1. RFP SOW Title_XLWU 19-8195_13Jun2022.docx

DOCX document 158 KB Posted

Attached to
Repair/Restore Pest Management Facility Federal contract opportunity
Solicitation number
FA481922R0015
Issued by
Department of the Air Force Air Combat Command

About this file

This Request for Proposal (RFP) solicits design-build services for the repair and restoration of a Pest Management Facility at Tyndall Air Force Base in Florida. Key requirements include repairing interior and exterior building elements as well as installing new compound fencing and support structures. The period of performance is 365 calendar days from notice to proceed. The contract will be fixed-price. The project value is between $800,000 to $2,000,000. Performance and payment bonds are required. Davis-Bacon wage determinations apply. The solicitation is set aside for HUBZone small businesses. Proposals are due via the request for proposal process in accordance with FAR Part 15.

View the file

Other files for this federal contract opportunity

Other files attached to Repair/Restore Pest Management Facility, newest first.
File Type Posted
Solicitation Amendment FA481922R00150003 SF 30.pdf PDF
Attachment 5 Section L and M 29 Jun 22.docx DOCX document
R00015 Q and A Part 2 Answered.xlsx XLSX spreadsheet
Solicitation Amendment FA481922R00150002 SF 30.pdf PDF
R00015 Q and A - Answered.xlsx XLSX spreadsheet
2. RFP APPENDIX - A Title_XLWU 20-8195_20220610.docx DOCX document
Attachment 5 Section L and M 15 June 2022 Update.docx DOCX document
Site Visit Sign in Sheet.pdf PDF
Solicitation Amendment FA481922R00150001 SF 30.pdf PDF
3. RFP APPENDIX - B Drawings 13Jun2022.pdf PDF
Attachment 14 Proof of Financial Responsibility.pdf PDF
Solicitation - FA481922R0015.pdf PDF
Attachment 2 RFP APPENDIX - A Repair Pest Management Facility_XLWU 20-8195_20Apr2022.pdf PDF
Attachment 4 RFP APPENDIX - C Repair Pest Management Facility_XLWU 20-8195.pdf PDF
Attachment 8 AF Form 66.xlsx XLSX spreadsheet
Attachment 9 AF Form 3000.pdf PDF
Attachment 10 AF 3064.pdf PDF
Attachment 13 Base Access Request EAL.xlsx XLSX spreadsheet
Attachment 3 RFP APPENDIX - B Drawings.pdf PDF
Attachment 5 Section L and M.docx DOCX document
Attachment 7 Wage Determination Building - FL20220005.pdf PDF
Attachment 15 AF Form 813 Demolish and Construct Pest Management Facility.pdf PDF
Attachment 1 RFP SOW Repair Pest Management Facility_XLWU 19-8195_20Apr2022.pdf PDF
Attachment 6 Other Contract Requirements.pdf PDF
Attachment 11 AF3065.pdf PDF
Attachment 12 Sample RFI.PDF PDF
Attachment 16 Division Cost Estimate Worksheet.xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4819-22-R-0015

20 Apr 2022

REQUEST FOR PROPOSAL

For

Repair (Restore) Pest Management Facility Building 1701

TYNDALL AFB FLORIDA

Project Number: XLWU 20-8195

4/20/2022

Contents

1.0SCOPE4
1.1General Requirements4
2.0APPLICABLE DOCUMENTS9
3.0GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)14
4.0MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS15
4.0A Table 1 - Table of Deliverables17
4.1Work Breakdown Structure (WBS)20
4.2Schedule and Planning Requirements20
4.2.1Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)20
4.2.2Integrated Master Schedule (IMS)20
4.2.2.1Contract Progress Schedule (AF 3064)20
4.3Status Reporting21
4.3.1Reporting Requirements for Firm Fixed Price (FFP)21
4.4Meeting and Conference Requirements21
4.4.2Red Zone Meeting22
4.5Contractor Documentation23
4.6Not Used24
4.7Permits24
4.8Not Used25
4.9Not Used25
4.10Site Access Badges25
4.11Worksite Activities and Coordination27
4.11.1Coordination of Activities27
4.11.2Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting28
4.11.3Recording and Preserving Historical and Archaeological Finds34
4.12Project Data/Project Deliverables35
4.12.1Protecting Unclassified DoD Data35
4.12.2Security Breach Notification35
4.12.3Data Collaboration Site35
4.13Health and Safety Plan (HSP) or (APP)35
4.14Quality System Plan (QSP)35
4.15Technical Plans and Reports36
4.15.1Construction Work Plan36
4.15.2Technical Reports36
4.15.3Environmental Protection Plan (EPP)36
5.0PROSECUTING THE WORK36
5.1Site Work38
5.1.1Conservation38
5.1.2Site Preparation38
5.1.3Demolition40
5.2Construction Operation Services41
5.2.1Construction41
5.2.2Completion Walkthroughs44
5.3Demobilization47
5.4Emergency Response47
5.5Maintenance and Repair47
5.6Ordnance Removal and Support47
5.7Security Requirements:47
5.8GENERAL SAFETY REQUIREMENTS48
5.9GENERATED REFUSE51
6.0FACILITY CONSTRUCTION PROJECT DELIVERY METHODS52
6.1Design Build (D-B)52
6.1.1Designers of Record (DOR)53
6.1.2Contractor Design Requirements after Award53
6.1.3User Requirements Design Meeting55
6.1.4Geotechnical/Hazardous Material Survey Requirements and Responsibilities.56
6.1.4.1Soil Survey Requirements and Responsibilities for Contractor.56
6.1.5General Design Requirements58
6.1.6Design Review72
6.2Design-Bid-Build (D-B-B)73
7.0ADDITIONAL REQUIREMENTS73
7.1Types of Projects/Work73
7.1.1Military Family Housing73
7.1.2Fueling System Projects73
7.1.3Range Construction73
7.1.4Renovations (including historic buildings)74
7.1.5Construction of Classified or Highly Secure Facilities74
7.2As-Built Documentation74
POINTS OF CONTACT (POCs)77
Attachments:78
Appendix A Description of Work78
Appendix B Maps, Drawings, and Other Project Specifics78

Appendix C Asbestos and Hazardous Materials Surveys…………………………………….............………………... 78

1.

