This solicitation is for demolition services at Tyndall Air Force Base in Florida. The contractor will demolish 122 structures, remove 125,000 linear feet of abandoned utilities and clear 2.2 million square feet of pavement over a 270-day period. Key response dates include a last day to submit questions of February 4th and bids are due by 1pm on February 23rd. The contract is set aside for 8(a) small businesses and has a NAICS code of 238910. The contractor must survey any facilities not previously assessed for hazardous materials and will provide archaeological monitoring as required. The contractor will also be responsible for utility disconnections and cutting/capping lines. Pricing should be fully burdened across CLINs for substructure demolition, pavement removal and utility demolition.
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Company | RFI # | Date of Request | Building #: | RFI Subject: | Potential Cost Impact | Potential Schedule Impact | Question: | Contracting Response | |
| Ahtna | 0001 | 1/29/21 | 119, 120, 121, & 128 | Location of Structure | No | No | These buildings do not show on the map. Please update map or provide a map with the location of these structues. | Added to "Appendix Q - Info for RFIs" | |
| Ahtna | 0002 | 1/29/21 | 214 | Contaminated Soil Removal | Yes | No | The abatement survey indictes contaminated soil around the structure. The survey says to stockpile the soil on site but does not provide a quantity. The scope of work appears to require the material to be disposed of off site at an approved landfill. The Is the contractor responsible for offsite disposal of contaminated soil identified in the report? If so, what is the quantity of material to be removed from the site or stockpiled on site? | Per Section 2.2.1.o of the PWS, excess soil remaining after demo that cannot be used to fill in cuts within site need to be removed and disposed of properly off base. You should not be taking direction on disposal from the surveys, all directions are in the PWS. Quantity of cut can be determined using foundation plans. | |
| Ahtna | 0003 | 1/29/21 | 214 | Parking Lot Removal | Yes | No | The statement of work requires the contractor to clear the area outlined in the aerial map in Appendix B. There are no dimensions for the areas to be cleared in the aerial map. The contract requires removal of the building foundation and the utilities within 10' of the builing footprint. Does this 10' area outside the building footprint include removal of all asphalt or only the asphalt required for removal of the utilities? How is the contracotor to determine the area of pavement removal shown on the map in appendix B if there are no dimentsions? Given that the pavement thickness and type of pavement vaires as many of the structures to be | ||
| demolished, the area and thickness of the pavement will impact the total price of the contract. | The 10' outside the building footprint includes asphalt, utilities, and everything else listed under the 2.2 description of work. Essentially after demo is complete there should be a contiguous piece of grass the same size as the building used to be, plus 10 ft on each side. |
The pavement thickness is roughly 3"-4".
| Ahtna | 0004 | 1/29/21 | 214 | Parking Lot Removal | Yes | No | Will the government provide dimension for the areas shown in blue on the map in Appendix B and the thickness of the pavement in each area shown in blue on the map in appendix B? Does the contractor assume the area of pavement to be removed will be 2,200,000 sf of asphalt pavement and do we use the information in Appendix I for pavement thickness? | The map is to scale. The scale is shown in the bottom left. For pavement thickness, type, and condition, refer to Appendix I and newly added "P20-3050 TAFB Pavement Survey Report" and "Zone 4 Geotech" in Appendix Q. |
| Ahtna | 0005 | 1/29/21 | N/A | Recyvled Material | Yes | No | Is there an onsite location for disposal/recycle of asphalt, conrete or steel material from the demoliton of the structeres and parking areas? | There are no onsite locations to stage asphalt or concrete. These must be disposed of properly. Steel/Sheet metal will be recycled per the PWS. |
| Ahtna | 0006 | 1/29/21 | N/A | Abatement Surveys | Yes | No | Appendix A identifies buildings where hazardous material surveys have been conducted. There are a number of structures with no surveys. Does the contractor assume these structures contain no hazardous materials? If not, does the government intend to provide surveys for the structures without surveys? | Contractors are advised not assume no hazardous materials are present. Not all facilities have been surveyed for hazardous materials. The contractor should make reasonable assumptions regarding the presence of potential hazards based on the information provided as well as the information presented during the prebid site visit. Buildings which have not been surveyed for hazardous materials must be surveyed as before abatement as part of the contract. |
| Ahtna | 0007 | 1/29/21 | 156 | Concrete Pavement Demolition | Yes | No | The map in appendix B shows an area adjacant to building 156 (Hangar 3) to be demolished to support a future MILCON. This are a is concrete. Clin 0004 calls for a fixed price for removal of NTE 2.2 million sq ft. It also requests a unit price per square foot. There is no distinction between asphalt pavement and concrete pavement. What is the thickness of the concrete pavement adjacant to building 156? Is the concrete reinforced? What is the area of the concrete to be removed? | Appendix I shall be used to determine pavement type and thickness, as stated in the PWS section 2.2. Area can be determined using the scale in the bottom left of the map. Government will consider a difference in asphalt vs concrete CLINS. |
Refer to Appendix Q: TAFB Pavement Survey Report and Zone 4 Geotechnical Report for more details.
