Responses to Louisiana Bridge Fence RFI.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- Construct AFTP Fence, Louisiana Avenue Bridge
- Solicitation number
- FA481924R0017
About this file
This document is a set of responses to questions from a Request for Information (RFI) related to a federal contract opportunity for the construction of an anti-terrorism force protection (ATFP) fence on Tyndall Air Force Base in Florida. The key details are:
The government prefers the fence to run straight as discussed at the site visit, rather than using a dogleg configuration shown in the drawings. The contractor can cut off posts at grade for the removal of the gate and posts across Louisiana Avenue, but must remove all other posts entirely. The contractor is responsible for removing the existing deadman anchors completely and backfilling all demolished post holes. Reuse of materials from the demolished fence is limited - chain-link fabric and concrete-encased poles cannot be reused. The government acknowledges the potential for material lead time delays and will allow extensions to the period of performance if needed to accommodate procurement timelines.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question No. | QUESTION | GOVERNMENT RESPONSE |
| 1 | Drawing C-100 in the Northwest quadrant, depicts a dogleg in the fence. Does the government intend to use this dogleg or should the fence run straight, as discussed at the visit? | The government prefers the fence to run straight as discussed at the bid walk. |
| 2 | Please confirm that the contractor can cut off posts at grade for the removal of the gate and posts across Louisiana Ave. only. All other posts are to be pulled in their entirety. | These can be cutoff flush with grade. Any holes must be filled with non-shrink grout. |
| 3 | Will the contractor be responsible for the complete removal of the existing dead men anchors or are the turnbuckles able to be cut off below grade? | The deadman anchors must be removed entirely. Please note that these were formed and cast above-grade and buried. They are not cast-in-place. |
| 4 | Will the contractor be responsible for the back filling of demolished post holes? | Yes |
| 5 | Please confirm contractor can reuse all usable material (except chain-link fabric) from demolished fence and acable on the new fences. | Fence fabric and any concrete encased poles that are demo'd cannot be reused. |
| 6 | Contractor has confirmed that materials lead time for project is approximately 60-90 days, at present. Please confirm that if necessary due to materials lead times that the period of performance will be extended, as appropriate. | The government is well aware of the impact on available and lead time on materials. If the timeline needs to be extended to accommodate procurement, it will be allowable. |