1.0 SCOPE

A. This is a Design-Build project for the repair and restoration of an existing building as well as new compound fencing and two (2) new pre-engineered support structures. The project is comprised of work on Tyndall AFB and the related disciplines of work as specific tasks in Scope of Work (Appendix A). The Design-Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW).

B. The Contractor shall be responsible for all professional services, A/E design, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the tasks defined by the SOW, including the disposal of all resulting waste materials and project clean up. The performed tasks shall be based on the project description, other data furnished in this SOW, and information covered during kick-off meeting.

C. This SOW sets forth the requirements for Design/Build (DB) contract site-specific design and construction effort to remove, repair and restore interior and exterior elements and related infrastructure within a building on Tyndall AFB, Florida.

D. See Appendix B for Supporting Documentation.

1.1 General Requirements

A. Applicable provisions of the Contract Clauses in the contract will govern work under each section of the specifications.

B. This project has an estimated period of performance from Notification to Proceed (NTP) through completion and turnover of the facility back to the Government for mission operations of 365 calendar days.

C. Proposal Documents: The contractor shall complete the proposal schedule included in the solicitation and include the completed schedule with the submitted proposal documents.

D. Measurements: The contractor is required to validate dimensions and quantities. The quantities are listed as approximations and contractor field measurements and quantity verification should be used for bidding package.

E. Field Changes:

a. Field Changes: The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the CO prior to execution. Only the CO may authorize field changes or deviations from the SOW.

b. No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether or not acting within the limits of his authority, or any other representatives of the Government, shall constitute a change order under the “Changes” clause of this contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting Officer.

F. Job Start Meeting: A job start meeting shall be accomplished with the Contractor, Contracting Officer, CE, and user following the Notice to Proceed (NTP). The meeting objective is to review project details, determine design delivery dates and anticipated construction start date, security procedures for site, dumpster locations, and any applicable requirements during construction. The Contractor shall visit the job site to verify location, conditions, and dimensions prior to starting work.

G. Pre-Construction Meeting: A preconstruction meeting shall be held when design has reached the Issued for Construction (IFC) stage and all preconstruction submittals have been approved. The contractor Quality Control Manager, Site Safety Officer, and Superintendent shall be required to attend. This meeting will address all items specific to the project to include access, safety, and environmental needs.

H. Facility Occupancy: This project will take place within an occupied facility and the mission of the occupants will continue in close proximity to this work. Work will need to be phased and coordinated with those occupants throughout. This contract includes the partial demolition of the existing facility.

I. Bulletin Board: Immediately upon mobilization, the Contractor shall provide a bulletin board not less than 36 by 48 inches (915 by 1220 mm) in size for displaying various documents required within the contract. The bulletin board shall be located at the project site in a conspicuous place easily accessible to all employees. All documents posted shall be legible and replaced as needed when unreadable. The board shall be displayed until the work is completed whereby the Contractor shall remove the board and remain the property of the Contractor. The contents of the board shall include, but not limited to, the following:

a. Contractor’s company name

b. Project name

c. MPLS number

d. Superintendent’s name and a 24 hour available response phone number

e. Equal Employment Opportunity poster

f. Wage determination

g. Wage Rate Information poster.

h. Other documents as needed or required.

J. Employee Parking: Contractor employees shall park privately owned vehicles in an area designated by CES and approved by the CO.

K. Job Site Tools and Equipment: All hand tools and equipment shall be maintained in good working conditions and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.

L. Field Measurements: The Contractor shall be required to make his/her own field investigations to verify existing conditions, dimensions and other information shown on Government available non-verified furnished reference drawings, solicitation documents and construction documents. Deviations, errors, or omissions in the government supplied reference materials or the design team’s construction documents shall be identified and addressed by the contractor during the design phase of the contract. They shall be annotated on the respective contract documents as well as on a consolidated register that will be made available to the government for simplified identification and review.

M. Notification Requirements: The Contractor shall notify the Government a minimum of ten (10) days in advance of each mobilization. The Contractor is required to notify the CO and Government Project Manager of critical issues that may affect the contract performance and/or human health and the environment. For critical issues pertaining to human health and the environment, the Contractor shall immediately notify the CO and stop work. Work shall only resume at the direction of the CO following resolution of the issue.

N. On-Site Field Oversight: The Contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of the construction period for the contract. It is the responsibility of the Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.

O. Federal Holidays:

a. The standard Federal legal holidays are observed:

1. New Year’s Day

2. Birthday of Martin Luther King, Jr.

3. Washington’s Birthday

4. Memorial Day

5. Independence Day

6. Labor Day

7. Columbus Day

8. Veterans Day

9. Thanksgiving Day

10. Christmas Day

11. Juneteenth

b. Any of the holidays falling on Saturday will be observed on preceding Friday; holidays falling on Sunday will be observed on the following Monday. In addition, the Government may dictate the work day before or the work day after an observed holiday as a “Family Day.”

c. The Contractor should not perform work on observed holidays, Wing Down Days, Wing Safety Days or Family Days unless authorized by the Contracting Officer for the TO. In the event work is authorized on observed holidays, the Contractor shall pay all applicable overtime and/or holiday pay rates required by law.

P. Working Hours: The normal duty hours of the facility are from 7:00 AM to 5:00 PM, Monday thru Friday excluding Federal Holidays. All work shall be performed during normal duty hours. All other hours to include weekend and holidays shall be requested through the CO for approval. This request shall be submitted no less than three (3) workdays prior to the time requested.

Q. Availability and Use of Utility Services: The contractor should plan on having an offsite office location. The government does not guarantee office space will be provided. The Government does not guarantee utilities will be provided for office space. The use of a generator and porta toilets may be required of office space is provided. To install and office space and laydown yard will require an 813 permit determination and could take up to 60 days to obtain the permit.

R. Sanitation: The Contractor shall provide and maintain within the construction area minimum field-type sanitary facilities approved by the CO. Government toilet facilities will not be available to Contractor's personnel.

S. Clean Up: At the end of each working day the Contractor shall clean up the work site by the removal of all construction debris, waste materials, packaging material and the like. If the before mentioned items could become airborne they shall b placed in refuse containers immediately. Clean up of the work site shall include the construction area(s), construction office area(s), material storage area (s), parking and eating area(s), and any other area(s) affected by the construction process. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily. Materials resulting from demolition activities which are salvageable shall be stored within the work area or at a supplemental storage area. Stored material not in trailers, whether new or salvaged, shall be neatly stacked when stored in an approved location.

T. Contractor’s Management and Use of Electromagnetic Emission Devices on Base: (Electromagnetic emission devices include: Radio/Radar Transmitters; Navigational Aids/Instrumentations; Signaling, Intrusion Detecting, and Identification Devices; Mobile and Fixed Business Radio Communications Equipment; and MARS, CBs, and Amateur Radio Stations.) The Contractor shall comply with the Air Force Military Training Center (AFMTC) Regulation 700-14, Jul 89.

U. Preparation of Progress Schedules and Reports: The reports contemplated by FAR Clause, 52.236-15, Schedules for Construction Contracts, shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. Contract Schedules and Reports shall run from Monday through Sunday and be submitted to the CO per table of deliverables located in 4.0A Table 1 - Table of Deliverables.

V. Deteriorated Construction And Finish

a. Authority: The QA Inspector will be the governing authority in determining if existing construction and finishes are deteriorated and require repair and/or replacement.

W. Contractor Storage/Staging Area

a. Operations and Storage Approval: Notwithstanding Contract FAR Clause, FAR 52.236-10, Operations and Storage Areas, subject to approval by the CO and in turn, availability and need, a storage/staging area may be provided at the subject project site. If project site space is not available, then offsite storage may be required.

b. Utility ‘tie-ins’, where available, are the Contractor’s responsibility. See 1.1 General Requirements, Q. Availability and Use of Utility Services for additional information.

c. Storage Area Clean Up: Weekly discard trash and debris in the Contractor’s containers (dumpsters). Do not allow debris to accumulate. At work completion, clean the storage area. This area must be free of any materials, trash or debris before receipt of final payment.

d. In areas of high visibility, the job site construction fence shall have a screen fabric material applied to the fence fabric in order to block the view during the construction phase. The CO will make the determination at the pre-construction meeting if the subject project will require a screened fence or not. Remove fence upon completion. Rehabilitate disturbed turfs and grass and if reseeding is required use Bermuda grass.

X. Hazardous component abatement for materials such as asbestos, lead-based paint, PCBs, and other hazardous materials shall be the responsibility of the Contractor. Abatement of mold resulting from water damaged materials shall be the responsibility of the Contractor.

Y. The duration of days is considered calendar days unless otherwise noted.

Z. COVID-19 Requirements - During the COVID-19 pandemic it is vital to Tyndall AFB’s Mission that the Contractor adhere to all Tyndall AFB Covid-19 directives to mitigate virus transmission. The contractor shall be responsible for the following: follow CDC guide lines, setting up teleconference meetings, wearing mask and social distancing when entering a government facility, the screening of their employees, and reporting COVID-19 cases to 325CONS Contracting Officer (CO) and 325CES Project Manager (PM). As Covid-19 directives are living documents, it is the Contractor’s responsibility to be informed and follow the most recent published directive.

2.0 APPLICABLE DOCUMENTS

A. The Contractor shall identify and comply with all applicable federal, state, and local laws; statutes; Executive Orders; Department of Defense/Air Force manuals, handbooks, regulations, guidance, and policies. The contractor shall comply with the National Institute of Building Sciences’ Whole Building Design Guide Construction Criteria Base (CCB) Unified Facility Criteria (UFC) 3-600-01 and all of the related libraries. The primary criteria are the Air Force Criteria from the Documents Library, but other agency criteria may be directed for use, depending on the customer agency for a particular TO. The Unified Facilities Guide Specifications (UFGS) is the mandatory starting point for all specifications, and shall not be deleted, materially modified, or made less stringent without Government approval. It is the contractor’s responsibility to identify and comply with all applicable requirements. It shall be the contractor’s responsibility as the Designer of Record (DOR) to identify any design/construction criteria waivers that are warranted for the Project and to accomplish all necessary coordination activities necessary to obtain approval of these proposed waivers through the Contracting Officer (CO), and/or Project Manager (PM).

B. In addition, the contractor shall refer to and comply with the current versions of the Department of Defense Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and The United States Air Force Construction Management Implementation Guide as well as the latest version of The USAF Project Manager’s Guide to Design and Construction. Base-specific documents are identified in the attached appendices.

C. The Contractor and Design Team shall adhere to the following guidance during design and construction phase(s) of this project: Those sections of the Southern Standard Building Codes not incorporated in the UBC/International Building Code (IBC) for our respective area, International Concrete Repair Institute (ICRI) Guidelines, Air Force Standards, Department of Defense (DOD) Directives, Florida State Statutes, and the Tyndall AFB Facility Excellence Plan (Base Regulations), Occupational Safety and Health Administration (OSHA) Requirements, Department of Environmental Protection (DEP) Regulations, Environmental Protection Agency (EPA) Regulations, and ABA Accessibility Compliance Requirements.

