Solicitation Questions and Answers April 9 2009.doc
DOC document 24 KB Posted
- Attached to
- BASE PAVEMENT
- Solicitation number
- FA488709R0013
About this file
Solicitation questions and answers 9 April 2009
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation questions and answers: 9 April 2009
1. The Bid schedule spread sheet talks about the Gila Bend AFAF but there is no place in the CLINS for this number. Is it to be a lump sum under Luke for both locations?
Response: We did not list separate CLINS for Gila Bend. The negotiated line item cost is valid for both Luke and Gila Bend project. See Item # 2 for cost differential.
2. Is there a % markup for the Gila Bend location from Luke?
Response: At either locations - typically a project is a project. We have identified Gila Bend projects for a possible 1-2% mark-up or inflation factor. Percentage would be based on project cost not line item costs. The government reserves the right to approve or disapprove this increase. Please see Bid Schedule Basic year bottom of the page.
3. On the Bid schedule are the quantities a total for both locations?
Response: Quantities are only estimation but are a total for both locations. We did not list separate CLINS for Gila Bend. The negotiated line item cost is valid for both Luke and Gila Bend project.
File details come from the government source that posted it. Updated .