This document package includes a request for information (RFI) submittal from a contractor and the corresponding federal contract opportunity notice. The RFI submittal contains eleven questions from the contractor regarding requirements for constructing a new Wildland Fire Center at Tyndall Air Force Base. The questions seek clarification on geotechnical data, vehicle access, mechanical system details, and other project specifics. The federal contract opportunity notice is a solicitation set aside for Service-Disabled Veteran-Owned Small Businesses to design and build the Wildland Fire Center. Proposals are due by September 16, 2020. The site visit was held on August 26, 2020 and the pre-proposal question deadline is August 31, 2020. The selected contractor will be responsible for constructing the new facility to house fire suppression equipment and staff.
View the file
Other files for this federal contract opportunity
Show all 25
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
RFI #
Date Requested: Potential Cost Impact: Yes: No:
Potential Schedule Impact:
Date Answered:
Request For Information Contract:
Building :
RFI Subject :
Information Requested:
Goverment Response:
Date
Contracting Officer (CO) Date
Requested by:
Answered by:
Contracting Officer Representative (COR)
ISSUE:
Tile
Paramount Construction Group x No: Yes: x
1. No wall tile in restrooms.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1. All walls are noted as painted gypsum board. Does the Owner require tile at the restroom wet wall locations?
Building: Construct Wildland Fire Center
2020-09-02T16:22:46-0500
JACKSON.STEVAN.F.1151007313
Potential Schedule Impact: Yes: No:
Civil Questions
1. No geotechnical information is available.
2. No topographic survey is available.
3. Various vehicles will access the bays. Vehicle from is generally south to north. Please note that pavement design and/or supply for vehicle access is not in the scope of this project.
4. The two aprons are 20x120 and 20x60.
5. Pavement is not in the scope of this project.
6. Government prefers bioretention basis.
Stevan Jackson
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1. Is geotechnical information available? Looking for boring data, groundwater levels, percolation data, etc. if available.
2. Is a topographic survey available?
3. What type of vehicle will access bays? What is the intended vehicle flow (e.g. enter on south and exit on north)? The DB team needs this info to evaluate vehicle turning radius so that the extent of pavement can be determined.
4. Section 2.1 Construction states “A 20’x120’ apron shall be provided on the entry side of the facility and a 20’x60’ apron shall be included on the opposite side. See attached schematic drawings for general layout.” A 20’x120’ apron is shown on the sketch on both sides of the building. What is the requirement?
5. Does any portion of the existing facility to the east need to be paved to allow for proper access onto the adjacent road to the south?
6. The DB team will need to meet the stormwater requirements per EISA 438 since the facility exceeds 5000 SF which means the 95th percentile rainfall will need to be retained. Does the government have a preference on the type and/or location of the proposed solution (i.e. bioretention basin, dry pond, underground detention, etc) ?
Building: Construct Wildland Fire Center
2020-09-02T15:36:45-0500
JACKSON.STEVAN.F.1151007313
2020-09-08T14:56:17-0500
SANDERS.MELISSA.L.1056026831
Proposal Requirements
No: Yes: x
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: Proposal requirements in Section L and M in solicitation words cut off, could you please send full documentation of each section so contractors know the requirements for submission.
Building: Construct Wildland Fire Center
Text1: - Unable to recreate the issue described when pulling the solicitation or amendment from beta.sam. I will send the documents to the contractor per their request.
Text2: SSgt Cory Bracy
2020-09-09T13:25:20-0500
BRACY.CORY.AUSTIN.1471666773
Mechanical
Yes: No: x
1. Correct
2. Correct
3. There will be no bulk oils or lubricants.
4. No compressed air in this scope.
5. Plumbing requirements are as call out in the scope of work.
6. No floor drains or trench drains.
7. There will be no full time occupants.
8. Natural gas is not available.
9. TRANE is the preferred vendor.
10. No utility meters
11. Yes. N/A
12. Thermostat is prefered.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1. It is assumed that vehicles will not be operating in the maintenance bay except for moving into and out of the bay and that a dedicated vehicle exhaust system is not required. Please confirm.
2. Verify that there are no below slab pits requiring dedicated exhaust in the maintenance bay. That is correct
3. Verify that there are no oils, lubricants, etc. required in the maintenance bay.
4. Verify that there is no requirement for compressed air in the maintenance bay. Not required in this scope
5. The plumbing scope as required in Section 2.1.1 is very limited. It is assumed that the plumbing scope is also to include the restroom domestic water and sanitary sewer services, as well as the break room sink listed in Section 2.1 Please confirm. Please also clarify if additional plumbing fixtures are required not specifically listed in the scope (beyond the minimum plumbing fixtures required by code). Plumbing requirements are as called out in the scope of work.
