs 3.5.4.4?

Answer: Yes, the contractor shall comply with AFI 32-2001, para. 3.5.4.4.. IAW AFI 32-2001 pre-incident plans shall be developed and maintained, with quantity adjustments approved by the Command Fire Chief

Question: 7.1. Will Gila Bend AFAF FES have to become Commission on Fire Accreditation International (CFAI) accredited? Who pays costs?

Answer: Yes, CFAI accreditation will be required at a time to be determined. No, the contractor will not burden the cost for the accreditation.

Question: 7.2. “…will notify the contractor of any changes of the two weekend flying days by 1600 hours on Friday, two weeks prior to the changes.”

Does this mean that a minimum of 14-days advanced notice of the change will be provided to the contractor? Please confirm.

Answer: Yes, per paragraph 7.2 of the PWS

Question: 7.2. In the event of a fire or medical emergency during times when the fire department in not staffed, should the contractor simply call the town of Gila Bend?

Answer: Yes, the contractor will call the GBAFAF Emergency Communication Center (open 24/7) and they will notify the Phoenix Dispatch.

Question: 7.2. Do current mutual aid agreements provide for unassisted, on base emergency response support by the town fire emergency staff? Please clarify.

Answer: No, the current mutual aid agreement does not provide for unassisted, on base responses.

Question: 7.2. What happens if two weekend flying day schedule is not provided to the contractor a minimum of 1 month in advance?

Answer: If a schedule is not provided at the required time crew will work the same fly days as the month before.

Question: 7.2. Similarly, what happens if 56th RMO/ASMS does not notify of any changes 1600 hours on Friday two weeks prior to the change?

Answer: If changes are not provided two weeks prior, fire fighters will be expected to work as scheduled Question: 7.2. When there is no FES on Gila Bend AFAF how will emergencies be processed? Examples: Fire Alarm activation, medical emergencies (billeting, Fam Camp, BMGR), HAZMAT incidents, wild land fires.

Answer: Per the PWS, the ECC is open 24/7. Alarm activations, medical assistance, etc. will be processed through the Emergency Communication Center to external agencies.

Question: 7.2. If FES is in fire/medical operations and 2400 on a Friday closure comes, what happens?

Do we cease operations?

Answer: No, operations will continue until the emergency has been resolved If not, will callout provisions then apply?

Answer: Yes, some call out provisions will apply Question: 7.3. If there is a request for the EOD Paramedic outside the required duty schedule how would that be handled?

Answer: Unscheduled request for an EOD paramedic will be negotiated.

Question: 7.3. DoD Instruction 6055.06, 6.3., Staffing Requirements. Determine, document, and provide staffing required to meet the level of service objectives using the tools and guidance in Enclosure 5. The staffing in PWS 7.2, do not comply with DoD Instruction 6055.06, enclosure 3, Table E3.T1.

What do we follow?

Answer: The contractor will follow the PWS The manning does not staff an initial full alarm assignment (Structural, Technical Rescue).

Answer: (See above) Are there any short-term, long-term, or temporary deviations?

Will contractor be provided a copy?

Answer: No, there are no short/long term or temporary deviations Question: 7.3. Are there any FES policy deviations in accordance with AFI 32-2001 paragraph 2.8?

Will contractor be given a copy?

Answer: No, there are no FES policy deviations Question: 7.3. Have there been any risk assessments accomplished in accordance with AFI 32-2001, paragraph 2.11.

Will the contractor be provided a copy?

Answer: Risk assessment is being accomplished by the MAJCOM Fire Chief; a copy will be made available when completed.

Question: 7.3.1. Are live fire training facilities available on site for structural and ARFF on Gila Bend AFAF?

If not, where is training conducted?

Answer: No, there are no live fire training facilities available on Gila Bend. All live fire training is performed at Luke Air Force Base Whose equipment is utilized (i.e.; vehicles, equipment, fuel) if the training is off site?

Answer: Luke AFB normally provides vehicles and personnel to operate the pit and structural fire facility. Contractor provides SCBA equipment, PPE and pays for the fuel used in the equipment.

Does the government reimburse OT labor costs required to accomplish this training?

Answer: Yes, the government reimburses contractor for overtime labor cost required to accomplish the training Question: 7.3.1. Are the listed National Fire Codes the National Fire Protection Association Fire Code?

Answer: Yes, access to online NFPAs is provided through AFCEC.

Question: 7.3.1. Who are the external agency's that requires coordination?

Answer: The contractor will be required to coordinate many agencies outside of the GBAFAF for the MAA, medical agreement and the local community.

Operational documents listed above, can you be more specific with titles with the corresponding, DODI, AFI, etc.?

Answer: Operating Instructions (AFI 32-2001), risk management plans (AFI 32-2001), SORC (AFI 32-2001), Standards of Coverage (32-2001), confine space, Risk Management Plan (AFI 32-2001), Master Plan (AFI32-2001), Fire Prevention Program (AFI 32-2001), Training Program (AFI 32-2001), HazMat Program (AFI 32-2001). Pre-Incident Plans (AFI 32-2001) this is not an all-inclusive list.

Question: 7.3.1. Do you have a specific list of required conferences/seminars?

How many?

Answer: No, there is no specific list of required conferences/seminars. However, events attended must meet the requirements set in paragraph 7.3.1 of the PWS. Air Force and Command sponsored/directed conferences and seminars pertaining to fire and emergency services.

Question: 7.3.3. Does the Fire Prevention/Training/Safety Officer have to be at auxiliary 6 fields during standbys?

Answer: No, the Fire Prevention/Training/Safety Officer does not need to be at Aux 6

Question: 7.3.5. Is there a requirement to be water rescue trained?

Answer: It will be IFC responsibility to determine, establish and maintain the capabilities to perform rescues related to the Gila Bend FES core missions.

Question: 7.3.8. Does any portion of AFI 32-2001, paragraph 3.5.6 apply?

Answer: Not at this time (Emergency Medical Services)

Question: 7.3.8. What happens if the final agreement/protocol is not reviewed/approved by the RMOD and the Fire and Emergency Services COR?

Answer: It is the contractor responsibility to research and locate an agreement that can be approved.

Question: 7.4. The contractor has entered into an Emergency Base Station Agreement with a hospital and the hospital medical director will establish protocols for the paramedics, etc.

Who provides medical equipment, medical supplies, and equipment?

Answer: It will be the contractor’s responsibility to obtain supplies/equipment needed to operate and provide medical care on Gila Bend Air Force Auxiliary Field and Barry M. Gold water Range per the PWS, Section I, Description of Service, para 1 Scope of Work.

Question: 7.4. Are medical equipment, supplies and vehicles contractor furnished?

Answer: Yes, all medical equipment, supplies and vehicles (ambulances) are furnished by the contractor. See above

Question: 7.4. Does the contractor have to provide treatment medications?

Answer: Yes, all treatment medications are furnished by the contractor, Per PWS, Section I, Description of Service, para 1 Scope of Work.

Question: 7.7.1. Are the services for only contractor emergency responder personnel?

Do outside agencies have to provide their own?

Answer: Yes, the emergency responder rehabilitation services are for GBAFAF emergency responders personnel

Question: 7.9. Are there any facilities outside the response times as outlined in DODO 6055.06 and AFI 32-2001, para. 2.3.3, 2.3.4?

Answer: Yes, there are facilities outside of the response times outlined in DODI 6055.06 Will the government provide building numbers and distance from fire station?

Answer: Yes, building and approximate distance from the fire station will be provided on industry day.

Question: 7.9.7.11. Is there an Installation Wild land Fire Management Plan? Will FES have to follow NFPA 1051?

Answer: Yes, the RMO is developing a Fire Management Plan and a copy will be provided to the contractor when completed. The contractor will be required to follow some portions of NFPA 1051 (training/safety, no certifications will be required)

Question: 7.12. Are all CFR vehicles able to carry 3 firefighters?

Answer: Yes, all CFR vehicles are able to carry 3 firefighters (one P-19 Striker, two RIVs P-34, two Pumpers P-24/P22, one Rescue P-32, one Tanker P-26 and two Command Vehicles)

Who will be notified when unable to support, due to the two CFR vehicles required for GB AFAF?

Answer: The contractor’s project manager and GB COR

Question: 7.12. What DODI, AFI etc. are the units utilizing Auxiliary Field "6" operating under?

