- FBNV 071475 – Repair Building 136
- Solicitation number
- FA487720R0018
About this file
This document provides details for a federal solicitation seeking design and construction services. The Department of the Air Force Air Combat Command is soliciting proposals for a firm fixed price contract to perform repair work at Building 136 located at Davis-Monthan Air Force Base in Tucson, Arizona. The work includes modification of the hangar door to accommodate a new aircraft as well as HVAC, electrical, and fire protection upgrades. The NAICS code for this opportunity is 238220 and the magnitude of work is between $1 million to $5 million. This procurement is set aside for competitive award to a certified HUBZone small business. The performance period is 210 calendar days and proposals are due based on the instructions and evaluation criteria provided in the solicitation. Interested firms must demonstrate bonding capacity up to the maximum project value. The primary point of contact for any questions is the listed contracting specialist with the alternate being the contracting officer, both with the 355th Contracting Squadron at Davis-Monthan Air Force Base.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Davis-Monthan Air Force Base, Arizona FBNV 071475, Repair Hangar, Fac 136 12 June 2020
01011-1
SECTION 01011 - DESIGN REQUIREMENTS
NOTE: The Davis-Monthan Air Force Base Design Compatibility Guideline (DCG) requirements and those defined in the following sections may directly affect the Contractor’s overhead for completing the scope of work. Failure on the part of the Contractor to adequately review this section and identify/clarify any requirements herein will not constitute justification of Contractor claims for additional Design costs.
1. PROJECT DESCRIPTION.
1.1. General. The Contractor shall perform all design and
construction services for project, Repair hangar 136 to accommodate EC-37B. Work will include hangar door modification to accommodate the unique tail configuration of the new aircraft, minimum fire protection compliance upgrade, and HVAC upgrade as well as any necessary work associated to the upgrade (i.e. Electrical) and bring the facility into compliance with current standards. All work shall comply with the current Base Design Compatibility Guidelines (DCG), and bring all facility systems up to current codes.
1.2. Location. The project site is located on southeast of
the intersection of Herky and Jammer Streets, Davis- Monthan Air Force Base (Tucson), Arizona. The base-approved Location and Site Plans may be made available to the Contractor upon request.
1.3. Project Programming. Government programming
requirements, classification of work, project approval levels, and funding appropriation have defined the requirement for execution of this project. The Contractor shall work the project as a whole. The Contractor shall maintain documentation to include, but not limited to, progress reports, requests for payment, change orders, modifications, and any other contractual (cost) documents for each project’s scope of the total project. All design and engineering costs shall be incorporated into this project.
1.4 Standards, Documents and Criteria. The design requirements within Section 01011 represent the minimum quality and quantity acceptable for the proposals and project submittals. The standards, documents, and criteria referenced within this RFP, although not all attached to or included in this RFP document shall be the most current version. Contractor shall be responsible for obtaining any documents not attached to or included in this RFP but referenced as criteria for the project. Requirements of this RFP may add to, delete, modify, revise, or substitute to the extent indicated for criteria contained in the referenced standards and documents; and this section shall be deemed the governing authority of any changes to the other-referenced standards, documents and criteria.
1.4.1. Sustainable principles, to include Life Cycle cost-effective practices, will be integrated into the design, development, and construction of the project in accordance with UFC 1‐200‐02. This includes preparation of a life‐ cycle cost analysis for energy consuming systems, renewable energy generating systems, whenever life‐cycle cost effective is selected as the reason any requirement of UFC 1‐200‐02 is partially compliant or not applicable. This project will comply with DoD Antiterrorism/Force Protection requirements per UFC 4‐010‐01.
1.4.2. The site and common public spaces shall be fully accessible to physically disabled persons and shall conform to the Americans with Disabilities Act (ADA) and Architectural Barriers Act (ABA) Accessibility Guidelines for Buildings and Facilities.
1.5 Design Standards. Equipment, hardware, and materials shall be standard manufactured items unless otherwise specified. Replacement parts shall be standard and readily available through commercial means.
Discontinued products will not be accepted unless approved by the Contracting Officer.
FACILITY 136
01011-2
FBNV 071475, Repair Hangar, Fac 136 12 June 2020
1.5.1. Equipment, materials, assemblies, spare parts, meters, monitors, controls, and any other articles of construction that are required to communicate with, connect to, operate with, or supplement existing base systems shall be 100% compatible in installation, configuration (including software), maintenance, repair, and operation or the item will not be considered equal and will be disapproved by the Government.
1.5.2. Brand Name References: The following is a list of highlighted brand name requirements from the base DCG.
This list should not be considered complete. All “Or Equal” material submittals shall be 100% compatible or the Government they will disapprove it.
Intrusion Detection Systems - Vindicator. Fire Detection/Prevention Panels – Monaco.
Door Hardware & Lock Sets – Best (See individual parts list in base DCG).
Electrical Metering Equipment – Ion.
Direct Digital Controls – Staefa.
1.6. Codes. The design, materials, equipment, and installation shall be in accordance with the requirements of the listed codes and design manuals, with the requirements of this section, and with the listed specifications. All references shall be assumed the most recent revision unless specifically noted otherwise. Although the references have been listed by engineering discipline for ease of citation, this does not preclude their requirement to be used for work within any other discipline. When there is a conflict between any listed code, guide or reference, the most stringent requirements shall apply.
1.6.1. Architectural References.
Air Combat Command (ACC) Architectural and Interior Design Standards.
Air Force Handbook (AFH) 32-1084, Civil Engineering Facility Requirements.
AFI 32-7063, Air Installation Compatible Use Zone Program.
American National Standards Institute (ANSI/CABO) A117.1, Americans with Disabilities Act (ADA)
Accessibility Guidelines for Buildings and Facilities.
Federal Architectural Barriers Act (ABA).
Gypsum Association Fire Resistance Design Manual.
NFPA 10, Portable Fire Extinguishers.
NFPA 80, Fire Doors and Fire Windows.
NFPA 80A, Protection from Exterior Fire Exposure.
NFPA 101, Life Safety Code.
NFPA 203, Roof Coverings/Roof Deck.
NFPA 220, Types of Building, Construction.
NFPA 231, General Storage.
Tile Council of America Handbook for Ceramic Tile Installation.
HQ AF/A1SA directed UFC 1-200-01, General Building Requirements.
UFC 3-120-01, Air Force Sign Standard, to include ACC Instruction 32-1054, Exterior Signs.
UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings.
UFC 3-600-01, Fire Protection Engineering for Facilities.
Intrusion Detection Systems--DCID 6-9, AFI31-401.
Information Security Program--DoD 5200.01-V3.
1.6.2. Structural References.
American Institute of Steel Construction (AISC) M018L, Load and Resistance Factor Design (LRFD) Manual of Steel Construction, Volume 1: Structural Members
AISC-M019L, Load and Resistance Factor Design Specification, Volume II: Connections.
ACI 318/318M-99, Building Code Requirements for Structural Concrete.
ACI 531-95, Building Code Requirements for Concrete Masonry Structures.
01011-3
American Welding Society (AWS) D1.1, Welding Handbook.
American Society of Civil Engineers (ASCE) 7, Minimum Design Loads for Buildings and Other Structures.
American Iron and Steel Institute (AISI) SG-930, Cold-Formed Steel Design Manuals.
Pre-stressed Concrete Institute (PCI) Manuals for Precast and Pre-stressed Concrete.
PCI Manual 116, Manual for Quality Control for Plants and Production of Precast and Pre-stressed Concrete
Products.
PCI Manual 117, Manual for Quality Control for Plants and Production of Architectural Precast Concrete
Products.
PCI Manual 122, Manual For Architectural Precast Concrete.
PCI Manual 126, Manual for the Design of Hollow Core Slabs.
Steel Deck Institute (SDI) Diaphragm Design Manual.
Steel Joist Institute (SJI) Standard Specifications and Load Tables for Open Web Joists.
1.6.3. Mechanical References.
Engineering Technical Letter (ETL) 88-1, Standard Guidelines for Submission of Facility Operating and Maintenance Manuals.
ETL 88-2, Reliability and Maintainability (R&M) Design Checklist.
ETL 88-8, Chlorofluorocarbon (CFC) Limitation in Heating, Ventilating and Air-Conditioning (HVAC) Systems.
ETL 90-10, Commissioning of HVAC Systems Guide Specification.
American Society of Heating, Refrigerating and Air Conditioning Engineers (ASHRAE), Fundamentals
Handbook.
ASHRAE HVAC Systems and Equipment Handbook.
ASHRAE HVAC Applications Handbook.
ASHRAE Standard 62.1, Ventilation for Acceptable Indoor Air Quality.
