Updated Section 01011 - Design Req 10 Sep 2024.pdf
PDF 408 KB Posted
- Attached to
- Sustain Overhead Electrical DMAFB
- Solicitation number
- FA487724R0021
About this file
This document is a Request for Proposal (RFP) for a project to design, plan, and perform repairs and replacements of overhead power lines and utility poles along Wilmot, Yuma, Herky, and Zapper Roads on Davis-Monthan Air Force Base in Arizona.
The project requires the contractor to replace utility poles, cross-arms, conductors, air brake switches, and other electrical components along the identified routes. Specific details include replacing 14 utility poles with 45-ft Western Red Cedar poles, 7 switch poles with 55-ft Western Red Cedar poles, and installing new 600-amp disconnects, air brake switches, lightning arrestors, cross-arms, and associated hardware. The contractor must also coordinate with the cable TV provider for service removals and reinstallations. The total performance period is 287 calendar days. Proposals are due by 14 August 2024 at 1:00 pm Arizona local time.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Davis-Monthan Air Force Base, Arizona FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-1
SECTION 01011 - DESIGN REQUIREMENTS
1. PROJECT DESCRIPTION
1.1. General. This request for proposal (RFP) provides for the design, plans, specifications, and repair by replacement overhead (OH) power lines and Utility poles with all new components and associated hardware along Wilmot, Yuma Rd., Herky and Zapper on Davis-Monthan AFB, AZ (see figure 1.2 for the specific location below). The contractor provides new Utility Poles to include cross arms, 4/0 / Aluminum Conductor Steel Reinforced (ACSR), and Air Brake Switches rated at 600 AMPS. Coordinate with cable TV provider for removal and reinstallation of the existing services. See section 1.6 for specific project design and construction requirements.
All primary overhead phases need to upgrade to 4/0 AWG conductors (See Figure 1.2).
1.2. Location. The project site is located at Davis-Monthan Air Force Base (Tucson) along Wilmot, Yuma Rd., Herky and Zapper Rd. Arizona. See Figure 1.2 for the existing site locations.
Figure 1.2
1.3. Project Programming. Government programming requirements, classification of work, project approval levels, and funding appropriation have defined the requirement for execution of this project. The Contractor shall work the project as a whole. The Contractor shall maintain documentation to include, but not limited to, progress reports, requests for payment, change orders, modifications, and any other contractual (cost) documents for each project’s scope of the total project. All design and engineering costs shall be incorporated into this project.
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-2
1.4. Codes, Standards, and References.
1.4.1. The Davis-Monthan Air Force Base Design Compatibility Guidelines (DCG) are incorporated by reference into the contract specifications. All provisions of the base DCG shall be complied with unless specifically deleted by the project documents.
1.5. Design and Construction Schedule. The Contractor shall provide as part of their proposal a preliminary design construction completion schedule for the Government’s review and approval. The total performance period cover progress from Notice To Proceed (NTP) to construction completion (PoP) and beneficial occupancy is 287 calendar days total, including the 31 days shown for project closeout and completion. The number of days shown address an approximate number of calendar days and are only suggested for the Contractor’s use. The Contractor shall clearly note any deviations to the suggested days as it relates to the benefit of the proposed project. The Government will evaluate Contractor proposed calendar days based on the best interests of the project execution and the Government’s requirements.
1.5.1. Following contract award, the Contractor shall finalize their proposed design and construction completion schedule. The Contractor shall prepare the schedule using the AF Form 3064, Contract Progress Schedule. The Contractor shall submit for government review and approval the AF Form 3064 no later than ten (10) calendar days following issuance of the Notice to Proceed.
1.6. Project Specific Design and Construction Requirements. The Contractor shall incorporate as part of their design and include in the construction the following requirements in accordance with all regulations, requirements, and standards identified in this RFP. The following requirements provide more detail than the generic descriptions provided in Section 1.1 of this RFP; and are the minimum requirements that ultimately satisfy the User’s needs and wants. The Contractor shall provide a complete and usable facility based around the User’s needs and wants and constructed in accordance and in compliance with commercial and industry standards.
1.6.1. General Requirements.
1.6.1.1. The construction site is in a (controlled / restricted) area and will require the Contractor and subcontractors to have the requisite badging and identification to access this project site. The Contractor shall consider in the contract documents (e.g., the construction breakdown cost estimate) the reasonable costs and effects of daily, short delays in accessing the project site, as required by the restrictive access requirements or by local alert conditions.
1.6.1.2. The Contractor shall provide design plans and specifications at the 65%, 95% and 100% (Design suitable for construction) milestone levels. The design shall be based on the information provided in the Task Order RFP, any government sponsored project site visits, and additional information as shall be provided by the Government. Each design milestone level shall meet the associated design submittal requirements as stated in Part 2, Design Submittal Requirements, of this section.
1.6.1.3. The Government will provide as-built drawings as requested by the Contractor. See Section 2.5.1.
1.6.1.4. All construction work shall be accomplished between the hours of 0630 to 1700, Monday through Friday, unless otherwise approved in writing by the Contracting Officer.
1.6.1.5. The project shall conform to all applicable Federal, State, and local laws, regulations and base-specific standards and applicable Unified Facilities Criteria (UFC). Where there is a conflict between the referenced standards the most stringent shall take precedence.
1.6.2. Demolition Requirements.
1.6.2.1. Power outages shall be kept to a minimum; all existing infrastructure shall remain in place and in service until the Overhead (OH) construction is complete to minimize the impact to the operations of the buildings. Disconnect and remove existing all associated electrical circuits, cables, devices, line insulators, raceways and power riser etc.
to source from the overhead electrical distribution system and recycle the copper cable providing a credit to the Government. Primary and secondary Riser conductors and conduit affected by project to be inspected and reused.
Work Included in this Contract: The following descriptions are for general reference only and shall not be construed as a complete list of all operations to be performed.
1.6.2.2. Disconnect and remove existing overhead primary electric distribution lines from existing Utility Poles as identified in section 1.6.10.2.2 – 1.6.10. 2.
1.6.2.3. Disconnect and remove Air Brake Switches
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-3
1.6.2.4. Remove the solid blade disconnects from the overhead electrical distribution system and salvage them to the Government. The Contractor shall coordinate the return of this property through the Contracting Officer.
1.6.2.5. Completely remove the existing Utility Poles as identified in section 1.6.10.2.5 - 1.6.10.7 including all hardware and the Cross Arms and dispose of properly off base (See Figure 1.2).
1.6.2.6. Remove the existing guy wires, insulators, lightning arrestors, etc. from the overhead electrical distribution system and dispose of properly off base. All power poles cross arms, guy wires, insulators and lightening arrestors shall become the property of the Contractor and removed from Davis-Monthan AFB.
1.6.2.7. All conductor removed from the project shall be recycled by the Contractor and a credit provided to the Government in the Contractor’s proposal.
1.6.3. Civil Requirements.
1.6.3.1. Field Information. Base utility information, which may be provided for this RFP, is the best information available and may be provided to assist the Contractor during the design of this project. The Contractor is solely responsible for field verifying all information given. The Contractor is also responsible for obtaining all information necessary to properly design and construct the project. Information gathering during the design shall be coordinated through the Contracting Officer. Any field surveying required to provide utility locations, manhole inverts, verification of existing grades and features, etc., shall be the responsibility of the Contractor and shall be tied into the base surveying datum.
1.6.3.2. The Contractor shall arrange for bluestaking of the site and any affected areas for the purposes of determining information applicable to, necessary for and pertinent to the investigation and design services as well as the construction services of this project.
1.6.4. Landscape Requirements.
1.6.4.1. Contractor shall restore the landscaping back to original condition, to the maximum extent possible, in a manner approved by the Contracting Officer.
1.6.5. Architectural Requirements. Not used.
1.6.6. Structural Requirements. Not used.
1.6.7. Mechanical Requirements. Not used.
1.6.8. Plumbing Requirements. Not used.
1.6.9. Fire Protection/Detection Requirements. Not used.
1.6.10. Electrical Requirements
1.6.10.1. The project location consists of overhead primary electric distribution (13.8 KV) along Yuma Rd. between Ramsgate Rd and Taxiway Echo, and along Zapper and Herky Rd. (See Figure 1.2). The designer record will provide calculations as part of all design and provide information in design analysis of design phase.
1.6.10.2. Installation
1.6.10.2.1 Provide new poles with all electrical accessories as necessary to satisfy the infrastructure (primary feed replacement) from existing utility poles along Yuma Rd. beginning at Ramsgate and ending at TXY Echo, Herky Blvd and Zapper Ave (See Figure 1.2). The contractor shall be responsible to ensure electrical power and all other services are fully restored at the completion of construction.
1.6.10.2.2 Replace existing primary lines with new 4/0 lines, between the follow locations (mostly along Yuma):
Line section: Pole 676 to Pole 672 to Pole 857 to Pole 845.
Line section: Pole 849 to 851 Line section: Pole 845 to Pole 839 to Pole (Riser at Bldg. 4870).
1.6.10.2.3 Replace existing primary lines with new 4/0 lines, between the follow locations (Mostly along Herky):
Line section: Pole 661 to Pole 659 to Pole 642 to Pole 646 to Pole 646a(BLD 257).
Line section: Pole 646 to 239 Line section: Pole 649 to Pole 643.
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-4
1.6.10.2.4. Replace existing primary lines with new 4/0 lines, between the following locations (Mostly along Zapper) Line section: Pole 857 to Pole 651.
1.6.10.2.5. Replace existing Poles with new Class 2 45-ft Western Red Cedar Poles (Qty 14) 237, 238, 239, 273, 274, 638, , 644, 645, 654, 655, 658, 849, 851.
1.6.10.2.6. Replace existing Switch Poles with new Class 1, 55-ft Western Red Cedar Poles (Qty 7) 208, , 665, 671, 844, 856, 858.
1.6.10.2.7. Any existing pole-mounted transformers on Utility Poles identified for replacement shall be removed from the existing Pole and re-installed on the new Utility Pole.
1.6.10.2.8. All new Poles shall be aligned and plumbed to 0 degrees to ensure they are completely vertical.
1.6.10.2.9. Replace all hardware on Switch Poles. New Air Brake Switches shall be all steel. All existing Air Brake Switches shall be returned to the Government.
1.6.10.2.10. Install two 600-AMP Disconnects on Poles and 652 (Qty 2).
1.6.10.2.11. Provide 10 additional poles (55’ Qty 2 and 45’ Qty 8), Cross arms, (Qty 30) 18 KV lightning arrestors to be replaced, as needed, based on field conditions found during construction. Price shall include demo of identified exiting poles and installation of new pole and associated components. Any additional poles and components that are not installed shall be provided to the Government at the completion of construction.
1.6.10.2.12. Replace all existing cross arms, side arms, insulators, support wires, fuses, fuse holders, and line switches. Cross arms shall be Type 4 Class 2 Brooks or Pennington Penta treated. For replaced poles, replace existing riser’s fuses with new, fused load break cutouts, 18kv LA’s, aluminum 3phase cutout mounting bracket, aluminum 3phase mounting bracket for LA’s and cable terms
1.6.10.2.13. Lines switches to be ground operated, gang operated switches rated for new 4/0 conductor current.
Other similar switches on the circuit are rated for 600A; any new switches should match existing. Include 10’ long 4/0 Ground Rod installed at base of each switch, with 6” extending above ground,
1.6.10.2.14. Remove and reinstall riser conductors.
1.6.10.2.15. All installations require Government inspection prior to energizing.
1.6.10.2.16. All work shall be carefully coordinated with the Government Project Manager. Electrical shutdowns shall be kept to a minimum to ensure affected facilities return to operation with minimum impact. All power outages will be conducted per 01010 section 2.2 “Utility Outages, Road Closures, and Digging Permits”.
1.6.10.2.17. Contractor shall be responsible for supplying a full and complete report for all work completed as part of this SOW. Report shall include electrical narrative details and identify electrical components with detailed photographic log detailing before and after conditions.
1.6.10.2.18. Provide and install all new conductor and conduit as necessary from new switches to existing electrical distribution. Provide wiring, connection, and all accessories.
1.6.10.2.19. All new installed components shall comply with Davis-Monthan AFB Design Compatibility Guidelines, and all applicable DoD, Federal, State, and local codes and standards.
1.6.10.2.20. Contractor will provide submittal on all items (include all electrical design details) in this RFP for Government approval.
1.6.10.2.21. Labels for New poles to be Aluminum embossed 3" Labels with Black Numbers on Yellow background, mounted in aluminum tag holder 6’ above ground. Numbering to include circuit and pole (example C2-655).
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-5
2. DESIGN SUBMITTAL REQUIREMENTS.
2.1. Standards, Documents, and Criteria. The design requirements within Section 01011 represent the minimum quality and quantity acceptable for the proposals and project submittals. The standards, documents, and criteria referenced within this RFP, although not all attached to or included in this RFP document shall be the most current version. Contractor shall be responsible for obtaining any documents not attached to or included in this RFP but referenced as criteria for the project. Requirements of this RFP may add to, delete, modify, revise, or substitute to the extent indicated for criteria contained in the referenced standards and documents; and this section shall be deemed the governing authority of any changes to the other-referenced standards, documents, and criteria.
2.2. Design Standards. Equipment, hardware, and materials shall be standard manufactured items unless otherwise specified. Replacement parts shall be standard and readily available through commercial means.
Discontinued products will not be accepted unless approved by the Contracting Officer. The Davis-Monthan AFB Design Compatibility Guidelines, this RFP, base guide specifications (if available), and all applicable codes, laws, and guidance, whether included in this RFP or not, will govern all design and construction of this project and the Contractor shall include all code and base DCG requirements in his bid. The Contractor SHALL conform all design and construction work to the base DCG and shall assume that no waivers to the stipulations included therein shall be granted.
2.3. Design Units. This project shall be designed in English inch-pound (I-P) units.
2.4. Reference Drawings Disclaimer. Drawings which may be provided as a part of this RFP are provided for reference only and only provide information for the Contractor’s use and incorporation into the design. Any drawings so provided shall not be considered complete and approved concept plans for this project. These drawings may be provided to give information on the types of renovations that are required to be included in the design and construction for the project and shall be used in the design of the facility to the extent necessary to construct a complete and usable facility. These drawings may include, but are not limited to, information addressing renovation of interior spaces; installation of an exterior, split-face concrete masonry wainscot; replacement of exterior windows and doors;
installation of a standing-seam metal roof (including substructure required); replacement/installation of mechanical, plumbing and fire protection; and electrical (interior, distribution, exterior, communications, local area networks, fire detection, etc.) systems. It is the Contractor’s responsibility to ensure the finished construction meets all of the requirements of this RFP. Drawings which may be provided as a part of this RFP may be available in electronic file format (AutoCAD).
2.4.1. Design Examples, References, and Preliminary Design Drawings. Design drawings and examples provided by the Government are for reference only and shall not be considered completed and approved concept plans for this project. Additional coordination of the design, in conjunction with the specific inputs from the Customer and base personnel during the required Design Charette, will be required to develop the approved concept plan and design development through the creation of construction documents, and construction (reference Part 5, ARCHITECTURAL DESIGN of this RFP - Not used).
2.4.2. The contractor is responsible during the project verify the existing conditions at the site.
2.5. Investigation Report. The Contractor is responsible for the following as part of the project Investigation Report:
2.5.1. The following investigative services shall be included, if applicable to the project:
• Investigation services shall include a plan check by the Contractor’s consultants of existing “as-built” drawing files, as applicable. Copies of requested as-built drawings may be furnished by the Government; however, it is the responsibility of the Contractor’s consultants to search the drawing files for applicable drawings. The Government does not guarantee the accuracy or completeness of any as-builts.
• In addition, as may be required by this RFP, the Contractor’s consultants will meet with the affected base agencies to gather information pertinent to this project.
• Investigation services for projects that affect existing facilities shall also include at least one field trip by the Contractor’s consultants to verify the existing conditions at the site.
2.6. Design Analysis. The Contractor is responsible for the following as part of the project Design Analysis:
2.6.1. The following computations must be included, if applicable to the project:
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-6
• Contractor shall provide electrical calculation limited Fuse sizing & wiring sizing.
2.6.2. The Contractor shall include, as a separate index in the Design Analysis at each submittal, the review comments received from the previous Air Force design reviews. Every review comment shall be annotated by the designer to indicate the disposition, i.e., whether the review comment is incorporated into the design documents; and, when incorporated, the location where the review comment is incorporated. If an exception to the incorporation of a review comment is proposed by the Contractor, he shall coordinate and resolve the exception with the base Project Manager; and, if the exception is approved, indicate same. If the exception is not approved, the designer shall annotate the disposition and the location of the review comment as described before.
2.7. Contract Drawings.
2.7.1. The Contractor shall provide a design and construction package that uses all design details given or referenced in this RFP and the base DCG. Additional details shall be created by the Contractor as required but shall conform to the requirements of this RFP and are subject to approval by Government. Base utility information, which may be provided for this RFP, is the best information available and may be provided to assist the Contractor during the design of this project. The Contractor is solely responsible for field verifying all information given.
2.7.2. The Contract Drawings shall be prepared entirely in accordance with the base DCG and shall clearly define all required work for this project. Drawings shall be prepared at a scale and level of all details appropriate to the subject, in accordance with accepted professional practice.
2.7.3. The Air Force may furnish a sheet border which includes the project information, which shall be attached to each sheet as an “XREF” object. The Air Force may, upon request, furnish the designer with the base-standard cover sheet and the base-standard short title block sheet, for use in this project.
2.7.4. The Contractor shall complete the entirety of the blank areas or spaces in the title blocks of all drawing sheets, including but not limited to, the correct FBNV number (no dashes) and the correct project title.
2.7.5. Site Layout. The project site shall be oriented with north being either at the top of the sheet or to the left of the sheet. All contract documents and drawings will reflect these cardinal directions for the sake of consistency and uniformity.
2.8. Contract Specifications.
2.8.1. The Contractor shall provide a design and construction package which includes project specifications based on the Unified Facilities Guide Specifications (UFGS) which can be obtained from the Whloe Building Design Guide website (www.wbdg.org).
2.8.2 The Contractor will edit each applicable UFGS section as appropriate to the project, and submit the edited specifications with each design submittal for the review and approval of the Government. Any portion of the specification sections proposed by the Contractor to be removed or omitted for this project shall be indicated by a strikethrough of the text, but leaving the text in the document until the 100% final document submittal. Any text proposed to be added to the specification sections by the Contractor shall be indicated by underlining the text.
2.8.3. Specifications shall include the Davis-Monthan AFB standard sections, "Section 01010, Statement of Objectives," and “Section 01011, Design Requirements” as provided with this RFP.
2.8.4. The Contract Specifications shall clearly define the type, quality, or other criteria relevant to all required work for this project. Specifications shall be prepared in the Construction Standards Institute (CSI) format, at a level of detail appropriate to the subject, in accordance with accepted professional practice.
2.8.5. To encourage competition, the Air Force prefers generic, quality-based or performance-based specifications.
For other than sole-sourced items identified by the Air Force (see Section 1.4.3), comply with the following instructions:
• To specify by manufacturer's name or catalog number, include at least three manufacturers whose products are essentially equal in quality, function, and cost; and then add the statement "or approved equal." If less than three manufacturers are known, specify the known information as a minimum standard of quality, type, color, etc.; and add the statement "or approved equal."
http://www.wbdg.org/
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-7
• To specify a single manufacturer and not allow submittal of proposed "equals," provide a brief written statement to the Air Force, separate from the specification, explaining the need for a single, specific product.
2.8.6. If tests are necessary, the specifications shall define the required criteria, number and type of tests to be made, and licensing or certifying requirements of the testing agency. All necessary testing shall be included in the contract specifications and shall be specified as being performed by and paid for by the construction Contractor. All new overhead will be visual inspect to prevent loose connections or inadvertent grounds. Provide a complete detailed report (include specific narrative) and results in writing.