| Ahtna | 0008 | 1/29/21 | 156 | Pavement Demolition | Yes | No | The map in appendix B shows the parking area to be removed. Part is asphalt and part is concrete. What is the area and thickness of the concrete pavement? What is the thickness and area of asphalt pavement? Is the concrete reinforced? | Appendix I shall be used to determine pavement type, as stated in the PWS section 2.2, as well as two products which were added to Appendix Q: TAFB Pavement Survey Report and Zone 4 Geotechnical Report. |
| Ahtna | 0009 | 1/29/21 | General | Pavement Breakdown | Yes | No | Based on initail review of the contract documents, would the government consider reworking Clin 0004 to provide a breakdown of the 2,200,000 square feet? We recommend separating the quantity of asphalt pavement and concrete pavement into two separate Clins. |
We also recommend the asphalt be subdivided into 2" thick, 4" thick and 6" thick Clins. This would minimize the potential issues associated with different site conditions during construction. We would also recommend the concrete be subdivided into 4", 6", 8", 10" and 12" thick.
| The distance to a disposal site will vary depending on the location of the pavement. Without a volume and location, the cost of disposal of the pavement will be impossible to calculate. Recommend Clins be established for pavement removal at each of the locations identified in the contract. | CLIN 0004 will be divided into two CLINS, one for asphalt and the other for concrete. As a not to exceed CLIN the depths should not matter at this time. | ||||||||
| Ahtna | 0010 | 1/29/21 | General | Updated Map | Yes | No | Many of the structures do not show on Appendix B. Will the government update Appendix B to reflect all the structures identified in Appendix A? | No new maps will be generated however more information is included in Appendix Q. | |
| Ahtna | 0011 | 2/2/21 | General | ACM Piping | Yes | No | Clin 0006, 0007 and 0008 identify a linear feet of utilities to be removed outside the 10' building line. Is there any Asbestos pipe or other hazardous materials associated with removal of these utilities? Based on the information shown, the contractor must assume there are no hazardous material associated with the utility removal. If there is hazardous material, will the government provide a location any type of material along with the quantity to be removed. | The government does not have an inventory of hazardous pipes; this will be addressed after award if pipes are found to contain hazardous materials. | |
| Ahtna | 0012 | 2/2/21 | General | Utility Excavation | Yes | No | Clin 0006, 0007 and 0008 identify a linear feet of utilities to be removed outside the 10' building line. The is no information on the depth of the utilities to be removed or the size of the utility pipes. The contractor does not have sufficient information to determine the quantity of excavation required to remove the utilities. Does the government intend to provide any additonal information on the depth of the exisiting utilites and the size of the pipes? What depth should the contractor assume for the excavation of the utiliites? What volume of material should the contractor assume will be excavated in order to remove the utilites? Will any of there excvation be over 5' deep? | The total CLIN in bid shall be based on an assumed depth of 3 ft for all lines other than sewer which will be assumed that 50% of the lines are at 3 ft and 50% of the lines are at 6 ft. Industry standards for line widths shall be used. | |
| Ahtna | 0013 | 2/2/21 | General | Utility Obstructions | Yes | No | Clin 0006, 0007 and 0008 identify a linear feet of utilities to be removed outside the 10' building line. Are there any underground obstructions not identifed in the contract drawings that will impact the removal of the underground utilities? | At this time no known undergraound obstructions exsist. Howeover, any that are found during the removal of the utilities wil be addressed at that time. | |
| Ahtna | 0014 | 2/2/21 | General | Utilities Under Pavement | Yes | No | Clin 0006, 0007 and 0008 identify a linear feet of utilities to be removed outside the 10' building line. Are there these utilities under pavement that is not shown to be removed in the contract drawings? If utilities to be removed are under existng pavement not shown to be removed, how does the contractor bid the removal and replacement of this pavement? | Refer to Appendix C and D for utility lines being removed. For utilities being removed where ashphalt or concrete remains the contractor is required to restor the area to its previous condition. | |
| Ahtna | 0015 | 2/2/21 | General | Hazardous Abatement | Yes | No | The solicitation identifies structures that do not have a hazardous material survey. The solicitation requires the contractor to provide surveys for these structures and abate any hazardous materials found. How does the contractor bid abatement when the quantities of hazardous materials are not known? Will a mod to the contract be issued to reimburse the contractor for removal of any hazardous materials found a a result of the survey of the structures? | Of the facilities marked as 'not surveyed' in Column G of Appendix A, the following will require the contractor to price in a hazmat survey into their bid: 120, 312, 1034, 1261, 1726, 3031, 6003, 8200, 9371, and 9424. These are the buildings which the FDEP considers 'facilities' and will require 10 day notifications as described in the PWS, EA, and 813s. 373, 7027, 7029, 7030, 7031, 42260, and 42275 only require sampling if ctr intends to recycle or reuse the concrete. 1022, 9419, and 22280 will require full TCLPs for their haz waste determinations. | |
| All Phase | 0001 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Can we dual/triple hat any of the onsite personnel? | No. See PWS section 4.1. | |
| All Phase | 0002 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Is there fill material available onsite? If available, is there a charge for it? | Fill material is not available on-site. The contractor is required to source clean fill from off-site. | |
| All Phase | 0003 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Is there a base landfill available for this project? If available, is there any fees for using it? | Tyndall AFB does not have a landfill. All materials must be disposed of off base. | |
| All Phase | 0004 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Are the utilities privatized? Are there any fees for the disconnection? | The water, electric and natural gas infrastructure on Tyndall AFB is privatized, review Section 9 of the PWS for further details. | |
| All Phase | 0005 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Could we get a site map of where the facility are located? Also could we get a haul route to get in and out of the Base to the | ||
| site? | Appendix B is the Site Map available. Specific haul routes are not required except for buildings very close to the flightline where activities will require a flightline waiver; that approved waiver with haul will be provided after award. | ||||||||
| All Phase | 0006 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Is water available at each location within 50 feet? | Hydrant Map provided in Appendix Q | |
| All Phase | 0007 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Please provide confirmation as to whether metals and machinery can be salvaged or if the installation is retaining these. | In accordance with PWS page 3, paragraph four; at this time the government cannot confirm what can be salvaged and what cannot, government will retain facility until it is turned over to the contractor, and all facilities will be turned over at different times. Regarding metals, see PWS section 4.3 | |
| All Phase | 0008 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: If the installation retains the salvage rights, is the contractor required to haul the salvageable items to the Base's yard, or will multiple containers be furnished? | Contractor shall not be required to relocate items government wishes to salvage, all will be removed prior. The only exception may be E waste, see section 2.2.1.c. The CFP will provide direction. | |
| All Phase | 0009 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: If the installation retains the salvage rights, what is the size of the items? | Installation will not require contractor to salvage items on base behalf. | |
| All Phase | 0010 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Are there any specific guidelines that include the handling of C&D and ACM waste? | See PWS sections 2.2.1, and 2.5 through 2.8. | |
| All Phase | 0011 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Will contractor have to perform environmental monitoring during asbestos abatement as per US Army Corps of Engineers Manual EM 385-1-1 (Section 06.B.05, Page 92) as well as Federal, State, and Local requirements? Or will Tyndall perform it? | Contractor shall abide by PWS section 2.3. | |
| All Phase | 0012 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Is there any UXO or any other special hazardous compliance requirements (CERLA, LBP, PCB, etc.)? | See PWS sections 2.5 through 2.8. | |
| All Phase | 0013 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Can concrete be used for backfill? | Crushed concrete can be used to restore sites on the top layer where specified, but it cannot be used to fill in the foundation. | |
| All Phase | 0014 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Can concrete be crushed onsite? | Concrete may be cruched on site for immediate disposal. At this time, crushed concrete may not be stockpiled on site. However, the government is working on a seperate contract that may change permit cruched concrete to remain on base. | |
| All Phase | 0015 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: If crushed concrete can be used for backfill, are there analytical requirements prior to use as backfill? | Crushed concrete can be used to restore sites on the top layer where specified, but it cannot be used to fill in the foundation. See PWS for specifications on backfill. | |
| All Phase | 0016 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Are there any constraints in recycling of painted concrete? | If the paint is lead based, the contractor must abide by PWS section 2.3. All concrete that will be recycled must be certified clean, either by using the surveys we've already conducted or surveys the contractor conducts. | |
| All Phase | 0017 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Do all onsite personnel need to be US Citizens? | No, however all onsite personnel will be required to complete a background check through the SFS approval process. | |
| All Phase | 0018 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Is it the intention of the Base to stabilize the disturbed areas with grass or gravel? If grass, what is the required grass mix for this project? | see PWS section 2.2.1.q. | |
| All Phase | 0019 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Where will the contractor's laydown/trailer area be located? Are there utilities available in this area? Water, electric, sewer? Please provide a map view of the laydown area. | The government has not designated a contractor trailer site and does not require one; if the contractor wishes to have one, they must formally request it following award. With the extensive amount of work taking place at Tyndall there is no guarantee that an area for a trailer will be available. | |
| All Phase | 0020 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Will utilities (i.e. water, electric) be provided by the Army or will the contractor have to pay? | Contractor shall issue a formal request for a laydown and trailer area post award; utility availability will be determined at that time. There is no guarantee that space and utilities will be provided. Water for the 'wet method' of demo is accessible, and at no cost to the gov't, via the base hydrants. | |
| All Phase | 0021 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Will backflow prevention devices be required at sources of water? | Yes, backflow prevention devices will be required in accordance with state regulation | |
| All Phase | 0022 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Please provide clarification on the topsoil requirement and area grading. Given the shallow footprint of some slabs on grade confirm that over-excavation will not be required to place 4 inches of topsoil. Confirm that topsoil is meant to be materials similar to the surrounding area. | See Section 2.2.1.q of the PWS. Contractor will not be required to raise up grade to where slab existed, ccontractor shall grade to surrounding area. | |
| All Phase | 0023 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: What are the access/badging requirements for contractor/subcontractor truck drivers? | All contractor personnel will have to submit to background checks prior to be provided access badges. | |
| All Phase | 0024 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Please provide a comprehensive map showing the location of all buildings to be included in the work? | Appendix B is the comprehensive map available. | |
| All Phase | 0025 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Are we removing all the foundation/slab in its entirety? Or we going down to a certain depth? | See PWS section 2.2.1.g; the entire extent of the foundation will require removal | |
| All Phase | 0026 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Is the contractor responsible for submitting the SWPPP and plans? | See PWS section 2.2.3 | |
| All Phase | 0027 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: How far should the utility disconnects be performed? | See PWS section 2.2; on the first effort the utilities shall be removed to 10 ft outside the footprint; on the third effort, back to their points of disconnection. | |
| All Phase | 0028 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Are there any ancillary structures that have to be demolished along with structures listed in the SOW? | See PWS section 2.2.1.i through k. | |
| All Phase | 0029 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Are there any Asbestos or other hazardous materials that are unaccounted for? | Anything not accounted for in the facilities listed in Appendix A as surveyed or facilities which have not been surveyed and will require survey as part of the contractor's price are unknown. | |
| All Phase | 0030 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Is there any Friable ACM that needs immediate removal? | It is the contractor's responsibility to determine this based on the surveys provided. | |
| All Phase | 0031 | 2/4/21 | N/A | N/A | Left Blank | Left Blank | ISSUE: Will missing Surveys be provided? | Any facilities which are labelled 'surveyed' in Appendix A have been provided in the original Appendix or Appendix Q, which consists of information requested in these RFIs. Any facilities which are not labelled as surveyed must be accomplished by the contractor. | |
| Brad Cole Site Services | 0001 | 2/3/21 | Left Blank | Permits | Yes | Yes | In section 2.1.1 Permits and Codes, it states that contractor is |
responsible for federal, state, local and environmental permits and associated costs. If, after verification, they are required, the procurement of these permits can take time to obtain. Will the
| allowable 270 days start from receipt of approved permits? | The period of performance will begin when the notice to proceed is issued. Any delays in obtaining the Permits and Codes may be addressed after award. | ||||||||
| Brad Cole Site Services | 0002 | 2/3/21 | Left Blank | Engineering Surveys | Yes | Yes | In section 2.1.1 Permits and Codes, it states that Engineering Surveys per 1926.850(a) shall be required. Were there engineering surveys completed prior to hazardous material investigations for the reports in appendix H? If so, can they utilized for determining if a building is safe to abate or will the contractor have to complete new surveys for each structure. In addition, the code states, a competent person, shall complete surveys. Please provide what requirements and or credentials the Govt will expect from the competent person completing the surveys. | No, the OSHA survey referenced is the contractor's responsibility to complete prior to demo at each site, the specs can be researched in the code referenced, but it is essentially a report of working conditions before the contractor sends their employees into the site. | |
| Brad Cole Site Services | 0003 | 2/3/21 | Left Blank | Building Existing Conditions | Yes | Yes | In section 2.2.3 (Asbestos Containing Material (ACM) and Lead Based Paints (LBP) Debris) of the Performance Work Statement Document it states that “All facilities will be abated if possible (safe to enter) by the contractor.” At the site visit, it appeared that many of the buildings to be demolished were severely damaged and not structurally sound to safely abate the buildings prior to demolition. For bid | ||
| purposes, can the Govt denoted which structure currently is safe to abate and which is not safe to abate to price demolition work accordingly? | The medical group has not determined that any of the facilities are safe to abate/enter for government/military personnel, but almost all facilities demolished thus far have been determined safe to abate/enter by the ctr. It will be ctr responsibility to determine which facilities they will allow their employees to abate. | ||||||||
| Brad Cole Site Services | 0004 | 2/3/21 | Left Blank | Crushing on site | Yes | Yes | If deemed clean of asbestos/lead, will on site crushing/ grading be allowed for demolished foundation concrete, sidewalks, CMU walls, misc. concrete pavement, etc. prior to hauling to approved recycle/disposal site? | If the crushing and stockpiling can be done within the demo footprint and the adjacent laydown area, then on-site crushing/grading can be considered, subject to government approval. There is not a separate site on base where contractor can crush. | |
| Brad Cole Site Services | 0005 | 2/3/21 | Left Blank | Govt Salvaged Items | Yes | Yes | In section 2.2 Description of work in the PWS its states that “bids shall not include equipment found at site visit for salvage as Govt property will be removed up until the date of demolition.” Does the Govt have a list of salvaged items that will be removed from each building prior to demolition activities? | The government is unable to provide a list of salvaged items, the contractor must infer that nothing will be available for salvage as base personnel will remove items up until the day of demo. | |
| Brad Cole Site Services | 0006 | 2/3/21 | Left Blank | Missing Surveys | Yes | Yes | In section 2.2 Description of work in the PWS its states that “if surveys are not included, contractor shall ask about missing information on the RFIs during solicitation.” Please provide the missing reports if available.? | Any facilities which are labelled 'surveyed' in Appendix A have been provided in the original Appendix or Appendix Q, which consists of information requested in these RFIs. Any facilities which are not labelled as surveyed must be accomplished by the contractor. | |
| Brad Cole Site Services | 0007 | 2/3/21 | Left Blank | Missing Surveys | Yes | Yes | In section 2.2 Description of work in the PWS its states that for the first effort substructure demolition that all foundations and utilities are to be removed within 10’ of the footprint. Please confirm that these demolished items are to be included in the lump sum substructure bid item for the structure and not the CLIN 0004 – CLIN 0008 bid items. | Correct, confirmed. | |
| Brad Cole Site Services | 0008 | 2/3/21 | Left Blank | Allowable Days | Yes | Yes | This project requirement consists of 120 structures that are to be demolished in 270 days per the solicitation. The PWS states that every site will require 10 day notification in advance of demolition of all structures; additionally there are to be three separate efforts or mobilizations as directed in the PWS. Assuming that the |
abatement and structural demolition for each structure could be accomplished in 5 days average, with the second and third efforts accomplished in 2 days each would result in a minimum of 9 days per site excluding the 10 day notification all to be accomplished within the 270 days which is not realistic given the size of some of the structures. Additionally, the PWS confirms "At times, multiple crews may be required to meet this schedule, but Government can confirm that there will not be two ‘sites to be cleared’ at the same time: the multiple crews would just result from the infrequent simultaneous need of building and pavement demolition.
"Is it the governments intention to require that all notifications, execution of the three core efforts: (1) Structural demolition of facilities and their supporting foundation and infrastructure,(2) Clearing of asphalt or concrete pavement and other non-earth materials within future MILCON sites, and (3) Demolition of
| abandoned utilities, and final disposal of all demolition debris be completed in 270 days after which liquidated damages would be assessed per the solicitation? | The contractor is permitted to notifiy intent to start demolishion of multiple sites as a part of a single notification. Addtionally, the contractor does have the ability to work multiple sites simultaneously provided that the contractor has sufficient oversight. A revision to the PoP is being considered. | ||||||||
| Brad Cole Site Services | 0009 | 2/3/21 | Left Blank | As-Built Drawings | Yes | Yes | Are structural as-built drawings available for all or some of the structures to be removed. | Appendix F contains all drawing available. Unfortuantely, this base is very old and a lot of records were destroyed in the hurricane | |
| Brad Cole Site Services | 0010 | 2/3/21 | Left Blank | Temporary Disposal Sites | Yes | Yes | Is it possible for one or more demolition debris temporary disposal / reduction sites be established on base to sort materials for recycling, reduction, and final disposal? | A temporary disposal/reduction site may be established adjacent to the active demolition site after receiving government approval. | |
| Brad Cole Site Services | 0011 | 2/3/21 | Left Blank | Unforseen Subsurface Structures | Yes | Yes | If unidentified or unforseen subsurface structures are discovered, what will be the parameters for removal and payment? For example, the Officers Club is a large CMU and concrete structure that was built on waterfront property that likely has driven piles connected to its foundation, absent as-built drawings this would be a significant differing and unforseen condition not included in the scope of work. | Appendix F contains all drawing available. For subsurfaces where there are no as builts contractors should bid on a reasonable foundation depth based on the type of structure it is supporting. Unusual conditions would be addressed after award. | |
| Brad Cole Site Services | 0012 | 2/3/21 | Left Blank | Debris Hauling | Yes | Yes | Given the magnitude of trucking of demolition debris to final disposal sites will any consideration be given for vetted haulers making trips on and off base or should non-productive truck costs be included in the bid price proposal? | Contractor personnel will be required to submit to background checks. Once background checks have been complete those members will have access to the job sites as directed by the contractor. This will include haulers. | |
| Brad Cole Site Services | 0013 | 2/3/21 | Left Blank | Waterfront Buildings Demo | Yes | Yes | At the two waterfront buildings shown on the site visit, are there any structures (docks, piles, decks, etc.) that need to be included in the demolition of the primary structure? | All items referenced in Appendix O shall be removed at the golf course. No docks or piles will be removed. |
| Brad Cole Site Services | 0014 | 2/3/21 | Left Blank | Contaminated Soil | Yes | Yes | During the course of demolition if non-suitable soils are encountered please specify civil specifications required for removal, disposal, and importation of compactible, suitable fill.. | See PWS sections 2.2.1, and 2.5 through 2.8. |
| Brad Cole Site Services | 0015 | 2/3/21 | Left Blank | Utilities within 10' of Buildings | Yes | Yes | If there is either electrical or communications conduits or duct banks within the building footprint, would we sever at the ten foot mark (after first disconnecting from the source) for the first phase of demolition? | Correct, conduits or duct banks will be severed at the ten four mark for the first phase of demolition |
| Brad Cole Site Services | 0016 | 2/3/21 | Left Blank | Lightening Policy | Yes | Yes | What is the Base policy for lightening safety stand downs? | Contractors shall follow an Emergency Action Plan (EAP) developed by the contractor, as outlined in 29 CFR 1910.38 or 29 CFR 1926.35. Base weather warnings are broadcast throughout. |
| Brad Cole Site Services | 0017 | 2/3/21 | Left Blank | Haz Material Disposal | Yes | Yes | Soil Borings- for the sites/borings that have been identified as above the thresholds. If, after excavation and the additional recommended sampling, the material is deemed special or haz waste, will disposal be by the base or the contractor? | The contractor will be required to appropriately dispose of all hazardous waste; see section 2.2.1.o and 2.5 through 2.9 of the PWS |
| Brad Cole Site Services | 0018 | 2/3/21 | Left Blank | Existing Transformer Ownership | Yes | Yes | It is our understanding that the utility co-op owns the transformers on the base, if so will they retain possession of these transformers or will the contractor need to include the testing and disposal of these items? | The contractor shall not be required to remove any transformers. |
| Brad Cole Site Services | 0019 | 2/3/21 | Left Blank | CO-OP Disconnects | Yes | Yes | Co-op- Does the base have a specific agreement with the co-op regarding the utility disconnect pricing? If so can this pricing be made public? | A Not To Exceed CLIN has been added in the amount of $500,000.00 to account for all utility disconnection services provided by the utilitiy companies. GCEC will cut and cap all know water mains serving each facility and open and inspect each transformer for the contractor to disconnect secondary service. Please note that this is solely an estimate and is subject to change upon final award. Also note that this price is subject to change if additional mains and/or transformer services are discovered during demolition. |
| Brad Cole Site Services | 0020 | 2/3/21 | Left Blank | SWPPP | Yes | Yes | Will a site wide Stormwater Pollution Prevention Plan (SWPPP) be required or will a Construction Generic Permit (CGP)/Notice of Intent (NOI) be submitted for each individual building/site? | If any demo's are large enough and within the same area enough to trigger one acre of disturbance, an NOI is required. Otherwsie, a SWPPP is required at each building. |
| Brad Cole Site Services | 0021 | 2/3/21 | Left Blank | Building Slab | Yes | Yes | Attachment 1 Superstructure/Substructure. Please clarify what pricing section the building slabs will fall under? | Substructure |
| Brad Cole Site Services | 0022 | 2/3/21 | Left Blank | Site Restoration | Yes | Yes | Site Restoration. Are the 900,000+ Sf of building areas to be demolished included in the 2.2 MIL SF of paving removal for turf/sod establishment or will the overall restoration area be 3.1 MIL SF? | The restoration of each building site should be included under each building CLIN under substructure. |
| Brad Cole Site Services | 0023 | 2/3/21 | Left Blank | Testing Requirements | Yes | Yes | A)Are there any engineering requirements associated with this project? |
And if so please provide the specifications.
B)Are there any surveying requirements associated with this project?
And if so please provide the specifications.
| C)What if any are the testing requirements for this project? And if so please specify. | See PWS for all required documentation. | ||||||||
| Brad Cole Site Services | 0024 | 2/3/21 | Left Blank | Testing Requirements | Yes | Yes | Can work be performed during non-standard hours? | Contractors should plan accordingly to complete work within standard hours. Alternative work times and weekend work requests can be made when needed but will require government approval. | |
| Brad Cole Site Services | 0025 | 2/3/21 | Left Blank | Supervision | Yes | Yes | Can a single triple hatted superintendent personnel provide field supervision for this project? If not please specify the level of field supervision required. | A single triple hatted superintendent cannot provide field supervision, see Section 4.1 of the PWS for details. | |
| Brice Builders | 0001 | 2/1/21 | 546 | Building Sequence | Yes | Yes | The period of performance is 270 calendar days but Building 546 is shown as not being available until September 1, 2022. Even allowing for a reasonable time for award, this start date for Building 546 is beyond the period of performance. | ||
| Please advise if Building 546 will be included in this project, if the period of performance will be altered or if some other solution is to be implemented. | A revised PoP is addressed in Amendment 2. | ||||||||
| Brice Builders | 0002 | 2/1/21 | All | Building Sequence | Yes | Yes | The period of performance is 270 calendar days. There are 122 facilities or structures to be demolished along with 125,000 lf of abandoned utilities and 2,200,000 sf of pavement. |
The PWS states, on page 3, Section 2.2, Description of Work, "At times multiple crews may be required to meet this schedule, but Government can confirm that there will not be two 'sites to be cleared' at the same time; the multiple crews would just result from the infrequent simultaneous need of building and pavement demolition."
The PWS states, on page 3, Section 2.2, Description of Work, "Facilities will be prioritized and scheduled based on dates provided by the Government.."
| Please provide the priorities and anticipated schedule for bidding purposes. Multiple moves of equipment has a significant cost impact and we need to be able to count those moves and potential multiple work sites. We are also concerned that 270 calendar days allows less than 2 days per site if multiple sites are not anticipated concurrently. (270 calendar days equals less than 200 weekdays unless the government expects a 7 days a week work schedule) | A revised PoP is addressed in Amendment 2. | |||||||
| Brice Builders | 0003 | 2/1/21 | All | Building Sequence | Yes | Yes | The period of performance is 270 calendar days. There are 122 facilities or structures to be demolished along with 125,000 lf of abandoned utilities and 2,200,000 sf of pavement. |
The PWS states, on page 3, Section 2.2, Description of Work, "At times multiple crews may be required to meet this schedule, but Government can confirm that there will not be two 'sites to be cleared' at the same time; the multiple crews would just result from the infrequent simultaneous need of building and pavement demolition."
The PWS states, on page 3, Section 2.2, Description of Work, "Facilities will be prioritized and scheduled based on dates provided by the Government.."
Brice is concerned that 270 calendar days allows less than 2 days per site if multiple sites are not anticipated concurrently. This also does not account for preconstruction submittals and pre-demo surveys.(270 calendar days equals less than 200 weekdays unless the government expects a 7 days a week work schedule)
| Please define the expected work schedule to meet the stated period of performance and the scope of work. | A revised PoP is addressed in Amendment 2. | |||||||
| Brice Builders | 0004 | 2/1/21 | All | Building Sequence | Yes | Yes | No specifications are found in the attachments. Will there be specifications associated with this project? | |
| CSI Divisions 1, 2, 31 and 33, at a minimum, seem appropriate for this project. | CSI divisions are specifically for organizing specifications packages that come with design drawings. This contract does not require a specification package, but all codes and standards mentioned shall be conformed to and referenced in the submittals that are required (ie demo plan, SWPPP, etc). | |||||||
| Brice Builders | 0005 | 2/1/21 | All | Building Sequence | Yes | Yes | This solicitation is issued with Service Act wage determination included. Why is this not a Davis Bacon, Construction project? |
Multiple options are shown in the contract documents for the percentage of self performance required by the contractor. Please provide a definition of which paragraph is applicable, and what the associated percentage of self performance by the contractor, is required.
| Reference 52.219-14 Limitations on Subcontracting (DEVIATION 2020-O0008). | This project has been solicited as a demolition service requirement, therefore we are utilizing a Service Act Wage Determination and the 50% percentage listed in 52.219-14 Limitations on Subcontracting. | ||||||||
| Brice Builders | 0006 | 2/1/21 | All | Piers | Yes | Yes | There are several piers associated with some of the facilities, ie: the Golf Course Club House, Marina, that are identified as needing to be demo'd. Does this include the pilings, and to what extent. Do we cut them off at the water line, sea floor, or remove them completely. | The piers at the golf course will be removed in accordance with Appendix O. There are no piers identified to remove at the marina, only pavement. | |
| Brice Builders | 0007 | 2/4/21 | 8200 | Ordnance Disposal Area | Yes | Yes | On Building/Area 8200, the spreadsheet indicates 3200 square feet of demolition. Based on Google Earth, there is not a building on site, however, we are to retain the rocket structure. Is this area restricted? Do we need permission to go look at it? Are there structure/s there? The Appendix B Map does not show that area. | Details provided in Appendix Q. | |
| Brice Builders | 0008 | 2/4/21 | 9456 | Building | Yes | Yes | On Building 9456 on the Appendix A spreadsheet, the building is listed as "Vehicle | ||
| Maintenance (Propane Tank)". Are we to demo the building or the propane tank or both? | The contractor is required to demo B9456 and all associated items, to include tanks. | ||||||||
| Brice Builders | 0009 | 2/4/21 | 9901, 9911, 9912 | Building Locations | Yes | Yes | On the Appendix A Spreadsheet, Buildings 9901, 9911 and 9912 are listed as being located in Carrabelle and Apalachicola. Do you have addresses? Drawings? Pictures? | Pictures were included in the picture appendix; no drawings are available. Addresses are the following: - |
9901: 830 Marine St, Carrabelle, FL;
9911/9912 (9912 is the fence around): 9911 Apalachee St, Apalachicola, FL
| Brice Builders | 0010 | 2/4/21 | 22280 | SFS Urban Assault Range | Yes | Yes | On the 22280 SFS Urban Assault Trainign Range on Boy Scout Road, the Appendix A | ||
| spreadsheet says that there will be "specific demo requirements". According to the email chain from Appendix P, the Users want some items left. Can you provide guidance on what will be left, what will be demo'd/removed? | Scrolling down past the email, the user clearly dictates on a map, and then in pictures, what facilites need to stay and what need to go in Appendix P. | ||||||||
| Brice Builders | 0011 | 2/4/21 | 22280 | 8(a) Set Aside | Yes | Yes | The solicitation is presently set aside for 8(a) entities with a size standard of $16,500,000 and no other restrictions. Will the government consider limiting the participation to regional 8(a) companies with a bona fide office in the region. | Additional restrcitions due to company locations is not being considered. | |
| Bristol | 0001 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | This project requirement consists of 120 structures that are to be demolished in 270 days per the solicitation. The PWS states that every site will require 10 day notification in advance of demolition of all structures; additionally there are to be three separate efforts or mobilizations as directed in the PWS. Assuming that the abatement and structural demolition for each structure could be accomplished in 5 days average, with the second and third efforts accomplished in 2 days each would result in a minimum of 9 days per site excluding the 10 day notification all to be accomplished within the 270 days which is not realistic given the size of some of the structures. Additionally, the PWS confirms "At times, multiple crews may be required to meet this schedule, but Government can confirm that there will not be two ‘sites to be cleared’ at the same time: the multiple crews would just result from the infrequent simultaneous need of building and pavement demolition." Is it the governments intention to require that all notifications, execution of the three core efforts: (1) Structural demolition of facilities and their supporting foundation and infrastructure, (2) Clearing of asphalt or concrete pavement and other non-earth materials within future MILCON sites, and (3) Demolition of abandoned utilities, and final disposal of all demolition debris be completed in 270 days afterwhich liquidated damages would be assessed per the solicitation? | The contractor is permitted to notifiy intent to start demolishion of multiple sites as a part of a single notification. Addtionally, the contractor does have the ability to work multiple sites simultaneously provided that the contractor has sufficient oversight. A revision to the PoP is being considered. | |
| Bristol | 0002 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Are structural as-built drawings available for all or some of the structures to be removed. | Appendix F contains all drawing available. Unfortuantely, this base is very old and a lot of records were destroyed in the hurricane | |
| Bristol | 0003 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Is it possible for one or more demolition debris temporary disposal / reduction sites be established on base to sort materials for recycling, reduction, and final disposal? | A temporary disposal/reduction site may be established adjacent to the active demolition site after receiving government approval. | |
| Bristol | 0004 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | If unidentified or unforseen subsurface structures are discovered what will be the parameters for removal and payment? For example, the Officers Club is a large CMU and concrete structure that was built on waterfront property that likely has driven piles connected to its foundation, absent as-built drawings this would be a significant differing and unforseen condition not included in the scope of work. | Appendix F contains all drawing available. For subsurfaces where there are no as builts contractors should bid on a reasonable foundation depth based on the type of structure it is supporting. Unusual conditions would be addressed after award. | |
| Bristol | 0005 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Given the magnitude of trucking of demolition debris to final disposal sites will any consideration be given for vetted haulers making trips on and off base or should non-productive truck costs be included in the bid price proposal? | Contractor personnel will be required to submit to background checks. Once background checks have been complete those members will have access to the job sites as directed by the contractor. This will include haulers. | |
| Bristol | 0006 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | At the two waterfront buildings shown on the site visit are there any structures (docks, piles, decks, etc.) that need to be included in the demolition of the primary structure? | All items referenced in Appendix O shall be removed at the golf course. No docks or piles will be removed. |
| Bristol | 0007 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Are there any requirements for historical or archeological monitoring or consulting? And if so please provide the specifications. | Requirements for monitoring can be found in section 2.2.4 "Archaeological Monitoring" of the PWS. |
| Bristol | 0008 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Are there any engineering requirements associated with this project? And if so please provide the specifications. | See PWS for all required documentation. |
| Bristol | 0009 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Are there any surveying requirements associated with this project? And if so please provide the specifications. | See PWS for all required documentation. |
| Bristol | 0010 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | What if any are the testing requirements for this project? And if so please specify. | See PWS for all required documentation. |
| Bristol | 0011 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Can work be performed during non-standard hours? | Contractors should plan accordingly to complete work within standard hours. Alternative work times and weekend work requests can be made when needed but will require government approval. |
| Bristol | 0012 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Can a single triple hatted superintendent personnel provide field supervision for this project? If not please specify the level of field supervision required. | A single triple hatted superintendent cannot provide field supervision, see Section 4.1 of the PWS for details. |
| Bristol | 0013 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | During the course of demolition if non-suitable soils are encountered please specify civil specifications required for removal, disposal, and importation of compactible, suitable fill. | See PWS sections 2.2.1, and 2.5 through 2.8. |
| Bristol | 0014 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | If there is either electrical or communications conduits or duct banks would we sever at the ten foot mark (after first disconnecting from the source) for the first phase of demolition? | Correct, conduits or duct banks will be severed at the ten foot mark for the first phase of demolition |
| Bristol | 0015 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | What is the Base policy for lightening safety stand downs. | Contractors shall follow an Emergency Action Plan (EAP) developed by the contractor, as outlined in 29 CFR 1910.38 or 29 CFR 1926.35. Base weather warnings are broadcast throughout. |
| Bristol | 0016 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Soil Borings-for the sites/borings that have been identified as above the thresholds. If, after excavation and the additional reccommended sampling, the material is deemed special or haz waste. will disposal be by the base or the contractor? | The contractor will be required to appropriately dispose of all hazardous waste; see section 2.2.1.o and 2.5 through 2.9 of the PWS |
| Bristol | 0017 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | It is our understanding that the utility co-op owns the transformers on the base, if so will they retain possession of these transformers or will the contractor need to include the testing and disposal of these items? | The contractor shall not be required to remove any transformers. |
| Bristol | 0018 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Co-op-does the base have a specific agreement with the co-op regarding the utility disconnect pricing. If so can this pricing be made public? | A Not To Exceed CLIN has been added in the amount of $500,000.00 to account for all utility disconnection services provided by the utilitiy companies. GCEC will cut and cap all know water mains serving each facility and open and inspect each transformer for the contractor to disconnect secondary service. Please note that this is solely an estimate and is subject to change upon final award. Also note that this price is subject to change if additional mains and/or transformer services are discovered during demolition. |
| Bristol | 0019 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Will a site wide Stormwater Pollution Prevention Plan (SWPPP) be required or will a Construction Generic Permit (CGP)/Notice of Intent (NOI) be submitted for each individual building/site? | If any demo's are large enough and within the same area enough to trigger one acre of disturbance, an NOI is required. Otherwsie, a SWPPP is required at each building. |
| Bristol | 0020 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Attachment 1 Superstructure/Substructure. What section will the building slabs fall under? | Substructure |
| Bristol | 0021 | 2/4/21 | N/A | No subject provided | RFI form not used | RFI form not used | Site Restoration. Are the 900,000+ Sf of building areas to be demolished included in the 2.2 MIL SF of paving removal for turf/sod establishment or will the overall restoration area be 3.1 MIL SF? | The restoration of each building site should be included under each building CLIN under substructure. |
| Cherokee-Federal | 0001 | 2/4/21 | N/A | Solicitation RFI - Contract Inquiry | Yes | Yes | A. The NAICS code for this project, as listed in the solicitation, is 238910 (Site Preparation Contractors). However, Section 3.0 of the PWS (pgs. 12 and 13) references a "Services Summary," where "The contract service requirements are summarized in performance objectives that relate directly to mission essential items...The Services Summary (SS) and the contractor's Quality Control Plan |
provide information on contract requirements, the expected level of contractor performance and the expected method of government validation and confirmation of services provided." Please confirm that Demolition of Facilities Phase VIII at Tyndall AFB, FL is a contract for construction, and not a contract for services as defined by 13 CFR 125.6.
B. Please confirm that this is a construction contract governed by the Davis Bacon Act, and if so, please provide the Davis Bacon wage determination for the appropriate jobsite (removing WD No. 2015-4559 from this contract as it is not applicable to construction work). Please include the applicable Davis Bacon clauses, removing 52.222-41 Service Contract Labor Standards (Aug 2018).
C. Please remove DFAR…