ASHRAE Standard 70, Method of Testing the Performance of Air Outlets and Air.
ASHRAE Standard 90.1, Energy Standard for Buildings Except Low-Rise Residential Buildings.
American Conference of Governmental Industrial Hygienists (ACGIH).
MIL HDBK 1190, Facility Design and Construction.
NFPA 90A, Installation of Air Conditioning and Ventilating Systems.
UFC 3-400-01, Energy Conservation UFC 3-400-02, Engineering Weather Data.
UFC 3-410-01FA, Heating, Ventilating, and Air Conditioning.
United States Energy Policy Act of 2005.
1.6.4. Plumbing References.
ANSI B16.3, Malleable Iron Threaded Fittings, Classes 150 and 300.
ANSI Z358.1, Emergency Eyewash and Shower Equipment.
American Society of Mechanical Engineers (ASME) A112.19.1M, Enameled Cast Iron Plumbing Fixtures.
ASME A112.19.2, Ceramic Plumbing Fixtures.
ASME A112.19.3, Stainless Steel Plumbing Fixtures (Designed for Residential Use).
NFPA 54, National Fuel Gas Code.
Plumbing And Drainage Institute (PDI) WH 201, Water Hammer Arresters.
UFC 3-420-01, Plumbing Systems.
1.6.5. Fire Suppression References.
NFPA 13, Standard for the Installation of Sprinkler Systems.
NFPA 24, Installation of Private Fire Service Mains.
NFPA 90A, Installation of Air Conditioning and Ventilating Systems.
NFPA 72, National Fire Alarm Code.
NFPA 101, Life Safety Code.
01011-4
UFC 3-600-01, Fire Protection Engineering for Facilities.
ETL 01-18 Fire Protection Engineering Criteria-Electronic Equipment Installation.
1.6.6. Electrical References.
ACC Architectural and Interior Design Standards.
The Davis-Monthan Air Force Base Design Compatibility Guidelines (base DCG), latest edition.
Tucson/Pima County Outdoor Lighting Code, 1993 Edition.
AFI 32-1063, Electric Power Systems.
AFI 32-1065, Grounding Systems AFMAN 88-9, Chapter 1, Electric Power Supply and Distribution.
AFMAN 88-9, Chapter 2, Interior Electrical System Design.
ANSI A17.1, Safety Code for Elevators and Escalators, ANSI A117.1, Buildings and Facilities - Providing Accessibility and Usability for Physically Handicapped
People.
ANSI C2, National Electrical Safety Code.
ANSI C57.12.00, General Requirements for Liquid-Immersed Distribution, Power, and Regulating
Transformers.
ANSI C57.12.26, Requirements for Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase
Distribution Transformers for Use with Separable Insulated High-Voltage Connectors, High-Voltage, 34500GrdY/19920 Volts and Below; 2500 kVA and Smaller.
ANSI C57.12.27, Conformance Requirements for Liquid-Filled Distribution Transformers Used in Pad- Mounted Installations, Including Unit Substations.
ANSI C57.12.28, Switchgear and Transformers - Pad-Mounted Equipment - Enclosure Integrity.
ANSI C84.1, Electric Power Systems and Equipment - Voltage Ratings.
ANSI/The Institute of Electrical and Electronics Engineers (IEEE) Standard 141, Recommended Practice for
Electric Power Distribution for Industrial Plants (The Red Book).
ANSI/IEEE Standard 142, Recommended Practice for Grounding of Industrial and Commercial Power
Systems (The Green Book).
ANSI/IEEE Standard 242, Recommended Practice for Protection and Coordination of Industrial and
Commercial Power Systems (The Buff Book).
Telecommunications Industry Association (TIA) Electronic Industries Alliance (EIA) 568, Commercial Building
Telecommunications Wiring Standard.
EIA 569, Commercial Building Standard for Telecommunications Pathways and Spaces.
EIA 607, Grounding and Bonding Requirements for the Telecommunications Infrastructure of Commercial
Buildings.
ETL 91-5, Fire Protection Engineering Criteria Emergency Lighting and Marking of Exits.
IEEE C62.41, Surge Voltage in Low-Voltage AC Power Circuits.
Illuminating Engineering Society (IES), Lighting Handbook, Reference and Application.
MIL HNDBK 419A, Chapter 1, Facility Grounding System.
