INDEFINITE DELIVERY, INDEFINITE QUANTITIES (IDIQ)

BASE PAVEMENTS AT

LUKE AIR FORCE BASE AND GILA BEND AF AUXIARY FIELD, ARIZONA

DIVISION 1 – GENERAL REQUIREMENTS

SECTION 01010 - SUMMARY OF WORK

PART 1 GENERAL

1.01 REQUIREMENTS INCLUDED:

A. Definitions

B. Work covered by contract documents

C. Use of premises.

D. Record drawings

1.02 DEFINITIONS:

A. Any reference throughout this specification to “Architect ‑Engineer” should be understood as a reference to “Contracting Officer.”

B. Any reference throughout this specification to “Owner” should be understood as a reference to “The Government.”

C. Payment provision contained in any portion of the referenced specifications and standards are to be disregarded.

1.03 WORK COVERED BY CONTRACT DOCUMENTS:

A. The following is a summary of work for Project No. NUEX 11-XXXX located at Luke AFB and Gila Bend AFAF, Arizona. The project shall include but is not limited to:

All pavement maintenance, replacement and restoration items included in the bidding documents when defined in the specific Delivery Order Document.
Base access and entry procedures. All workers shall obtain base pass identification to perform work on federal installations. Process for contractors DBIDS pass. Refer to policy dated Sept 10 for contractor employee installation access.

Hazmat, Material Usage Reports, Disposal and Herbicides. All materials and supplies entering or exiting federal installations shall be tracked and documented. Submit Hazmat questionnaire, environmental reporting form, and disposition of materials, with MSDS for contract and individual delivery orders. Herbicide reporting form shall also be submitted as required.

01010-1

Executive Order 13514; Federal Leadership in Environmental, Energy and Economic Performance. ETL 08-13; Incorporating Sustainable Design and Development (SDD) Construction Policy. Contractor shall divert waste, at a minimum, 50% from landfill. Recycle or salvage 50% construction demolition and land clearance waste. Recycled materials for use in construction shall be 5-15% as required. The government reserves the right to approve or reject recycled products for new construction.

The above description of work is for the purpose of general information only and is not intended to include and describe every feature or item of work or to define the scope of work.

Use of environmental reporting for HAZMAT and herbicide usage is mandatory.

1.04 UTILITIES:

Water, gas, and electricity will be furnished to the Contractor by the government from the Government’s existing system outlets.

Utilities will be furnished at no cost to the Contractor, except for telephone.

Government may (at their option), furnish to the Contractor approximately 100’ x 100’ space within the Contractor’s staging area for their placement of a construction trailer and to allow for storage/staging of material for this project. This area shall be reviewed at the time of the Pre-Construction Meeting.

01010-2

SECTION 01031

INTERFACING OF NEW AND EXISTING WORK

PART 1GENERAL
1.01REQUIREMENTS INCLUDED:

A. Work items shall be scheduled to avoid or minimize interference between existing to remain and new work.

B. In addition to demolition specified in Section 02050 and that specifically shown, shall cut, move, or remove items as necessary to provide access or to allow alterations and new work to proceed. This includes:

1. Repair or removal of hazardous conditions.

2. Removal of items and items serving no useful purpose, such as abandoned piping, conduit etc, unless otherwise indicated.

3. Removal of unsuitable or extraneous materials like debris and deteriorated concrete.

4. Cleaning of surfaces and removal of surface finish as needed to install new work and finishes.

C. Patch, repair, and refinish existing items to remain to the specified condition for each material with a workmanlike transition to adjacent new items of construction.

1.02 RELATED REQUIREMENTS:

A. Section 01010: Summary of Work.

B. Section 01045: Cutting and Patching.

C. Section 01300: Submittals.

D. Section 01500: Construction Facilities and Temporary Controls.

E. Section 01700: Contract Close Out.

F.Section 02050: Demolition and Removal.
1.03ALTERATIONS, CUTTING, AND PROTECTION:

A. Assign the work of moving, removal, cutting, and patching to trades qualified to perform the work in a manner to cause least damage to each type of work, and provide means of returning surfaces to appearance of new work.

B. Perform cutting and removal work to remove minimum material necessary and in a manner to avoid damage to adjacent work.

1. Cut finish surfaces such as concrete and asphalt in a straight line or at a natural point of division.

C. Perform cutting and patching as specified in Section 01045.

D.Protect from damage by adjacent work all existing structural members, finishes, facility systems and equipment that are to remain.
PART 2PRODUCTS
2.01SALVAGED MATERIALS:
A.Do not incorporate salvaged or used material in new construction except as indicated or with approval of Contracting Officer.
2.02PRODUCTS FOR PATCHING, EXTENDING, AND MATCHING:

A. Contractor work shall:

1. Provide same products or types of construction as that in existing structure, as needed to patch, extend, or match existing work.

a. Generally, Contract Documents will not define products or standards of workmanship present in existing construction. Contractor shall determine products by inspection and any necessary testing. Workmanship standard shall be determined by use of the existing as a sample for comparison.

2. Require that patching, extending, or matching be performed as to the extent necessary to make work complete and consistent with identical standards of quality.

PART 3EXECUTION
3.01PERFORMANCE:

A. Patch and extend existing work using skilled mechanics who are capable of matching existing quality of workmanship.

B. Quality of patched or extended work shall be not less than that specified for new work.

3.02 DAMAGED SURFACES:

A. Patch and replace any portion of an existing finished surface which is found to be damaged, lifted, discolored, or shows other imperfections with matching material.

1. Provide adequate support of substrate prior to patching the finish.

2. Refinish patched portions in a manner to produce uniform color and texture over entire surface.

3.03 TRANSITION FROM EXISTING TO NEW WORK:

A. When new work abuts or finishes flush with existing work, make a smooth and workmanlike transition. Patched work shall match existing adjacent work in texture, color, and appearance so that the patch or transition is invisible at a distance of five feet.

END OF SECTION

01031-3

C. Damp cure cementatious grout for four days.

3.07 FIELD QUALITY CONTROL

A. Field inspection and testing will be performed under provisions of Section 01400.

END OF SECTION

Other files

File Type Posted
Questions and Answers.docx DOCX document
Highway Wage determination Maricopa.docx DOCX document
ETL 09-6 Landing Zone Etc.pdf PDF
afi32-1042.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE.doc DOC document
11 BASE PAVEMENT SPECSMain.doc DOC document
FY 11 Bid Sch Airfield Pavements.xls XLS spreadsheet
FA4887-11-R-0003 Airfield and Base paving Solicitation Document.rtf RTF text file
SOW Airfield Paving.rtf RTF text file
FY11 Bid Sch Base Pavements.xls XLS spreadsheet
etl_08_13.pdf PDF
ETL 09-6 Chg 1.pdf PDF
AF Form 3064 CP Schedule.xfdl XFDL file
ETL 4-2 Change 1.pdf PDF
11 AIRFIELD SPECS.docx DOCX document
Contractor's HAZMAT Questionnaire.doc DOC document
BASE PVMT FORM 66 New.xls XLS spreadsheet
ETL09-2.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .