Appendix A Phase 8 Notes Per Bldg 24Feb21.xlsx
XLSX spreadsheet 21 KB Posted
- Attached to
- FA481921B0003 - Tyndall AFB - Demolition Phase 8 Federal contract opportunity
- Solicitation number
- FA481921B0003
About this file
This document contains details for a federal solicitation for demolition services at Tyndall Air Force Base. The solicitation is set aside for 8(a) small businesses and seeks bids for the demolition of 48 buildings in Phase 8 of the base reconstruction project. Bids are due by February 23, 2021 and must include pricing on the Demo Phase 8 Pricing Sheet attachment. The work includes demolishing structures across the flightline, ammunitions, and subscale drone areas of the base and backfilling with grass. The Air Force plans to award a contract by March 2021 for work to be completed between September 2021 and January 2022.
View the file
Other files for this federal contract opportunity
Show all 36
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reduced Appendix A
| Bldg | Name | Location | Map Location | Estimated SF | Year Built | Surveyed? | (PMO) Status | MilCon Overlap | Zone | Occupancy | Temp Solution | Demo No Earlier Than | Clear Site Goal | MilCon NTP Issued_Last Possible Day | Restore to? | Notes/Also Take Out? |
| 212 | REC PAVILION | Flightline | FL East | 462 | yes | MP DEMO | OSS | 2- Flightline Ops | used | will move with FS. Dates conflict - temp move difficult and MILCON dates flexing, further clarity post award | 15-Aug-21 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | ||
| 214 | Fire Station #1 | Flightline | FL East | 19299 | 1965 | yes | MP DEMO | OSS | 2- Flightline Ops | occupied; generator; tank | moving to 335 with sprungs and trailers | 15-Aug-21 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | tank; remnants of tower mounted to south side and its small remaining foundation below grade; pavilion (B212), dates in conflict - more info to come |
| 216 | RAPCON / AIRFLD | Flightline | FL East | 11567 | 1980 | yes | HARD | OSS | 2- Flightline Ops | occupied; generator; tank. fiber in foundations of bldgs nearby | occupants in 1285 | 1-Jul-20 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | tank |
| 217 | OSS ADMIN | Flightline | FL East | 1412 | 1961 | yes | HARD | OSS | 2- Flightline Ops | comm needs to cut/pull back cables | N/A | 1-Jul-20 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 219 | COMMAND POST/OG AND OSS SQUADRON | Flightline | FL East | 22893 | 1963 | yes | HARD | OSS | 2- Flightline Ops | ITN; generator; EMCS supports 214, too; need to splice out comm lines | ITN moved | 1-Sep-20 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 246 | WEAPONS TRAILER MAINTENANCE | Flightline | FL West | 12056 | 1959 | yes | Future Demo | Infrastructure | 4- Infrastructure | maintenace | sprung at ammo | 15-Apr-21 | 18-Sep-21 | 17-Nov-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 256 | DRONE SUBSCALE MX | Flightline | FL East | 26871 | 1960 | yes | MP DEMO | Infrastructure | 4- Infrastructure | occupied; tank | moving to T256 which are relocating to 258 pad | TBD | TBD | TBD | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | tank; very precise structure removal and limits of slab demo provided |
| 262 | MXS STORAGE | Flightline | FL East | 1040 | 1969 | yes | FDR DEMO | Infrastructure | 4- Infrastructure | some storage | possibly sprung city or flightline | 1-Apr-21 | 18-Sep-21 | 17-Nov-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 266 | BASE SUPPLY | Flightline | FL East | 135247 | 1998 | yes | MP DEMO | Spc Purp Veh Maint | 2- Flightline Ops | storage and retrieval; comm needs to splice out comm lines for adj trailer | assets picked up | 1-Jul-20 | 18-Mar-21 | 17-May-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | loading dock in rear |
| 273 | FIRE SUPPRESSION PUMPHOUSE for 290, 295 | Flightline | FL East | 3300 | 2004 | yes | MP DEMO | OSS Parking Lot | 2- Flightline Ops | used; generator; many tanks, support 290 too | dates in flux - will remain until F-22's leave | 1-Oct-21 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 274 | DRONE MAINTENANCE | Flightline | FL East | 6532 | 2004 | yes | Future Demo | Infrastructure | 4- Infrastructure | occupied | temps at 9700 area | 1-Sep-21 | 18-Sep-21 | 17-Nov-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | infrastructure dates more flexible - awaiting full project schedule |