MIL HNDBK 1190, applicable ETL’s/CTL’s.
NFPA 70, National Electrical Code (NEC).
NFPA 72, National Fire Alarm Code.
NFPA 75, Electronic Computer/Data Processing Equipment.
NFPA 90A, Air Conditioning and Ventilating Systems.
NFPA 101, Code for Safety to Life from Fire in Buildings and Structures.
NFPA 780, Standard for the Installation of Lightning Protection Systems.
UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings, latest edition.
1.7 Field Information. The utility and as-built information provided by the government, is the best information available. It is provided to assist the Contractor during the design of this project. The Contractor is responsible for field verifying all information given. The Contractor is also responsible for obtaining all information necessary to properly design and install all work. Gathering information during design shall be coordinated through the Contracting Officer. Any survey required providing utility locations, manhole inverts, and verification of existing features shall be the responsibility of the Contractor and shall tie into the project datum.
1.8. Site Visits. The contractor shall make periodic visits to the project site during the investigative and design phases.
1.9. Design and Construction Schedule. The Contractor shall provide as part of their proposal preliminary design and construction completion schedules for the Government’s review and approval. The Government will evaluate Contractor-proposed calendar days based on the best interests of the project execution and the Government’s requirements. The performance period for the entire project may not exceed 179 calendar days. All days listed will be calendar days and include all Contractor actions such as design, construction, travel, mobilization, drawing and construction material submittal periods, etc. Contractor shall submit an AF Form 66, Schedule of Material Submittals. Contractor shall be given the construction NTP, at the Contracting Officer’s discretion, at the time of the 95% design approval to begin mobilization, site work, and demolition concurrently with the completion of the remainder of the design package.
1.9.1. Following contract award, the Contractor shall finalize their proposed design and construction completion schedules. The Contractor shall prepare the schedules using the AF Form 3064, Contract Progress Schedule. The Contractor shall submit for government review and approval the AF Form 3064 no later than ten (10) calendar days following issuance of the Notice to Proceed.
1.10. Permits. The Contractor is responsible for obtaining all necessary Federal, state, county, and local permits required to complete the construction of this project. The Contractor is responsible for paying all fees associated with obtaining the permits and performing all work as required within the permits at no extra cost to the Government.
1.11. Project Specific Design and Construction Requirements. The Contractor shall incorporate as part of their design and include in the construction the following requirements in accordance with all regulations, requirements, and standards identified in this RFP. The following requirements provide more detail than the generic descriptions provided in Section 1.1 of this RFP; and are the minimum requirements that ultimately satisfy the User’s needs and wants. The Contractor shall provide a complete and usable facility based around the User’s needs and wants, and constructed in accordance and in compliance with commercial and industry standards.
1.11.1. General Requirements.
1.11.1.1 Provide the Design and Construction to Repair Hangar 136 to accommodate the new EC-37B aircraft mission. The EC-37B will be replacing the EC-130 as the aerial platform for Compass Call operations. The first EC-37B is expected to arrive in FY21. This is the only facility on base that can house the EC-37B during the overlap of 4 years of interim operation. The height of the existing hangar door cannot accommodate the unique tail configuration of the EC-37B. The main door opening currently has a height of 24 ft; the EC-37B has a tail height of 27 ft, 4 in. Although the building does have a 40 ft high tail slot, it is not wide enough for the EC-37B to utilize because of the aircraft’s “T-Tail” configuration. The required height and width of the buildings hangar door opening shall be determined by the Contractor’s/Design Team during the design process and in accordance with clear distances indicated by the UFC requirements for hangars/doors-Refer to the attached EC-37B General Dimensions Document for further information.
1.11.1.2. All construction work shall be accomplished between the hours of 0630—1700, Monday through Friday, unless otherwise approved in writing by the Contracting Officer (CO.
1.11.1.3. Davis Monthan AFB is a controlled area and will require the Contractor and subcontractors to have the required badging and identification to access the base. The Contractor shall consider in their proposal the reasonable costs and effects of daily, short delays in accessing the project sites, as required by the restrictive access requirements or by local alert conditions. Government will not provide escorts for base access.
01011-5
The Contractor's access/haul route shall be exclusively through the Swan Gate at the northwest entrance of the Base. Hauling or receiving materials through other gates shall not be permitted.