2.9. Construction Cost Estimate.
2.9.1. The AF Form 3052, Construction Cost Estimate, shall cover all materials, labor, equipment, and direct costs required for construction of the project as designed, six months after design completion. The Air Force may furnish the designer with a sample cost estimate template.
2.9.2. For completed construction cost estimates, mark “FOR OFFICIAL USE ONLY” and the page number at the bottom of each estimate page.
2.9.3. On the first page, provide the summary information, date and signature as required by the template which may be furnished. The Air Force prefers the use of 15% overhead, 10% profit, 2% bond and 3.25% (5% of 65%) tax planning factors, cumulatively applied in accordance with the template which may be furnished.
2.9.4. The Air Force discourages the use of contingency factors. Prepare the Construction Cost Estimate in line item format broken out by CSI Division with sub-catatogires as appropriate with separate material and labor costs with sufficient detail to provide accurate figures.
2.9.5. If the Construction Cost Estimate exceeds the Air Force’s estimated construction cost in this RFP, the designer shall, without additional fee:
• Reduce estimated project costs by identifying less costly materials, techniques, or design features. The project design must still provide a fully complete and usable facility.
• Provide a list of additive bid items, the inclusion of which would bring the project back up to the original project funding limitation. The basic project design must still provide a fully complete and usable facility in the event that any or all of the additive bid items are not included in the project.
• Cost estimates for additive bid options, if any, must be identified as such and compiled separately from, but in the same format as, the Construction Cost Estimate.
2.9.6. If a complete and usable facility cannot be provided within the project funding limitation, notify the base Project Manager through the Contract Administrator in writing immediately. The Air Force shall either arrange additional funds, reduce the scope, or cancel the project.
• If additional funds are arranged or if the project scope is reduced, the base Project Manager will notify the designer in writing through the Contract Administrator. The Air Force will not renegotiate the designer's contract unless a major change in scope is necessary.
• If the project is canceled, the base Project Manager will notify the designer in writing through the Contract Administrator. The Air Force will pay the designer for all services provided on the project prior to receipt of such notification.
2.9.7. For this project, the Contractor shall separately identify categories of work including but not limited to new construction, maintenance, and repair. The Contractor shall prepare the Construction Cost Estimate to enable each category of work to be bid separately. See Section 1.6.1.
Contractor shall verify prior to start of work and shall consider all costs prior to submitting a bid. Submitt to Contracting Squadron the breakdown by each electrical items cost include all electrical components (include all areas adjacent to each existing poles) and with specific picture/photo/drawing (as part of the field investigation report with all electrical narrative in details). All documents shall be legible and can be read.
2.10. Schedule of Material Submittals.
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-8
2.10.1. An AF Form 66, Schedule of Material Submittals, has been provided by the Government with this RFP. This furnished Schedule of Material Submittals (Form 66) identifies submittal items that shall be provided by the Contractor in accordance with Section 01010 and 01011 requirements for government review and approval.
2.10.2. During the course of design and specification development, the Contractor shall append the Form 66 to include submittal items as required by the project specification sections. The Government has provided the Form 66 in Microsoft Excel format for this purpose. The appended Form 66 generated during the design shall be submitted with the Contractor’s edited specifications for government review and approval. The Form 66 must identify all items required to be submitted by the construction contractor for government review and approval prior to installation.
Submittals may include, but shall not be limited to, certificates of compliance, shop drawings, samples, color selections, or other items called for in the contract specifications.
2.10.3. The approved Form 66 will become the scheduling document for material submittals and will be used to manage submittals by all parties throughout the life of the contract.
2.10.4. During construction, it may be discovered that this list was not all-inclusive and that additional submittals may be required from and shall be submitted by the Contractor, as directed by the Contracting Officer.
2.10.5. For more information, see paragraph 1.4, Submittal Procedures, of Section 01010, “Summary of Work”.
2.11. Color Boards. Not Used
2.12. Design Submittal Package Requirements. The Contractor shall submit to the Government the following copies of the contract drawings, specifications, and other contract documents at each design stage.