Answer: AFPAM 32-2004, AFI 32-2001 and Aux 6 user requirements Question: 7.12 “Overtime personnel shall not be used for these standbys.” Please clarify the intent of this sentence.

Answer: “Overtime personnel shall not be used for these standbys” does not apply and will be removed from the PWS Is Aux 6 standby work somehow reimbursable?

Answer: No, Aux 6 standbys are not reimbursable If it is part of the firm fixed price, why is overtime an issue here? Please clarify.

Answer: Yes, this is a firm fixed price. “Overtime personnel shall not be used for these standbys” does not apply and will be removed from the PWS Question: 7.14. Will the contractor provide and maintain extinguishers to (NGA)? Please define system checks?

Answer: Yes, the contractor shall maintain and provide extinguishers to NGA. Examples of systems to be checked are: fire alarm, detectors and sprinkler systems evaluation per the PWS, Section I, Description of Service, para 1 Scope of Work.

Question: 7.15. Is there a TIG to NFPA 1582?

Answer: Yes, there is a 1582 TIG If so will the government provide?

Answer: Access to 1582 TIG can be obtained via AETC Fire and Emergency Services web and Fire and Emergency Services SharePoint/ web sites

Question: 7.16.1. What are the IAW established directives?

Answer: Do to ACES server changes this portion of para 7.16.1 no longer applies and will be corrected.

Does the Air Force provide or have available, operation and software maintenance training for ACES-FD/RM?

Answer: No, there is no operation or software maintenance training for available ACES-FD/RM.

What is the government designated replacement database? Is the current ACES-FD/RM being phased out?

Answer: As of 1 August ACES will convert from a Server Base system to a Web Based system...

Question: 7.16.1. Will the contractor have to place contractor owned equipment in ACES -FD/RM servers?

Answer: Yes, for tracking purposes (equipment inspection, testing dates, etc.)

Question: 7.17. Who pays for salaries for firefighters during calls for mutual aid to local community?

Answer: Mutual aid responses are performed with on duty personnel, there for the contractor continues to pay firefighters salaries.

Who pays for damaged equipment, used supplies or equipment becomes unserviceable during a response for mutual aid to local community.

Answer: Cost of damaged equipment, used supplies or equipment becoming unserviceable during a mutual aid response, beyond normal wear and tear will be negotiated.

Question: 7.19. Must the company name be on the uniform?

Answer: Not required

Question: 7.22. Is there a government owned equipment listing? Does the government provide SCBA gear and Proximity Gear?

Answer: Yes, there is a government owned equipment list in the PWS (Sections V Technical Exhibits). No, the government will not provide SCBAs and proximity gear, per the PWS, Section I, Description of Service, para 1 Scope of Work.

Question: 7.20. Will a copy of the FESAP/MICT be provided for review, prior to bid?

Answer: No, there are no plans to provide a copy of the FESAP/MICT at this time

Question: 7.27. Is there a TIG to NFPA 1500? Please provide.

Answer: The TIG for 1500 is still being developed

Question: 7.26. Will the contractor be provided location, and type of all confined spaces, prior to contract start?

Answer: Information will be carried forward and provided during the transition

Question: 7.26. Is all confined space and high angle rescue equipment furnished by the contractor? Please clarify.

Answer: Yes, all confined space and high angle rescue equipment is furnished by the contractor, per the PWS, Section I, Description of Service, para 1 Scope of Work

Section 8 Security Forces Services

Question: 8.4. If the Primary Uniform is the dress blue pants/shirt with metal badges, will contractor be required to provide both a primary and a secondary uniform?

Answer: No. The PWS does not mention a secondary uniform. The correct PWS terminology is alternate uniform. The contractor is required to provide primary and alternate uniforms. Examples of alternate uniform items are light blue color shirt and waist length jacket.

Question: 8.4.1."The primary uniform is for performing duties requiring interaction with general public, such as installation entry control point, installation law enforcement duties, and formal gatherings". 31-122.4.20 allows for a Utility Uniform for Flight line, training, etc.

Will RMO allow this uniform as primary due to harsh environment and frequent flight line and desert patrol, etc?