1.11.1.4. This project will require fenced screening around the construction site. A temporary fence shall be provided by the Contractor in accordance with paragraph 2.9, Fenced Storage Yard of Section 01010, The requested size of the Contractor's storage and staging area shall be proposed as part of the design.
1.11.1.5. Unless noted otherwise, it is assumed that the capacity of the existing building electrical service will be sufficient to accommodate the requirements of this project. However, it shall be the Contractor’s responsibility to determine the adequacy of the electrical service and in the case that the service is not adequate, submit a written report within 30 days of Project Design Start (Notice to Proceed) indicating the deficiency, along with the recommended size/capacity required to the Contracting Officer.
1.11.1.6. Field Information. Base utility information, which may be provided for this RFP, is the best information available and may be provided to assist the Contractor during the design of this project. The Contractor is solely responsible for field verifying all information given. The Contractor is also responsible for obtaining all information necessary to properly design and construct the project. Information gathering during the design shall be coordinated through the Contracting Officer. Any field surveying required to identify/verify utility locations, manhole inverts, existing grades and features, etc., shall be the responsibility of the Contractor and shall be tied into the base-surveying datum.
1.11.1.7. The contractor shall verify the presence or absence of asbestos-containing materials (ACM) by conducting an asbestos study of the facility. Contractor conducted tests shall be facility-wide and shall be comprehensive for the purposes of determining information applicable to, necessary for and pertinent to both the investigation and design services of this project. For example, particular care shall be exercised to test the composite of all existing construction materials, such as carpet/adhesive over one or more layers of resilient tile/adhesive, which may be found in the existing floor finishes. Include the resultant report and recommendations in the Investigation Report.
Additionally, forward one (1) copy of the final approved report and recommendations to the base Project Manager and 355 CES Environmental Element (355 CES/CEIE). Any required abatement identified from this report shall be addressed as a contract modification at the government’s discretion.
1.11.1.8. The contractor shall verify the presence or absence of lead-based paint or other lead-containing coating.
Design for and conduct lead-based paint and/or lead-containing coating removal in all construction areas found to contain such material. Contractor conducted tests shall be facility-wide and shall be comprehensive for the purposes of determining information applicable to, necessary for and pertinent to both the investigation and design services of this project. Include the resultant report and recommendations in the 100% Title 1-A Investigation Report. Additionally, forward one (1) copy of the final approved report and recommendations to the base Project Manager and 355 CES Environmental Element (355 CES/CEIE).
1.11.2. Demolition Requirements.
1.11.2.1. Demolition shall be accomplished as required per the design specifications indicated in this Section 01011.
1.11.2.2. Existing construction scheduled to be removed shall be inspected and evaluated for recycling or reuse.
Items determined suitable for recycling or reuse shall be separated, set aside, and stored or delivered to a collection point for reuse, remanufacture, recycling, or alternative disposal. Materials shall be designated for reuse on site whenever possible. Government reserves the right to salvage material not being reused.
1.11.2.3. Where removals leave holes and damaged surfaces exposed in the finished work, patch and repair these holes and damaged surfaces to match adjacent finished surfaces, using on-site materials when available. Where new work is to be applied to existing surfaces, perform removals and patching in a manner to produce surfaces suitable for receiving new work. Finished surfaces of patched area shall be flush with the adjacent existing surface and shall match the existing adjacent surface as closely as possible as to texture and finish.
1.11.3. Mechanical Requirements.
1.11.3.1. Replace/upgrade the two existing Air Handling Units (AHUs) serving the North and South wing- Administrative areas. The AHUs shall be replaced "like for like" and include all associated appurtenances.
1.11.3.2. Remove and replace the existing ductwork with new ducting with the SMACNA Class A seal throughout the facility to include diffusers and air valves, in accordance with ASHRAE 90.1, UFC 3-410-01, and the
D-M DCG.
01011-6
1.11.3.3. Replace and upgrade existing Carrier-Water Cooled Direct Expansion (Model 50BA024640, Serial X294356).
1.11.3.4. Design/Install two (2) new replacement Computer Room Air Conditioning Units and associated condenser/piping (See attached Drawing 1) in accordance with ASHRAE 90.1, UFC 3- 410-01, and base DCG. System shall be capable of maintaining the temperature at 75 degrees Fahrenheit +/- 3 degrees and approximately 50% or less relative humidity.