2.12.1. 65% Design Submittal.
• 2 copies of full-size drawings and 1 copy of half-size drawings.
• 1 copy of Contractor final specifications.
• 1 copies of the AF Form 3000, Material Approval Submittal (to include cut sheets and substantiating information) of major equipment items of items with long lead times (See Section 1.5). The Contracting Officer may provide copies of the AF Form 3000 with applicable instructions for completion and submission.
• 1 copies of the AF Form 66, Schedule of Material Submittals, reflecting the above submittals.
• 1 PDF copy of all documents and PDF and AutoCAD copies of all drawings.
2.12.2. 95% Design Submittal
• 2 copies of full-size drawings and 1 copy of half-size drawings.
• 1 copy of Contractor final specifications.
• 1 copies of the AF Form 3000, Material Approval Submittal (to include cut sheets and substantiating information) of major equipment items of items with long lead times (See Section 1.5). The Contracting Officer may provide copies of the AF Form 3000 with applicable instructions for completion and submission.
• 1 copies of the AF Form 66, Schedule of Material Submittals, reflecting the above submittals.
• 1 PDF copy of all documents and PDF and AutoCAD copies of all drawings.
2.12.3. 100% Design Submittal (Design suitable for construction).
• 2 copies of full-size drawings and 1 copy of half-size drawings.
• 1 copy of Contractor final specifications.
• 1 copies of the AF Form 3000, Material Approval Submittal (to include cut sheets and substantiating information) of major equipment items of items with long lead times (See Section 1.5). The Contracting Officer may provide copies of the AF Form 3000 with applicable instructions for completion and submission.
• 1 copies of the AF Form 66, Schedule of Material Submittals, reflecting the above submittals.
• 1 PDF copy of all documents and PDF and AutoCAD copies of all drawings.
2.13. Codes. The design, materials, equipment, and installation shall be in accordance with, but not limited to, the requirements of the Davis-Monthan AFB Design Compatibility Guidelines, this RFP, base guide specifications (if available), and all applicable codes, laws, and guidance, whether included in this RFP or not; and with the listed codes, guides, and manuals. All references shall be assumed to be the most recent revision unless specifically noted otherwise. Although the references have been listed by engineering discipline for ease of citation, this does not
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-9 preclude their requirement to be used for work within any other discipline. When there is a conflict between any listed code, guide or reference, the most stringent requirements shall apply.
2.13.1. Electrical References.
• ACC Architectural and Interior Design Standards.
• The Davis-Monthan Air Force Base Design Compatibility Guidelines (base DCG), latest edition.
• Tucson/Pima County Outdoor Lighting Code, 1993 Edition.
• AFI 32-1063, Electric Power Systems.
• AFI 32-1065, Grounding Systems
• AFMAN 88-9, Chapter 1, Electric Power Supply and Distribution.
• AFMAN 88-9, Chapter 2, Interior Electrical System Design.
• ANSI A17.1, Safety Code for Elevators and Escalators,
• ANSI A117.1, Buildings and Facilities - Providing Accessibility and Usability for Physically Handicapped
People.
• ANSI C2, National Electrical Safety Code.
• ANSI C57.12.00, General Requirements for Liquid-Immersed Distribution, Power, and Regulating
Transformers.
• ANSI C57.12.26, Requirements for Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase
Distribution Transformers for Use with Separable Insulated High-Voltage Connectors, High-Voltage, 34500GrdY/19920 Volts and Below; 2500 kVA and Smaller.
• ANSI C57.12.27, Conformance Requirements for Liquid-Filled Distribution Transformers Used in Pad-Mounted Installations, Including Unit Substations.
• ANSI C57.12.28, Switchgear and Transformers - Pad-Mounted Equipment - Enclosure Integrity.
• ANSI C84.1, Electric Power Systems and Equipment - Voltage Ratings.
• ANSI/The Institute of Electrical and Electronics Engineers (IEEE) Standard 141, Recommended Practice for
Electric Power Distribution for Industrial Plants (The Red Book).