Answer:

A. The PWS does not reference AFI 31-122.

B. Materials may be negotiated with RMOD approval

Question: 8.4.1.1. AFI21-101-14.19.2.6.1 prohibits the wear of Metal Insignia/badges on the flight line.

Will the RMO allow soft badges?

Answer:

No, the RMO will not allow soft badges AFI 21-101 is intended for maintainers.

Section I-9 Logistic Services

Question: 9.8.14. AFI 24-301 paragraph 8.10. states: "Licensing Contractor Personnel: IAW DOD 4500.36-R para C8.2.5. Contracts and agreements will require that operators comply with licensing requirements of the State and local motor vehicle laws. DoD contractor employees shall not be issued Optional Form (OF 346), ―U.S. Government Motor Vehicle Operator’s Identification Card‖ or AF Forms 2293 or 2296. DoD contractor employees assigned to operate either government owned/leased equipment in performance of their contract shall be certified, by the contractor and at the contractor’s expense, as being fully qualified to operate the vehicles/equipment to which they are assigned. The prime contractor shall document all operator qualifications. This documentation shall be provided to the administrative contracting officer before any contract employee engages in any mode of equipment operation. This letter will be updated as necessary and remain on file with OR&L and the administrative contracting officer.

Is it the intent of the government for the contractor to issue an additional license to personnel operating Government Vehicles or follow the guidance in AFI 24-301 paragraph 8.10?

Question: 9.9.3. As the U-Drive-It (UDI) fleet required by the PWS is contractor furnished and only known qualified contractor personnel are insured.

Will the government assume liability and provide insurance for all other users?

Answer: Government personnel are insured by the government

Question: 9.9.4. Please explain other contract locations in terms of (distance, interstate, intrastate, etc.).

Answer: Phoenix and Tucson metro areas except when transporting target vehicles and materials which include all of the states bordering Arizona as listed in paragraph 9.9.2.

Question: 9.9.4. Please provide a listing and work load of cargo and munitions to be moved.

Is there a requirement to move oversize loads and if so how many and to where this may necessitate the contractor paying for an Oversize Load permit(s)?

Answer: Oversized permits required are for the contractor to move his own and EOD equipment back and forth to the ranges and target vehicles and equipment from other states.

The contractor is not responsible for moving munitions on the public highway

Question: 9.9.6. With reference to "all users on base," does this include deployments?

Answer: Yes If so please provide a workload estimate.

Answer: Deployments are a monthly occurrence and range from 2 personnel to 500 personnel.

Does the using group pay for the fuel?

Answer: Yes If not please provide estimated fuel use.

Question: 9.9.6. Does the loading or unloading of equipment/supplies involve munitions/weapons?

Answer: Yes If so does the government provide training?

Answer: No

Question: 9.9.7.1. Please define "vicinity" (size of area) with reference to "… remove all associated trash, glass, tires, plywood, and vehicle parts from the vicinity of the vehicle extraction site."

Answer: Everything within 100’ of the vehicle removal site and everything that falls off in the course of moving it to the base.

Question: 9.9.7.1. Please provide a workload estimate as to the number of abandoned vehicles to be removed yearly?

Answer: No more than 12 annually

Question: 9.9.7.1. Please clarify the distances to the areas from which abandoned vehicles are to be removed.

Answer: ID DISCUSSSION MAP Answer: As much as 240 miles round trip from GBAFAF.

Please clarify if these locations are on roads or off road and if off road how far and the type terrain.

Answer: As much as 60 miles on primitive roads which are not maintained Please explain how "The contractor shall limit damage to natural resources to the extent possible..."

Answer: To max extent reasonable…Use your expertise.

Section I-10 Range Maintenance Services

Question: 15.8.4.16 and 15.8.4.19 refer to the same target (328).

Please clarify which paragraph and work requirement is correct.

Answer: There are 2 artillery sites. Target number will be corrected.

Question: 15.7.9.1. The PWS does not reference the run-in lines that are mentioned in AFI 13-212LukeSup paragraph 3.7.4.

Please clarify if there is a requirement to maintain these run-in lines and if so to what standard.

Answer: There is no requirement to maintain the Nuke run in lines.

