BASE PVMT FORM 66 New.xls

XLS spreadsheet 39 KB Posted

Attached to
Airfield and Base Paving IDIQ on Luke Air Force Base and Gila Bend Auxiliary Field
Solicitation number
FA4887-11-R-0003
Issued by

About this file

AF Form 66

View the file

Other files

File Type Posted
Questions and Answers.docx DOCX document
Highway Wage determination Maricopa.docx DOCX document
ETL 09-6 Landing Zone Etc.pdf PDF
afi32-1042.pdf PDF
PAST PERFORMANCE QUESTIONNAIRE.doc DOC document
11 BASE PAVEMENT SPECSMain.doc DOC document
FY 11 Bid Sch Airfield Pavements.xls XLS spreadsheet
FA4887-11-R-0003 Airfield and Base paving Solicitation Document.rtf RTF text file
SOW Airfield Paving.rtf RTF text file
FY11 Bid Sch Base Pavements.xls XLS spreadsheet
etl_08_13.pdf PDF
SOW Base paving.rtf RTF text file
ETL 09-6 Chg 1.pdf PDF
AF Form 3064 CP Schedule.xfdl XFDL file
ETL 4-2 Change 1.pdf PDF
11 AIRFIELD SPECS.docx DOCX document
Contractor's HAZMAT Questionnaire.doc DOC document
ETL09-2.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Spec Sort

PROJECT NUMBERPROJECT TITLESOLICITATION / CONTRACT NO.
1/1/11SCHEDULE OF MATERIAL SUBMITTALSNUEX 11-0501MAINTAIN BASE PAVEMENTFA4887-11-R-0003
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
LINE NO.ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATIONOF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACUTER'SRECOMMENDATIONSMANUFACUTER'SWARRANTYCATALOG DATAOPERATINGINSTRUCTIONSSEE PARAGRAPHREFERENCEOTHERREQUIRED SUBMISSION DATEDATE RECEIVED IN CON-TRACTINGDATE TO CIVIL ENGINEER-INGRETURN SUSPENSE DATEFOLLOW-UPDATE CONTRACTOR NOTIFIEDCONTRAC-TOR RE- SUBMIT-TALFINAL APPROVALREMARKS
APPROVEDDISAPPROVED
Contract Closeout5 Days
101010, 1.54after
As Built DrawingsNTP
Preliminary Network5 Days
2[01310, 1.02, A, 1]4after
Construction Pregress ScheduleNTP
Network Analysis5 days
3[01300, 1.02, A, 2]4after
Construction Progress ScheduleNTP
Construction Progress5 Days
4[01300, 1.02,A,3]4after
Construction Pregress ScheduleNTP
Network Analysis Software5 Days
5[01300,1.02,A,4]4after
Construction Progress ScheduleNTP
Final Inspection Request5 Days
6[01700, 1.03, A]4after
Contract CloseoutNTP
Utlity Outages5 Days
7[01800, 1.04, A]4after
Special ConditionsNTP
Certification5 Days
8[02231, 1.04, A]4After
Aggregate Base CourseNTP
Mix Design5 Days
9[02238, 1.04, A]4After
Port. Cement Stab. Base CourseNTP
APPLICATION5 Days
10[02542,1.03,A]4after
PAVEMENT REINFORCING FABRICNTP
MIX DESIGN5 days
11[02510,1.03, A]4after
HOT MIX ASPHALT (HMA)NTP
Mix Design
12[02520,1.03, A]4See Specs
PORTLAND CEMENT CONC PVMT
Mix Design /Tests
13[02543, 1.02 A]4See Specs
Coal Tar Sealent
Equip. / Surface Smoothness
14[02546, 1.02, A]4See Specs
Cold-Mill Bitimum
Proceedure5 days
15[02566, 1.02, A]4after
Reseal Joints In Rigid PavementNTP
Proceedure / Mix Design5 days
16[02572, 2.03, A]4after
Asphalt Slurry SealNTP
Proceedure5 days
17[02574, 2.01, A]4after
Preservitive SealNTP
Proceedure5 Days
18[02575, 2.03, A]4after
Hot Asphalt Rubber Chip SealNTP
Product Data5 Days
19[02987, 1.02, A]4after
PAVEMENT MARKINGNTP
Proceedure / Product Data5 days
20[02579, 2.01, A]4after
Crack Sealingsampling
Product Data5 days
21[02623, 1.02,A]4after
CONC WORK FOR WALKWAYSNTP
Product Data5 days
22[02900,1.02,A]4after
SOIL STABILIZATIONNTP
Proceedure / Product Data5 days
23[03100,1.06,A]4after
CONCRETE FORM WORKNTP
Proceedure / Product Data5 days
24[03200,1.04,A]4after
CONCRETE REINFORCEMENTNTP
PRODUCT DATA5 DAYS
25[03250,1.03, A]AFTER
JOINT SEAL & REINF. CONC. PVMTSNTP
MIX DESIGN5DAYS
26[03300,1.02,A]44AFTER
CAST IN PLACE CONCRETENTP

&L&"Arial"&BAF Form 66, Computer Generated