6. Are floor drains and/or trench drains required in the Maintenance Bay? No
7. What are the anticipated number of full-time occupants within the building? 4-11
8. Is natural gas available on the site? No
9. Is there a preferred heating source for the heating system in the maintenance bay? No
10. Will building utility meters be required for new services?
11. Is it acceptable to locate the HVAC equipment in the Maintenance Bay space? Yes. If not, please clarify the preferred location within the office area. NA
12. Clarify the HVAC systems to be used in the Maintenance Bay. Section 2.1.3 lists an “and/or” option.
Building: Construct Wildland Fire Center
2020-09-02T16:41:44-0500
JACKSON.STEVAN.F.1151007313
Deliverables xParamount Construction Group
The schedule of deliverables remain as stated in scope.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: In attachment 1 scope of work deliverables it calls for 95% final design 50 days after NTP. The contractor and design team both need time to coordinate with metal building fabricator to ensure building can be installed. Due to past experience this seems like a relatively short turn around. We would like to request that 95% final design be extended out to 90 days after NTP.
Building: Construct Wildland Fire Center
2020-09-02T15:51:10-0500
JACKSON.STEVAN.F.1151007313
2020-09-08T14:58:48-0500
SANDERS.MELISSA.L.1056026831
Antenna
1. Antenna installation/support structure design and installation is the responsibility of the contractor's Designer of Record.
2. The communications room location is the responsibility of the contractor's Designer of Record.
Provide an analysis through the submittal process and the government will review.
3. Stub out location and tie in point will be identified by the contractor's Designer of Record. The transformer that will be provided the base privatized utility will be supplied with stub outs.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1) Are they providing the antenna installation/support structure?
a. If not:
i. Do they have a specific antenna that they want/need?
ii. Is it acceptable for the antenna to fail at wind speeds from 100 mph to 165 mph?
iii. Will structural help design the support for the antenna to coordinate with?
b. If yes:
i. Are they providing drawings of the antenna support for coordination?
ii. Are they locating the antenna on the building in a particular place for coordination purposes?
2) The floor plans do not show a Comm Room. Is this combined with the electrical room?
3) Communications is to be stubbed out of the building? Where do they want the tie in point for communications to be?
The existing transformer is not within the scope of work. Does it already have stub outs or do we need to go under the transformer pad and provide conduits to the new building?
Building: Construct Wildland Fire Center
2020-09-03T09:18:52-0500
JACKSON.STEVAN.F.1151007313
2020-09-08T14:59:46-0500
SANDERS.MELISSA.L.1056026831
Utilities
1. The private utility provider provides power to the transformer. Location is shown on the site map in Appendix B. The contractor will pro bring power from the transformer to the building.
2. There will need to be utility connections for a refrigerator and and ice dispenser in the break area.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1. Please provide specific definition/locations of the utility take over points. The scope and drawing provided are unclear as to demarcation point between private utility work and Contractor’s expected scope.
2. Will break area require utility connections for Owner provided appliances? i.e. refrigerator, dishwasher, water/ice dispenser?
Building: Construct Wildland Fire Center
2020-09-02T15:58:03-0500
JACKSON.STEVAN.F.1151007313
2020-09-08T15:00:46-0500
SANDERS.MELISSA.L.1056026831
Vehicle Bays
1. NA
2. a. No thickened concrete base. Nothing will be supported from overhead structure.
b. No specialized equipment with unique electrical loads needed. No high voltage connections.
c. No wash down area. No interior slab drainage. No oil separators.
d. No vehicle maintenance pits or hydraulic lifts.
e. These will be provided to the successful bidder for design analysis.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 2. Please provide additional information regarding expected activities and equipment in the vehicle bays:
a. Will Owner provided equipment require any thickened concrete bases? Support from overhead structure?
b. What is the anticipated electrical load of any Owner provided equipment for the vehicle bays? Any high voltage connections required?
c. Is a wash down area required? Interior slab drainage? Oil separators?
d. Will vehicle maintenance pits or hydraulic lifts be required?
e. Types and weights of vehicles utilizing the bays?
Building: Construct Wildland Fire Center
2020-09-02T16:12:37-0500
JACKSON.STEVAN.F.1151007313
2020-09-08T15:01:49-0500
SANDERS.MELISSA.L.1056026831
Doors
1. There are five 12x12 rollup doors.
2. Wood doors are required.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1. The scope of work references (5) 12 x 12 roll up doors. Floor plan drawing would seem to indicate the presence of (6) 12 x 12 doors
2.The scope of work references solid wood stained doors for the interior. Based on scope, it would seem that metal doors would stand up to the anticipated use with less damage over time. Please confirm if wood doors are required.
Building: Construct Wildland Fire Center
2020-09-02T16:14:59-0500
JACKSON.STEVAN.F.1151007313
2020-09-08T15:02:35-0500
SANDERS.MELISSA.L.1056026831
Fire Cache Area
The fire cache is a supply of fire tools and equipment stored for the exclusive use in fire suppression.
The specific code requirement for this space will be identified to the designer of record for the successful bidder.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1. What materials are expected to be stored in the Fire Cache area? Please specify code requirement confirming 1 hour rating is sufficient.
Building: Construct Wildland Fire Center
2020-09-02T16:06:41-0500
JACKSON.STEVAN.F.1151007313
Fire Alarm/Fire Suppression
1. This is correct.
Request For Information: FA481920R0028
Date Requested: 8/31/2020
ISSUE: 1. No fire alarm or fire suppression scope is noted.
Building: Construct Wildland Fire Center
2020-09-02T16:25:00-0500
JACKSON.STEVAN.F.1151007313