Question: 15.7.4. Please clarify how many strafe pits are on each range. The wording suggests a total of 4, "two on the right side of the main tower and two on the left side of the main tower."

Answer: There are 2 strafe pits on each numbered range.

Question: 15.7.9.3. Please provide the specifications/description for the radar reflectors (size, height, etc.).

Answer: Approximately 8’ X 8’ mounted in a trailer

Question: 15.8.2. Please clarify what 40% and 50% mean. Is it 40% and 50% of the targets on each tactical range or 40% and 50% of the total targets on all Tactical ranges?

Answer: 40% pertains to the maximum percentage of targets the contractor will have to replace on each Tactical range (NTAC, STAC, ETAC) in a year.

50% pertains to the percentage of targets the contractor will have to paint on each Tactical range annually.

Section IV General Information, Network Professional Training Program

Question: 3.5. What is the Training Standardized Criteria for CSAs?

Answer: Must possess A+ certification

Question: 3.5. How will the appointed CSAs receive training/knowledge on local host base NETOPS protocols?

Answer: Certified CSA will coordinate training with 56 COM SQ

Question: 3.5. What specific area of AFI 36-2201 addresses task qualification process for knowledge-level training and performance training of CSAs?

Answer: PWS tweak…AFI 36-2201 does not address task qualification/knowledge level for CSA.

Reference to AFI 36-2201 will be corrected before Contractor Solicitation.

Answer: What AFI references qualifications/certifications are required for Client Support Administrator?

Answer: DODI 8570

Network Professional Training Program. The contractor shall appoint a primary and alternate Client Support Administrator (CSA) and ensure training satisfies standardized criteria. This person shall be responsible/knowledgeable of configuration of PCs and related hardware, basic networking, procuring, managing and troubleshooting all computer systems, printers, scanners, software and information technology equipment required to meet the performance of the contract image1.emf

25OWS MOA 2013.pdf

UNIT DATA SHEET Reviewed By:

25 OWS KP

25 OWS - EU Review Accomplished 07-Oct-13 56 RMO DPW Next Review (NLT) 06-Oct-14

Airfield Hours: Link to FLIP/Appch Plates https://

Alternate Link http://www.fltplan.com/AwMainToApproachPlates.exe?CRN10=1&CARRYUNAME=PILOT&MODE=SEARCH&end=end

Airfield ICAO

KGXF

DSN

896-5258 896-5272 896-5241

UNIT ADDRESS LINE 1:

UNIT ADDRESS LINE 2:

UNIT ADDRESS LINE 3:

COMM

ALT Ops Location Telephone 1

AFLD Services Telephone 1 AFLD Services Telephone 2

EU / Agency

Location

BASE NAME:

ALT OPS LOCATION

7101 Jerstad Luke AFB, AZ 85309

Gila Bend AFAF, AZ

Note: Deviations from AFMAN 15-129 standard/default highlighted in

TAF Service Provided By 25 OWS:

NOT A 25 OWS TAF LOCATION

Standard Specification and Amendment Criteria Other Than Ceiling and Visibility

Standard Specification and Amendment Criteria Ceiling or Visibility Criteria

Advisory Type Criteria Area Affected Desired Lead Time

(other than those stated in Issued By Winds 16-24 Knots Observed Winds 16-24 knots within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Winds 25-34 Knots Observed Winds 25-34 knots within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Winds ≥ 35 Knots Sustained Observed Winds ≥ 35 knots within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF

Crosswinds 15-19 Knots Observed Crosswinds 15-19 knots within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF

Crosswinds 20-24 Knots Observed Crosswinds 20-24 knots within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF

Crosswinds ≥ 25 Knots Observed Crosswinds ≥ 25 knots within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Lightning /Thunderstorms > 5 and

< 25 NM

Observed Lightning /Thunderstorms > 5 and <= 25 NM occurring for the Runway Complex. Aerodrome (>5 TO <= 25NM)

Observed KGXF

Chill Index Caution/No-Fly Zones Observed Chill Index Caution < 15F or No Fly Zones < -25F Aerodrome (5NM)