D. In addition to adhering to the previous guidance, the Contractor shall review and adhere to the most recent version of the following code criteria as applicable at start of the design phase:

a. UFC 1-200-01The DoD Building Code
b. UFC 1-200-02High Performance and Sustainable Building Requirements
c. UFC 1-300-02Unified Facilities Guide Specifications (UFGS) Standard
d. UFC 1-300-07ADesign Build Technical Requirements
e. UFC 1-300-08Criteria for Transfer and Acceptance of DoD Real Property
f. UFC 3-101-01Architecture
g. UFC 3-110-03Roofing
h. UFC 3-110-04Roofing Maintenance and Repair
i. UFC 3-120-01Design: Sign Standards
j. UFC 3-120-10Interior Design
k. UFC 3-190-06Protective Coatings and Paints
l. UFC 3-201-01Civil Engineering
m. UFC 3-201-02Landscape Architecture
n. UFC 3-210-10Low Impact Development
o. UFC 3-220-01Geotechnical Engineering
p. UFC 3-220-05Dewatering and Groundwater Control
q. UFC 3-230-01Water Storage and Distribution
r. UFC 3-240-01Wastewater Collection and Treatment
s. UFC 3-250-01Pavement Design for Roads and Parking Areas
t. UFC 3-250-03Standard Practice Manual for Flexible Pavements
u. UFC 3-250-04Standard Practice for Concrete Pavements
v. UFC 3-250-08FASealing Joints and Cracks
w. UFC 3-250-11Soil Stabilization for Pavements
x. UFC 3-260-02Pavement Design for Roads, Streets, Walks, and OpenStorage Areas
y. UFC 3-301-01Structural Engineering
z. UFC 3-310-04Seismic Design for Buildings
aa. UFC 3-400-02Design: Engineering Weather Data
ab. UFC 3-401-01Mechanical Engineering
ac. UFC 3-410-01Heating, Ventilating, and Air Conditioning
ad. UFC 3-410-02Direct Digital Control for HVAC
ae. UFC 3-410-04Industrial Ventilation
af. UFC 3-420-01Plumbing Systems
ag. UFC 3-430-09Exterior Mechanical Utility Distribution
ah. UFC 3-450-01Noise and Vibration Control
ai. UFC 3-501-01Electrical Engineering
aj. UFC 3-520-01Interior Electrical Systems
ak. UFC 3-530-01Interior and Exterior Lighting and Controls
al. UFC 3-550-01Exterior Electrical Power Distribution
am. UFC 3-560-01Electrical Safety O&M
an. UFC 3-570-01Cathodic Protection
ao. UFC 3-575-01Lightning and Static Electricity Protection
ap. UFC 3-580-01Telecommunications Interior Infrastructure
aq. UFC 3-600-01Fire Protection Engineering for Facilities
ar. UFC 3-701-01DoD Facilities Pricing Guide, with Change 2; 2019
as. UFC 3-730-01Programming Cost Estimates for Military Construction
at. UFC 3-740-05Handbook: Construction Cost Estimating
au. UFC 4-010-01DOD Minimum Antiterrorism Standards for Buildings
av. UFC 4-010-05Sensitive Compartmented Information Facilities
aw. UFC 4-021-01Mass Notification Systems
ax. UFC 4-021-02Electronic Security Systems
ay. UFC 4-211-01Aircraft Maintenance Hangars
az. USAF BIMMinimum Requirements Version 2.1
ba. ABASArchitectural Barriers Act Standards; The ABA
may be found at https://www.access-board.gov/guidelines-
and-standards/buildings-and-sites/about-the-aba-
standards/aba-standards
bb. AFDSAir Force Design Guide
bc. AFGM 2018-32-01Civil Engineer Control Systems Cybersecurity
bd. AFI 32-1020Planning And Programming Built Infrastructure Projects
be. AFI 32-1024Standard Facility Requirements
bf. AFI 32-1063Electrical Power Systems
bg. AFI 32-1064Electrical Safe Practices
bh. AFI 32-1065Grounding System
www.wbdg.org › FFC › AFI › afi_32_1065_2017
bi. AFI 32-1067Water Systems
bj. AFI 32-1068Heating Systems and Unfired Pressure Vessels
bk. AFI 32-1069Gas Supply and Distribution
bl. AFMAN 91-203Air Force Occupational Safety, Fire and Health Standards
bm. AFMAN 32-1084Facility Requirements Standards
bn. ASCE 7-10Wind Loads
bo. ASHRAE 62.1Ventilation for Acceptable Indoor Air Quality
bp. ASHRAE 90.1Energy Standard for Bldgs. Except Low-Rise Residential
bq. ASHRAE 100Energy Conservation in Existing Buildings
br. ASHRAE 111Testing, Adjusting, and Balancing of Building HVAC
Systems
bs. ASHRAE 180Inspection & Maintenance Commercial Bldg. HVAC
Systems
bt. ASHRAE 202Commissioning Process for Buildings and Systems
bu. ASHRAE Guide 4Prep of Operating and Maintenance Documentation
bv. ECB 2018-11Control System Cybersecurity Coordination Requirement
bw. EISAEnergy Independence and Security Act of 2007
bx. EM 385-1-1USACE Safety and Health Requirements Manual
by. FC 4-218-03FAir Force Criteria for Precision Measurement EquipmentLaboratory Design and Construction
bz. FARFederal Acquisition Regulations
ca. FS 553Florida Building Code
cb. IBC 2018International Building Code, 2018 Edition
cc. IESIlluminating Engineering Society Lighting Handbook
cd. IMCInternational Mechanical Code
ce. IPCInternational Plumbing Code
cf. MIL-HDBK-1190MILITARY HANDBOOK: FACILITY PLANNING AND
DESIGN GUIDE
cg. NBIMS US V3National BIM Standard US Version 3
ch. NEBBStandards for Whole Building Systems Commissioning
ci. NECNational Electrical Code, current edition
cj. NEMANational Electrical Manufacturer's Association
ck. NESCNational Electrical Safety Code current edition
cl. NFPA 13Standard for the Installation of Sprinkler Systems
cm. NFPA 70National Electric Code
cn. NFPA 72National Fire Alarm Code
co. NFPA 101Life Safety Code