1.11.3.5. Provide heating and Cooling (Evaporative Cooling) to the existing hangar. Remove the existing Carrier units in the hangar bay (Heat only), and replaced/upgraded with new chiller and air handler(s) with hot/cold decks as necessary to heat and cool the hangar bay. The existing boiler serving the hangar bay units shall remain and be reused in the heating in the hangar bay. Provide AC load calculations for this new system in the hangar bay.
1.11.3.6. The contractor shall provide commissioning services for the HVAC system by an independent, third-party contractor specializing in system commissioning.
1.11.4. Fire Protection/Detection Requirements.
1.11.4.1. Upgrade the following in order to fix DoD Configuration Control:
1.11.4.2. Replace sprinkler heads (46). Provide wet sprinkler protection IAW the requirements of UFC 03-
600.01 and NFPA13.
1.11.4.3. Add pressure relief trim device above riser.
1.11.4.4. Add identification tags to valves (8).
1.11.4.5. Rearrange piping to pressurize bladder tank only when system activates.
1.11.4.6. The foam control panel is currently located in an unconditioned space (fire riser room off the hangar bay). Provide a mini-split unit to the fire riser room to provide a conditioned space for the panel.
1.11.4.7. Replace with stations having key reset (3). Replace newer model fire/MNS panel.
1.11.5. Electrical Requirements.
1.11.5.1. Incorporate any necessary electrical upgrade in order to support the HVAC AHU upgrade and Evaporative Cooling.
1.11.5.2. The design and construction of this project will incorporate applicable US Government and ACC high performance green building (HPGB) and Sustainable guidelines, objectives, requirements, and best practices established in Executive Order 13423, Public Laws, and Federal Regulations, addressing as a minimum: water use, energy use reduction (per EPAct 2005 and CFR Title 10 Part 433), building commissioning, materials selection, and indoor environmental quality.
1.11.5.3. The design and construction of this project, in particular, HVAC and electrical lighting, will meet Tucson Electric Rebate Program requirements. The power to the new hangar bay doors shall be provided before the facility connection to allow the Fire Dept. to open the hangar bay doors in an emergency and local facility power is cut.
2. DESIGN SUBMITTAL REQUIREMENTS.
2.0 DESIGN SUBMITTAL REQUIREMENTS.
2.1. Investigation Report. The Contractor is responsible for the following as part of the project Investigation Report:
2.1.1. The following investigative services shall be included, if applicable to the project:
2.1.1.1. Investigation services shall include a plan check by the Contractor’s consultants of existing “as-built” drawing files, as applicable. The Government may furnish copies of requested as-built drawings; however, it is the responsibility of the Contractor’s consultants to search the drawing files for applicable drawings. The Government does not guarantee the accuracy or completeness of any as-built.
01011-7
1380800043C Line
1380800043C Line
1380800043C Line
1380800043C Line
1380800043C Line
1380800043C Line
1380800043C Line
FBNV 071475, Repair Hangar, Fac 136 27 September 2019
2.1.1.2. In addition, as may be required by this RFP, the Contractor’s consultants will meet with the affected base agencies to gather information pertinent to this project.
2.1.1.3. Investigation services for projects that affect existing facilities shall also include at least one field trip by the Contractor’s consultants to verify the existing conditions at the site.
2.1.2. Items to be reported on include but are not limited to the applicable portions of the following paragraphs:
2.1.2.1. Existing interior and exterior physical conditions applicable to the project.
2.1.2.2. Accuracy and completeness of reference data furnished by the Government.
2.1.2.3. Architectural, communications, electrical, fire protection, mechanical, structural, utility, UFAS/ADA Accessibility Guidelines, International Building Code or other special system requirements.
2.1.2.4. Availability and adequacy of existing structure, utilities, or systems to support requirements identified above.
2.1.2.5. Special design problems or interferences with existing conditions, e.g., asbestos and/or lead-based coatings abatement, and proposed solutions or design options.
2.1.2.6. Problems anticipated with constructing the project within budget, and proposed solutions or options and the anticipated costs.
2.1.2.7. Report shall include conceptual or schematic drawings of proposed Site Plan.
2.2. Design Analysis. The Contractor is responsible for the following as part of the project Design Analysis:
2.2.1. The following computations must be included, if applicable to the project:
2.2.1.1. Utility loads.
2.2.1.2. Electrical loads and equipment sizing including fault current analysis and coordination studies for new buildings and major repairs.