Observed KGXF

Watch Type Criteria Area Affected Desired Lead Time

Mission Impact (other than those stated in

AFMAN 15-129) Issued By Freezing Precipitation Potential for Freezing Precipitation exists (SWAP) Aerodrome (5NM) As Potential Warrants 25 OWS Hail Potential for Hail >= 1/2 inches. (SWAP) Aerodrome (5NM) As Potential Warrants 25 OWS Heavy Rain Potential for Heavy Rain >= 2 inches. within 12 hours. (SWAP) Aerodrome (5NM) As Potential Warrants 25 OWS Heavy Snow Potential for Heavy Snow >= 2 inches. within 12 hours. Aerodrome (5NM) As Potential Warrants 25 OWS High Winds Potential for High Winds >= 50 knots. Winds from: (SWAP) Aerodrome (5NM) As Potential Warrants 25 OWS Lightning Potential for Lightning within 5nm exists for the Runway Complex. (SWAP) Aerodrome (5NM) 30 minutes 25 OWS Sandstorm Potential for Sandstorm Visibility <= 5/8 SM (SWAP) Aerodrome (5NM) As Potential Warrants 25 OWS Tornado Potential for Tornadic Activity exists (SWAP) Aerodrome (5NM) As Potential Warrants 25 OWS Winds Potential for Winds >= 35 but < 50 knots. Winds from: Aerodrome (5NM) As Potential Warrants 25 OWS

Warning Type Criteria Area Affected

Desired Lead Time Mission Impact

(other than those stated in

AFMAN 15-129)

Issued By

Lightning Observed Lightning within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Turbulence ≥ Severe Observed Severe Turbulence within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Icing ≥ Moderate Observed Moderate Icing within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Low-Level Wind Shear Observed LLWS within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Tornado or Funnel Cloud Observed Tornado or Funnel Cloud within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Squall Line Observed Squall Line within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Sandstorm Observed Sandstorm within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Hail Observed Hail within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Volcanic Ash Observed Volcanic Ash within 5nm occurring for the Runway Complex. Aerodrome (5NM) Observed KGXF Freezing Precipitation Freezing Precipitation expected (SWAP) Aerodrome (5NM) 90 minutes 25 OWS Hail Forecasted Hail >= 1/2 inches. (SWAP) Aerodrome (5NM) 120 minutes 25 OWS Heavy Rain Potential for Heavy Rain >= 2 inches. within 12 hours. (SWAP) Aerodrome (5NM) 90 minutes 25 OWS Heavy Snow Heavy Snow accummulation >= 2 inches. within 12 hours. Aerodrome (5NM) 90 minutes 25 OWS High Winds Forecasted High Winds >= 50 knots. Winds from: (SWAP) Aerodrome (5NM) 120 minutes 25 OWS Sandstorm Forecasted Sandstorm Visibility <= 5/8 sm. (SWAP) Aerodrome (5NM) 90 minutes 25 OWS Tornado Tornado expected (SWAP) Aerodrome (5NM) 30 minutes 25 OWS Winds Forecasted Winds >= 35 but < 50 knots. Winds from: Aerodrome (5NM) 90 minutes 25 OWS

NOTES:

Observed criteria is for open airfield hours only. 25 OWS will not issue any of the observed criteria for this location.

Weather Watches

Weather Warnings

Weather Advisories

Agency DSN Number Commercial Number

COMMAND POST

COMMAND POST PRIMARY

COMMAND POST ALT 896-5241

TOWER

ATC PRIMARY 896-5289

ATC BACKUP 896-5189

BASE OPERATIONS PRIMARY 896-5233/896-5298/896-8818

MISC

OBSERVER 896-5258

LUKE EU 896-5241

PRIMARY WWA CONTACTS ARE MAINTAINED IN THE JET/IWWC DATABASE

ACCESSIBLE TO BOTH 25 OWS AND 56 EU.

The JET/IWWC contact listing database is the definitive source; under routine conditions, modification will be by mutual consent.

Emergency or temporary changes may be necessary without prior coordination.

Black = Primary / Red = Alternate

25 OWS will notify Primary Command and Control, ATC, and EU when Weather Watches, Warnings, or Advisories are issued during an IWWC outage.

IWWC Back-Up Contact Information

896-5800/5600

Unit Info

TAF Criteria

WWA Criteria

IWWC Back-Up Contacts