cp. NFPA 1141

cq. NPDES National Pollutant Discharge Elimination System http://www.dep.state.fl.us/water/stormwater/npdes/construction3.htm

cr. SMACNA GuidesSheet Metal & Air Conditioning Contractors’ National
Assoc.
cs. TAFB FEPTAFB Facility Excellence Plan
ct. TAFB IFSTAFB Installation Facility Standard
https://www.tyndallifs.com/
cu. TM 5-683Facilities Engineering Electrical Interior Facilities
cv. TM 5-684Facilities Engineering - Electrical Exterior
cw. USAF BIMMinimum Requirements Version 2.1
cx. UFASUniform Federal Accessibility Standards
cy. UFGS 23 09 00Instrumentation and Control for HVAC
cz. UFGS 23 09 13Instrumentation and Control Devices for HVAC
da. UFGS 23 09 23.02BACnet Direct Digital Control for HVAC and Other
Building Control Systems
db. UFGS 23 09 93Sequences of Operations for HVAC Controls
dc. UFGS 25 05 11Cybersecurity for Facility-Related Control Systems
dd. UFGS 23 08 10Utility Monitoring and Control System Testing
de. UFGS 25 10 10Utility Monitoring and Control System (UMCS) Front End
and Integration

df. Tyndall Mass Notification System Messages

dg. Tyndall Rebuild Facility Related Control Systems (FRCS) Technology Summary –Appendix L –22 Sept 2021

dh. Memorandum For ALMAJCOM-FOA-DRU, Mandatory Use Policy for Air Force Carpet Acquisitions within the Contiguous U.S.

E. Lightning Protection Requirement: Lightning Protection System (LPS) shall be designed and installed IAW the following references:

a. AFI 32-1065Grounding System
www.wbdg.org › FFC › AFI › afi_32_1065_2017
b. NFPA 70National Electric Code
c. NFPA 780Standard for the installation of Lightning Protection System
d. UFC 3-575-01Lightning and Static Electricity Protection System
e. UL 96Lightning Protection Components
f. UL 96AInstallation Requirements for Lightning Protection System
g. UL 467Grounding and Bonding Equipment

F. Security Requirements:

a. MIL-HDBK-1013:DOD Military Handbook Design Guidelines for Physical
Security of Facilities
b. AFI 31-101:Air Force Instruction 31-101: The Air Force Installation
Security Program
c. DOD 5200.1.RDepartment of Defense 5200.1.R: Information Security
Program Construction Standards.
d. ICD-ICS-705Tech Spec
e. UFC 4-010-01Unified Facilities Criteria Antiterrorism Standards for New
and Existing Facilities
f. UFC 4-010-05Sensitive Compartmented Information Facilities
g. UFC 4-010-06Cybersecurity of Facility-Related Control Systems

G. FAR Case No. 92-54 requires the Solicitation Package for all construction projects to reflect the government's preference for "acquisition of environmentally sound and energy efficient products and services, and an affirmative procurement program favoring items containing the maximum practicable content of recovered materials".

H. DOD Information

a. Department of Defense Manual 5200.01, Volume 1; DoD Information Security Program: Overview, Classification, and Declassification; 2012

b. Department of Defense Manual 5200.01, Volume 2; DoD Information Security Program: Marking of Classified Information; 2013

c. Department of Defense Manual 5200.01, Volume 3; DoD Information Security Program: Protection of Classified Information; 2013

d. Department of Defense Manual 5200.01, Volume 4; DoD Information Security Program: Controlled Unclassified Information (CUI); with Change 1 2018

I. DOD Information J. Facilities Department of K. Federal Green Construction Guide for specifiers. This guide can be found at: http://www.wbdg.org/design/greenspec.php

L. Non-ERP Soil Management Guidelines, May 2020

M. The Contractor shall perform all work IAW with AFI, ETL, UFC and industry standards. Compliance with AF UFCs is mandatory unless the IFS has more stringent requirements. If the Contractor determines that the work cannot be performed and/or included in the SOW IAW with ETL’s/UFCs or industry standards, the Contractor shall notify the Tyndall AFB POC listed in this document in writing immediately before award of the contract. Otherwise, the Contractor shall be responsible for the required work.

N. All work shall be in compliance with all Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DODI), Department of Defense Directives (DODD), or other higher authority documents as applicable. Many applicable compliance documents are authorized by DoD MIL-STD-3007F, and are available through the Government-sponsored Whole Building Design Guide located at https://www.wbdg.org.

O. If there is a conflict between these codes, regulations specifications, and/or guidance documents, the most stringent requirements shall apply, as determined by the CO through the Request for Information (RFI) process. These listed documents do not relieve the Contractor from complying with other required regulatory documents not listed.

P. The government may take up to 30 days to review design documents. The contractor schedule activity for less days will be overridden by this time frame and will not be considered a delay by the government. The contractor schedule shall reflect the 30 day review time.

3.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)

A. Historical architectural and structural construction documents may be available for review, however field verification and documentation of existing conditions and configurations prior to construction is essential. The government takes no responsibility for errors and omissions contained in the reference material and field verification shall be performed by the contractor.

4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS

A. Design submittals, 65%, and 100%, will be routed with an AF Form 3000 and will be reviewed and approved/disapproved within 15 calendar days.

B. No delay damages or time extensions will be allowed for time lost in late or lost submittals. The official review time starts when the CO acknowledges the receipt of the submittal.

C. Submittals pertaining to environmental issues may take up to 30-45 days for review and approval. Wetland permits may take greater than 60 days to process. Environmental 813 submittals shall include drawings, locates for utilities with depth, size of lines, length of runs, underground or above ground routing, spatial coordinates, duration of the laydown yard or temporary trailer, number of personnel, location of temporary porta toilets, etc. Delays greater than the anticipated days listed herein do not constitute a governmental delay. Contractor will be allotted a no-cost Period of Performance (PoP) extension for days over and above those listed herein.

D. All other submittals should be reviewed and approved/disapproved within 10 work days. Submittals will be reviewed for accuracy and relevance to the project and specifications. Material Submittal documents shall be submitted with AF Form 3000, Material Approval Submittal.

E. Submittal documents shall include required forms, reports, drawings, samples, pictures, media recordings, manufacturer data, certifications, test reports, equipment warranty information, and the like. Submittal documents shall be submitted by the Contractor to the by CO for approval. All submitted documentation shall become the complete property of the Government. The Contractor shall not purchase, install, or construct any equipment or facility component, for which a submittal is required, without first obtaining an approved signed submittal from the CO. Required submittals shall be listed on AF Form 66, Schedule of Material Submittals, and/or a Submittal Register approved by the CO.

F. Table of Deliverables: Project deliverables shall be as shown in the following 4.0A Table 1 - Table of Deliverables. The dates in the table are hard dates not to be exceeded without CO approval. The deliverables and scheduled activities may be provided or completed early.

G. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.

H. Submittals required by the contract documents shall be listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but have been omitted from the register or marked "N/A."

I. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.

4.0A Table 1 - Table of Deliverables

Document

Copies
Max Delivery Timeframe
325 CES
325 CONS
Electronic
Hard Copy
Electronic
Hard Copy

Standard Meetings and Reports

Meeting Minutes
1
0
1
0
3 calendar days after each meeting
Progress Schedule(AF 3064 or approved equivalent)
1
0
1
0
5 calendar days after NTP
Progress Report (AF 3065 or approved equivalent)
1
0
1
0
Weekly
3-week Look Ahead report
1
0
1
0
Weekly
Daily Logs - Form 1477 or equiv.
1
0
1
0
NLT 0900 the day following - Daily
HAZMAT Forms 81 and 82
1
1
1
1
10 Days prior to preconstruction meeting
Work Clearance Request (AF Form 103A)
1
1
1
1
10 Days prior to preconstruction meeting
Submittal Register (AF Form 66)
1
0
1
0
At the 100% Final Design
Construction Material Testing Reports
1
0
1
0
As required
Welding/Burn Permit
1
0
1
0
Prior to commencing work
Production or Delivery Problem Report
1
1
1
1
At time of identification
Draft DD1354
1
0
1
0
When request for final inspection is submitted

Work Activities

Kickoff meeting with all stakeholders
1
0
1
0
5 Days Prior to NTP
Health and Safety Plan (HSP) or (APP)
1
0
1
0
Prior to site visits
NTP
1
0
1
0
NA
Contractor Site Investigation
1
0
1
0
5 Days from NTP
Design Quality Plan (DQCP) or (DQSP)
1
0
1
0
Prior to Design Starting
Quality Control Pan (QCP) or (QSP)
1
0
1
0
Prior to construction activities
Construction Work Plan (CWP)
1
0
1
0
Prior to construction activities
Site Investigation Memorandum
1
0
1
0
10 Days from NTP
35% Design w/ AF Form 3000
1*
0
1*
0
40 Days from NTP
35% Design Review and Meeting
1
0
1
0
30 Days from 35% Design Submittal
35% Design Resubmittal if submittal was disapproved
1
0
1
0
10 Days from 35% Design Disapproval
35% Design Final Submittal and Approval
1
0
1
0
10 Days from 35% Design Re-Submittal
65% Design w/ AF Form 3000
1*
0
1*
0
20 Days 35% Design Approval
65% Design Review and Meeting
1
0
1
0
30 Days from 65% Design Submittal
65% Design Resubmittal if submittal was disapproved
1
0
1
0
10 Days from 65% Design Disapproval
65% Design Final Submittal and Approval
1
0
1
0
10 Days from 65% Design Re-Submittal
100% Design w/ AF Form 3000
1*
0
1*
0
20 Days from 65% Final Design
100% Design Review and Meeting
1
0
1
0
30 Days from 100% Design Submittal
100% Design Resubmittal if submittal was disapproved
1
0
1
0
10 Days from 100% Design Disapproval
100% Design Final Submittal and Approval
1
0
1
0
10 Days from 100% Design Re-Submittal
All Material Submittals
1
0
1
0
As called out in AF Form 66
Demolition Plan when demolition activities
1
0
1
0
Prior to 100% Design Approval
Environmental Plan (EPP)
1
0
1
0
Prior to Construction Activities
Storm Water Pollution Protection Plan (SWPPP)
1
0
1
0
Provided as part of the EPP
Red Line drawings Submitted
1
0
1
0
As required
Mobilization of Contractor
0
0
0
0
After pre-construction meeting.
Pre-Construction Meeting
1
0
1
0
After all pre-construction submittals are submitted and approved.
Red Zone Meeting
1
0
1
0
60 Days Prior to Beneficial Occupancy Date (BOD) or 80% point in progress
Pre-Final Walkthrough Punchlist
1
0
1
0
At end of Implementation
Pre-Final Walkthrough Punchlist Report
1
0
1
0
5 Days prior to Final Inspection
Operations & Maintenance Manuals
1
1
1
1
5 Days prior to Final Inspection
HAZMAT Form 83
1
0
1
0
Monthly
Final Walkthrough Punchlist
1
0
1
0
10 Days after Pre-Inspection
Final Walkthrough Punchlist Report
1
0
1
0
5 Days After Final Inspection
O&M’s Review
1*
1
1*
0
5 Days After Final Inspection
As-Built Design Documents
1
0
1
0
5 Days After Final Inspection
As-Built Design Drawings
1*
0
1*
0
5 Days After Final Inspection
As Built Review Meeting
1
1
1
1
10 Days After Final Inspection
As Built Review Comments
1
0
1
0
15 Days After Final Inspection
O&M’s Acceptance
1*
1
1*
0
15 Days After Final Inspection
As Built Comments Acceptance
1
0
1
0
20 Days After Final Inspection
As Built Approval
1
0
1
0
20 Days After Final Inspection
Transfer & Acceptance of Military Real Property (DD 1354)
1
1
1
0
5 Days after Final Design Approval
O&M’s to user
1
0
1
0
10 Days after Final Design Approval
User training
1*
1
1*
0
15 Days after Final Design Approval

*Both Autodesk AutoCAD and Adobe Acrobat versions of drawings are required

J. Electronic copies of all design deliverable documents shall be provided on CD or DVD discs, formatted for use by the latest software version, and compatible with the Government’s version of Microsoft Word, Excel, PowerPoint, Access, Outlook, the Adobe family of products, the Autodesk family of applications, the ANSYS family of applications, or other software platform as appropriate and as determined and directed by the CO. Whenever possible, the electronic files given to the Government should be compatible with at least one software program application listed on the Air Force Evaluated Products List (EPL) or the Defense Information Systems Agency (DISA) Approved Products List (APL). For any submitted documents converted to one of the above formats from another software program, the Contractor shall also submit the electronic document file from the software program originally creating it, along with a statement describing what creating software program and version was used, as well as any programs used to convert files from one format to another. Submitted electronic files shall be unlocked and fully editable.

K. Builder Template

a. A builder template will be provided to the contractor to complete for real property items that were installed per the scope of work.

4.1 Work Breakdown Structure (WBS)

A 3064 or equivalent spreadsheet is used for the WBS. The task number, start and stop dates, Value for the task will be provided.

4.2 Schedule and Planning Requirements

See Section General Requirements

4.2.1 Project Planning Chart (PPC) and/or Construction Planning Chart (CPC)

Not Applicable.

4.2.2 Integrated Master Schedule (IMS)

4.2.2.1 Contract Progress Schedule (AF 3064)

A. The Contractor shall submit a signed AF 3064, Contract Progress Schedule, depicting an overall contract progress schedule for the main elements of work for the period of performance as described in the 4.0A Table 1 - Table of Deliverables. The line items, associated project percentages, and dates shall accurately depict the planned work to be performed. The AF 3064 shall be formatted to show schedule by the week (Monday thru Sunday) and shall represent a schedule of values for each line item of work. Note that the schedule should reflect work as Monday through Friday. The AF 3064 shall not show any weekend or holiday work.

B. A template spreadsheet may be provided by the government to use for progress reporting.

C. The progress schedule shall be signed by CE recommending approval and approved by the CO.

4.2.2.2 Contract Progress Report (AF 3065)

1. The Contractor shall submit AF 3065 as described in 4.0A Table 1 - Table of Deliverables. This report shall be signed by the Contractor’s on-site representative in the Remarks section of the AF 3065. The work elements and percentages of the total job identified on the AF 3065 shall be identical to the work elements and percentages on the AF 3064. The Contractor shall obtain either the QA Inspector or the Government contract inspector’s acceptance by signature of the actual reported progress prior to submission to the CO. Additionally, the Contractor shall submit the updated AF 3064 as an attachment to the AF 3065.

4.2.2.3 Submitting Schedules and Reports

1. Contract Progress Report. Contract Schedules and Reports shall run from Monday through Sunday and be submitted to the CO by Tuesday of the following week. Contractor will prepare reports covering activities for days work and give one to the Government Inspector for each week of work even if there was no work accomplished that week. The weekly report may be turned in for each week at the end of the week when construction begins.

A 3064/3064/schedule spreadsheet may be used to coordinate progress reporting. A example spreadsheet can be provided.

4.3 Status Reporting

4.3.1Reporting Requirements for Firm Fixed Price (FFP)
4.3.1.1Contractor’s Progress, Status, and Management Report (CPSMR)

A. A 3065 is used for this project.

4.4 Meeting and Conference Requirements

A. Upon award the Contractor shall attend the following meetings at a minimum: Job Start, Pre-Construction, all Design Reviews, Incremental Site Inspection (as needed), Test and Balance (as needed), Commissioning (as needed), Pre-Final Walkthrough, Final Walkthrough, and other meetings (as needed). The Contractor shall participate in other meetings as needed to facilitate the project’s work, and as required by the CO.

B. Job Start Meeting

a. The Contractor shall attend a Project Job Start at TAFB. The Contractor shall review the most updated versions of codes, standards, and policies applicable to this project prior to the meeting. These documents should include TAFB design standards, DoD Unified Facility Criteria, and the Florida Building Code, among others including those referenced in this document. The Contractor shall, at the Project Kickoff submit a memorandum stating that applicable codes, standards, and policies were reviewed; stating which documents (title, revision number, date, source, etc.) were reviewed, and listing any RFI’s that resulted from the review.

b. The purpose of this meeting is to introduce project stakeholders, clarify the scope of work, review TAFB policies, and communicate information pertinent to the project. Within the time listed in 4.0A Table 1 - Table of Deliverables of the meeting, the Contractor shall submit minutes for approval.

Pre-Construction Meeting

a. Before the contractor can mobilize site and begin construction, the contractor shall attend the pre-construction meeting. This meeting will take place when all of the pre-construction submittals have been submitted and approved.

b. Pre-Construction submittals shall include:

100% Design Documents Contractor QC Plan Site Safety and Health Plan Environmental Protection Plan

c. Contractor personnel to attend this meeting shall include:

Quality Control Manager Site Superintendent Site Safety and Health Officer (SSHO)

Contractor will be responsible to take and distribute meeting minutes to all those in attendance at the meetings. Minutes shall be distributed to attendees for review, comment, and correction the time listed in 4.0A Table 1 - Table of Deliverables of meeting events.