• ANSI/IEEE Standard 142, Recommended Practice for Grounding of Industrial and Commercial Power
Systems (The Green Book).
• ANSI/IEEE Standard 242, Recommended Practice for Protection and Coordination of Industrial and
Commercial Power Systems (The Buff Book).
• Telecommunications Industry Association (TIA) Electronic Industries Alliance (EIA) 568, Commercial Building
Telecommunications Wiring Standard.
• EIA 569, Commercial Building Standard for Telecommunications Pathways and Spaces.
• EIA 607, Grounding and Bonding Requirements for the Telecommunications Infrastructure of Commercial
Buildings.
• ETL 91-5, Fire Protection Engineering Criteria Emergency Lighting and Marking of Exits.
• IEEE C62.41, Surge Voltage in Low-Voltage AC Power Circuits.
• Illuminating Engineering Society (IES), Lighting Handbook, Reference and Application.
• MIL HNDBK 419A, Chapter 1, Facility Grounding System.
• MIL HNDBK 1190, applicable ETL’s/CTL’s.
• NFPA 70, National Electrical Code (NEC).
• NFPA 72, National Fire Alarm Code.
• NFPA 75, Electronic Computer/Data Processing Equipment.
• NFPA 90A, Air Conditioning and Ventilating Systems.
• NFPA 101, Code for Safety to Life from Fire in Buildings and Structures.
• NFPA 780, Standard for the Installation of Lightning Protection Systems.
• UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings, latest edition.
• UFC 4-021-01, Mass Notification Systems.
• Underwriters Laboratories (UL) 268, Smoke Detectors for Fire Protective Signaling Systems.
3. CIVIL DESIGN. Not Used
4. ELECTRICAL DESIGN. In general, the following paragraphs are intended to assist and inform the Contractor of the general architectural criteria controlling base designs. Use the following paragraphs as needed.
FBNV 240027, Overhead Electrical Sustainment, Phase 1 10 September 2024 Solicitation packages (Rev 6.0)
01011-10
4.1 General Requirements.
4.1.1. General Requirements. The Contractor shall visit the site to verify all electrical site conditions and shall consider all existing site conditions in all proposal, design, and construction efforts. The Contractor shall become familiar with all electrical requirements of this project prior to bidding. The Contractor shall demolish and remove off-base all existing materials and objects which conflict with the new/repaired construction; and shall provide all labor and materials and equipment to provide a new/repaired facility.
4.1.2. General Scope. The Contractor shall design and provide replacement systems for all electrical systems and utilities, including but not limited to telephone/data, for this project. The Contractor shall coordinate with the local CATV company, local telephone company, and the Davis-Monthan AFB electric shop to demolish and remove the existing overhead CATV, street lighting, telephone/communication, and existing related power-apparatus equipment, and devices, etc., in this project site; and install new OH, CATV, power, telephone/communication, as required in this
RFP.
4.1.3. Commercial Codes and Design Manuals. All design and installation work shall conform to the latest editions of the references listed in Section 2.13.8, unless otherwise indicated herein.
4.1.4. NEC Covered vs. Non-Covered. All electrical systems and equipment, both interior and exterior, installed under this project shall, for the purposes of NEC application and compliance, be considered as "Covered" and shall be installed per the requirements given in the NEC. None of the systems or equipment installed shall be considered as "electric utility" systems or equipment. However, the power cables going from the exterior transformers to the buildings shall be considered as the "service" or as "service conductors" and shall be installed per the requirements given below and in accordance with NEC applicable articles.
4.1.5. Coordination. Electrical work shall be coordinated through the Contracting Officer. The order of construction shall be as directed under "phasing", in other parts of this RFP.
4.1.6. Digging Permits. Digging permits shall be obtained in accordance with the procedures outlined in paragraph 2.2c., Utility Outages, Road Closures, and Digging Permits –“Base Outages and Digging Permits (AF Form 103, BCE Work Clearance Request)” of Section 01010, Summary of Work.
4.1.7. Specifications. Specifications shall be provided as part of the contract documents for this project.
Attachments:
Atch 1: Electrical Map Final v2.
End of Section 01011