| 275 | 250K WATER STORAGE SUPPORTING B273 | Flightline | FL East | 1500 | 2004 | yes | MP DEMO | OSS Parking Lot | 2- Flightline Ops | using | dates in flux - will remain until F-22's leave | 1-Oct-21 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 276 | 250K GA WATER TANK SUPPORTING B273 | Flightline | FL East | 1500 | 2004 | yes | MP DEMO | OSS Parking Lot | 2- Flightline Ops | using | dates in flux - will remain until F-22's leave | 1-Oct-21 | 13-Nov-21 | 12-Jan-22 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 312 | AFFF SUPPORT BLDG FOR 316 | Flightline | FL East | 240 | 2001 | need | HARD | none | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | guidelines for disposing of AFFF must be abided by | ||||||
| 333 | VERTICAL ACFT EXTERNAL TANK STORAGE | Flightline | FL East | 11700 | 2004 | yes | Future Demo | Infrastructure | 4- Infrastructure | tank cataloguing | tanks shipped out | 1-Dec-20 | 18-Sep-21 | 17-Nov-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | infrastructure dates more flexible - awaiting full project schedule |
| 370 | DEPLOYMENT PROCESING CENTER | Flightline | FL East | 11100 | 1994 | yes | MP DEMO | Infrastructure | 4- Infrastructure | none | N/A | 1-Jul-20 | 18-Sep-21 | 17-Nov-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | infrastructure dates more flexible - awaiting full project schedule |
| 373 | LRS RAMP - TRUCK SCALE | Flightline | FL East | 2200 | 1943 | only need it if you want to recycle or reuse | MP DEMO | Infrastructure | 4- Infrastructure | Used | buying ramp | 1-Jul-21 | 18-Sep-21 | 17-Nov-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | infrastructure dates more flexible - awaiting full project schedule; includes weighing equipment encased in concrete |
| 546 | FLT SIM PHYSI AND COOLING TOWER (44403) | Flightline | FL West | 23917 | 1955 | yes | HARD | Infrastructure (NW corner) | 4- Infrastructure | E half occupied, mission criticial, cannot be demo'd until new FSRM complete | FSRM project complete | 1-Sep-22 | 18-Sep-21 | 17-Nov-21 | SW or SP backfill with Bahia (Pensacola or Argentine for flightline side) grass established | |
| 6002 | LATRINE 6000 AREA REC SITE | Flightline | FL 6000 | 393 | 1993 | yes | MP DEMO | none | N/A | SW or SP backfill with Bahia grass established | must abide by SHPO | |||||
| 6003 | PAVILION AT 6000 AREA | 6000 Area | 500 | 1993 | need | HARD | SW or SP backfill with Bahia grass established | must abide by SHPO | ||||||||
| 6006 | EXERCISE COMMAND CENTER | Flightline | FL 6000 | 528 | 1996 | yes | MP DEMO | none | N/A | SW or SP backfill with Bahia grass established | ||||||
| 6028 | SHOP | Flightline | FL 6000 | 1020 | 1945 | yes | HARD | none | N/A | SW or SP backfill with Bahia grass established | ||||||
| 6030 | GROUND MX SHOP | Flightline | FL 6000 | 4000 | 1962 | yes | HARD | CE Maint Shop | 5- Industrial | none | N/A | 1-Jan-21 | 11-May-21 | 10-Jul-21 | SW or SP backfill with Bahia grass established | |
| 6060 | SABER CONTRACTOR STORAGE | Flightline | FL 6000 | 6360 | 1992 | yes | HARD | none | N/A | SW or SP backfill with Bahia grass established | ||||||
| 6067 | CE UTILITIES | Flightline | FL 6000 | 1500 | 1991 | yes | HARD | need to reroute comm to 6056/6070 | N/A | SW or SP backfill with Bahia grass established | ||||||
| 7027 | STORAGE | Ammo | Ammo | 5000 | 1988 | only need it if you want to recycle or reuse | MP DEMO | 7000 Area | 7- MSA | only slab remains | 1-Sep-20 | 21-Apr-21 | 20-Jun-21 | SW or SP backfill with Bahia grass established | ||
| 7029 | MUNITIONS STORAGE | Ammo | Ammo | 5000 | 1985 | only need it if you want to recycle or reuse | MP DEMO | 7000 Area | 7- MSA | only slab remains | 1-Sep-20 | 21-Apr-21 | 20-Jun-21 | SW or SP backfill with Bahia grass established | ||
| 7030 | STORAGE | Ammo | Ammo | 5000 | 1983 | only need it if you want to recycle or reuse | MP DEMO | 7000 Area | 7- MSA | only slab remains | 1-Sep-20 | 21-Apr-21 | 20-Jun-21 | SW or SP backfill with Bahia grass established | ||
| 7031 | STORAGE MUNITIONS | Ammo | Ammo | 5000 | 1988 | only need it if you want to recycle or reuse | MP DEMO | 7000 Area | 7- MSA | only slab remains | 1-Sep-20 | 21-Apr-21 | 20-Jun-21 | SW or SP backfill with Bahia grass established | ||
| 7033 | MUNITION ADMIN | Ammo | Ammo | 3220 | 1983 | yes | Future Demo | alarm hub; generator; tank | SW or SP backfill with Bahia grass established | |||||||
| 7040 | SHP MSL AS | Ammo | Ammo | 3200 | 1987 | yes | Future Demo | none | N/A | SW or SP backfill with Bahia grass established | ||||||
| 8522 | SUBSCALE DRONE MX BLDG | Subscale | Subscale | 1695 | 1961 | yes | HARD | only slab and half wall remains | N/A | definitely take out half walls, slab may be desoped |