Unedited digital copies of all Contractor recordings shall be provided to the Government within 3 days of the recording date.

4.4.2 Red Zone Meeting

A. Construction Red Zone Activities

Once construction is 80% complete for each facility or 60 days prior to beneficial Occupancy Date (BOD), the Contractor shall conduct weekly Red Zone Meetings instead of the regular weekly Project Update meetings. Red Zone Meetings shall cover not only the construction progress, but also project close out activities, including commissioning activities, training activities, and the preparation of project close out documents.

B. Builder Template

A builder template will be provided to the contractor to complete for real property items that were installed per the scope of work.

4.5 Contractor Documentation

A. The Contractor shall also create and submit for approval an AF Form 66, Schedule of Material Submittals as the project Submittal Register. The Submittal Register shall indicate when documents shall be submitted for review and approval. The modified submittal register shall include design phase submittals, construction phase submittals, and project close out submittals. It shall also include copies of any submittal forms likely needed by the construction Contractor. The submittal register shall include the documents listed below, in addition to other documents, as applicable.

B. Design Package

a. The Contractor shall prepare and submit for review and approval a design package. The package shall be submitted at the 65% and the 100% design level. (4.0A Table 1 - Table of Deliverables for deliverable dates.) The various required elements of the design package are discussed and detailed in other sections of this document.

b. The design of the building and the materials selected shall be high quality, durable and easily maintained. All parts of the project site and building design shall be in compliance with the current version of the Tyndall AFB Installation Facility Standards (IFS).

c. The building interior and exterior design and finishes shall comply with the current Tyndall Air Force Base (AFB) Installation Facilities Standards (IFS). All Exterior Paint and Coatings, Storefront and Entry Doors, Door Glazing, Window Frames and Glazing, Louvers, Hardware, Lighting, Roof Systems and Roofing, Wall Panels, Gutters, Downspouts, Scuppers, Railings and other design related features are to comply with the Architectural characteristic of the Current Tyndall AFB IFS. The 325th CES at Tyndall AFB will make final selections related to all colors and textures for interior and exterior of building from manufacturer's standard color range provided during submittal phase from the contractor. In general, no bronze or brown exterior finishes will be included on the project.

d. Government Review: The Contracting Officer or the authorized representative may furnish the contractor review comments on the data submitted at the 65% and 100% design phase submittals. The Government's review is intended to be limited to functional aspects, with limited technical review of a general cursory nature only. Any review by the Government of technical items shall not be construed to relieve the contractor of responsibility for technically correct and complete documents in compliance with applicable codes, industry standards, and the intent of this SOW. Review comments for compliance with Federal Acquisition Regulations (FAR) will also be provided by the Contracting Officer. Government design review comments will be issued to the contractor within 30 days of design submittal receipt. If any review comment requires clarification and/or amplification to assure compliance, the contractor shall notify the Contracting Officer or the authorized representative in writing. After each review, the contractor will be furnished the comments to be annotated and returned to the Government. The contractor shall furnish these annotated comments to the Government no later than 5 calendar days after receiving the comments. The contractor shall comply with the review comments in the development of data for the next submittal.

e. The Contractor shall provide 100% Final Design package for approval. All previous Government comments shall be addressed in this design package. No review conference is required for this design submittal. The submittal will be formally approved upon verification that the package is complete, and all previously provided review comments have been addressed.

C. Submittal Register

a. The Contractor shall use AF Form 66, Schedule of Material Submittals. The modified submittal register shall include design phase submittals, construction phase submittals, and project close out submittals. It shall also include copies of any submittal forms likely needed by the construction Contractor. The submittal register shall include the documents listed below, in addition to other documents, as applicable.

b. Partial Design Submittal List of Requirements

1. AF Form 3000 documenting the submittal Contents.

2. Table of Contents.

3. Construction documents.

4. Fully populated AF Form 66; Schedule of Material Submittals.

4.6 Not Used

4.7 Permits

A. The Contractor shall develop, coordinate, and be responsible for labor, professional services and other costs associated with acquiring any and all required state, local, and other applicable permits; base access (including off-base easements and leases), agreements, licenses, and certificates required to perform and complete the project. Before the start of work, the Contractor shall process an Air Force Form 103, Work Clearance Request, through the local Base Civil Engineer (BCE) office. The Contractor shall comply with applicable permit conditions, environmental protection policies and appended guidelines.

B. The contractor shall comply with all applicable permit conditions and shall keep all permits “current” until construction is 100% complete. The contractor may be required to provide the permits to the Government as required.

C. If any compliance/enforcement organization notifies the contractor that a certain permit is not required, the government requests a copy of the official notification, from that organization, that the permit is not required. Documentation must be received by the government prior to work commencing.

D. The Contractor shall thoroughly investigate the requirements for permitting of air quality, potable water, wastewater, storm water discharge, NPDES, dredge and fill, local construction for disruptions of vehicular traffic and base utility systems, and other permits during design. The Contractor shall determine permit requirements as part of the Design Phase.

a. Some potential permits for the project:

· FDEP/NFWMD Environmental Resource Permitting in accordance with FAC 62-330

· FDEP/NPDES storm water construction permit in accordance with FAC 62-621

· Environmental Protection Plan (EPP)

4.8 Not Used

4.9 Not Used

4.10 Site Access Badges

A. Registration Process:

a. DBIDS Pre-Enrollment: Individual credential recipients will be required to complete the virtual pre-enrollment process and provide the alpha/numeric number and a legible front/back copy of a valid proofing document with photo (DL, Passport, etc..) to their company.

1. Companies will provide required information to their Authorizing Officials (AO).

2. AO’s will forward information to the VCC via SAFE files for processing.

B. The pre-enrollment process can be located at https://dbids-global-enroll.dmdc.mil/ or by scanning the QR code below.

a. This website allows an individual to pre-enroll…

This is the start of the file's text. The full file is on GovTribe.