2.2.1.3. Heating, ventilation, and air conditioning loads, calculated on both a room-by-room and block basis.
Proportioning the air on a square footage basis shall not be allowed. Loads must be calculated utilizing a software package specifically designed for that purpose.
2.2.1.4. Sizing of mechanical equipment, ducts, and piping.
2.2.2. The Contractor shall include, as a separate index in the Design Analysis at each submittal, the review comments received from the previous Air Force design reviews. The designer to indicate the disposition shall annotate every review comment, i.e., whether the review comment is incorporated into the design documents; and, when incorporated, the location where the review comment is incorporated. If the Contractor proposes an exception to the incorporation of a review comment, he shall coordinate and resolve the exception with the base Project Manager; and, if the exception is approved, indicate it. If the exception is not approved, the designer shall annotate the disposition and the location of the review comment as described before.
2.3. Contract Drawings.
2.3.1. The Contractor shall provide a design and construction package that uses the design details given or referenced in this RFP and the base DCG. Additional details shall be created by the Contractor as required, but shall conform to the requirements of this RFP and are subject to approval by Government.
2.3.2. The Contract Drawings shall be prepared entirely in accordance with the base DCG and shall clearly define all required work for this project. Drawings shall be prepared at a scale and level of detail appropriate to the subject, in accordance with accepted professional practice.
2.3.3. The Air Force may furnish a sheet border, which includes the project information, which shall be attached to each sheet as an “XREF” object. The Air Force may, upon request, furnish the designer with the base-standard cover
01011-8 sheet and the base-standard short title block sheet, for use in this project.
2.3.4. The Contractor shall complete the entirety of the blank areas or spaces in the title blocks of all drawing sheets, including but not limited to, the correct FBNV number (no dashes), the correct project title, and the correct drawing number 190020.
2.3.5. Site Layout. All contract documents and drawings will reflect north-south cardinal directions for the sake of consistency and uniformity.
2.3.6. This project shall be designed in English inch-pound (I-P) units.
2.4. Contract Specifications. The Contractor shall provide a design and construction package, which includes project specifications based on the Unified Facilities Guide Specifications (UFGS), which can be obtained from the Whole Building Design Guide website (www.wbdg.org). At a minimum, the Contractor will include the UFGS sections listed in the specifications table of contents provided by the Government with this RFP.
2.4.1 The Contractor will edit each applicable UFGS section as appropriate to the project, and submit the edited specifications with each design submittal for the review and approval of the Government. Any portion of the specification sections proposed by the Contractor to be removed or omitted for this project shall be indicated by a strikethrough of the text, but leaving the text in the document until the 100% final document submittal. Any text proposed to be added to the specification sections by the Contractor shall be indicated by underlining the text.
2.4.2. The edited specification sections shall be included for submittals with the Davis-Monthan AFB standard specifications title/cover page, table of contents, "Section 01010, Summary of Work" and “Section 01011, Design Requirements” (this section) provided by the Government with this RFP. The Contractor may edit the table of contents, but will not edit the title/cover page nor any portion of Sections 01010 or 01011.
2.4.3. The edited specification sections shall clearly define the type, quality, or other criteria relevant to all required work for this project. Specifications shall be prepared at a level of detail appropriate to the subject, in accordance with accepted professional practice.
2.4.4. To encourage competition, the Air Force prefers generic, quality-based or performance-based specifications.
For other than sole-sourced items identified by the Air Force (see Section 1.5.2), comply with the following instructions:
2.4.4.1. To specify by manufacturer's name or catalog number, include at least three manufacturers whose products are essentially equal in quality, function, and cost; and then add the statement "or approved equal." If less than three manufacturers are known, specify the known information as a minimum standard of quality, type, color, etc.; and add the statement "or approved equal."
2.4.4.2. To specify a single manufacturer and not allow submittal of proposed "equals," provide a brief written statement to the Air Force, separate from the specification, explaining the need for a single, specific product.
2.4.4.3. If tests are necessary, the specifications shall define the required criteria, number and type of tests to be made, and licensing or certifying requirements of the testing agency. All necessary testing shall be included in the contract specifications and shall be specified as being performed by and paid for by the construction Contractor.
2.5. Schedule of Material Submittals
2.5.1. An AF Form 66, Schedule of Material Submittals, has been provided by the Government with this RPF. This furnished Schedule of Material Submittals (Form 66) identifies submittal items that shall be provided by the Contractor in accordance with Section 01010 and 01011 requirements for government review and approval.
2.5.2. During the course of design and specification development, the Contractor shall append the Form 66 to include submittal items as required by the project specification sections. The Government has provided the Form 66 in Microsoft Excel format for this purpose. The appended Form 66 generated during the design shall be submitted with the Contractor’s edited specifications for government review and approval. The Form 66 must identify all items required to be submitted by the construction contractor for government review and approval prior to installation.
01011-9
01011-10
Submittals may include, but shall not be limited to, certificates of compliance, shop drawings, samples, color selections, or other items called for in the contract specifications
2.5.3. The approved AF Form 66, Schedule of Material Submittals, will become the scheduling document and will be used to control submittals throughout the life of the contract.
2.5.4 During construction, it may be discovered that this list was not all-inclusive and that additional submittals may be required from and shall be submitted by the Contractor, as directed by the Contracting Officer.
2.5.5 For more information, see paragraph 1.4, Submittal Procedures, of Section 01010, Summary of Work.
2.6. Color Boards.
2.6.1. The Color Boards must contain samples, schedules, and descriptions as necessary to identify all finishes.
Photographs or renderings may supplement the descriptions, but may not be used instead of samples.
2.6.2. Submit color boards on 8-1/2" x 11" sheets in three-ring binders. Sheets must be neutral-colored illustration board heavy enough to support samples without tearing out of the binder. Adhesives must permanently bond samples to the sheets.
2.7. Design Submittal Package Requirements. The Contractor shall submit to the Government the following copies of the contract drawings, specifications, and other contract documents at each design stage.
2.7.1. Investigation Report.
• two (2) copies Investigation Report
2.7.2. 65% Design Submittal.
• 1 copy of the draft Design Analysis.
• 1 copy of full-size drawings and two (2) copies of half-size drawings.
• 1 copy of Contractor-edited specifications with edit notes.
• 1 copy of the AF Form 3000, Material Approval Submittal (to include cutsheets and substantiating information) of major equipment items of items with long lead times. The Contracting Officer may provide copies of the AF Form 3000 with applicable instructions for completion and submission.
• 1 copy of the AF Form 66, Schedule of Material Submittals, reflecting the above submittals.
• 2 CD’s with PDF’s copies of all documents and PDF and AutoCAD copies of all drawings.
2.7.3. 95% Design Submittal.
• 1 copy of the interim Design Analysis with edit notes (as necessary to document 65% Design Submittal reviews).
• 1 copy of full-size drawings and two (2) copies of half-size drawings.
• 1 copy of Contractor-edited specifications with edit notes (as necessary to document 65% Design Submittal reviews).
• 1 copy of the AF Form 66, Schedule of Material Submittals with edit notes (as necessary to document 65% Design Submittal reviews).
• 2 CD’s with PDF’s copies of all documents and PDF and AutoCAD copies of all drawings
• 1 copy of the color board showing all interior/exterior finishes
2.7.4. 100% Design Submittal (with all 65% and 95% Design Submittal review comments incorporated)..
• 1 copy of the final Design Analysis.
• 1 full-size and one half-size sets of high-quality bond drawings.
01011-11
• 1 copy of the specifications.
• 1 copy of the AF Form 66, Schedule of Material Submittals.
• 2 CD’s with PDF’s copies of all documents and PDF and AutoCAD copies of all drawings.
• 1 copy of the color board showing all interior/exterior finishes
2.8. Review Time for Submittals.
2.8.1. Submittals: Listed above are the numbers of copies (unless otherwise indicated) to be mailed or hand carried to the Base Contracting Officer by the contractor.
2.8.2. Complete all work for the Investigative / Pre-design Phase Stop work until given Notice to Proceed. A review conference will be held at Davis Monthan AFB after a twenty one (21) day review period starting upon receipt by Civil Engineering.
2.8.3. Complete the 65-percent design phase and submit Stop work until given Notice to Proceed. A design- review conference will be held at Davis Monthan AFB after a thirty (30) day review period starting upon receipt by Civil Engineering.
2.8.4. Complete the 95-percent design phase and submit. . A design-review conference will be held at Davis Monthan AFB after a thirty (30) day review period starting upon receipt by Civil Engineering.
2.8.5. Complete the Corrected 100-percent design phase and submit all the required information as described within fifteen (15) days of the Notice to Proceed. No design-review conference will be held.
End of Section 01011