This document includes a pricing sheet and solicitation for a federal contract opportunity to repair base boardwalks. The solicitation requests proposals to repair boardwalks at Tyndall Beach and Crooked Island beaches on Tyndall Air Force Base. Interested women-owned small businesses should provide pricing details using the template sheet to repair and replace decking, railings, supporting structures, and related materials. Proposals are due by August 31, 2020. A site visit will be held on August 7, 2020 for interested parties to attend. The work is set aside for women-owned small businesses. The soliciting agency is the Department of the Air Force Air Combat Command. Questions are due by August 14, 2020.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TBBW
| 2.3.1 GENERAL CONDITIONS | SECTION SUB TOTAL | $ - 0 | |||||
| GENERAL CONDITIONS | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | Mobilization/Demobilization | A mobilization cost will be given in order to get the contractor set up on Tyndall AFB. This shall include, but may not be limited to the fees associated in moving equipment, material, and personnel to this area. | JOB | $ - 0 | |||
| 2 | Equipment Rental | All costs associated with equipment rental to accomplish the work. | Month | $ - 0 | |||
| 3 | Superintendence | All costs associated with providing oversite during the performance of on site activities; layout, demolition, construction. | DAY | $ - 0 |
2.3.1 a DESIGN & PROFESSIONAL SERVICES SECTION SUB TOTAL $ - 0
| DESIGN & PROFESSIONAL SERVICES | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | Professional Services | All costs associated with professional services to enable design and construction such as assessments, surveys, permitting, testing, etc | JOB | $ - 0 | |||
| 2 | Design | All costs associated with professional design and construction document creation | JOB | $ - 0 | |||
| 3 | Project Management | All Costs associated with project management | JOB | $ - 0 |
2.3.1 b DEMOLITION SECTION SUB TOTAL $ - 0
| BOARDWALK, PHONE STATIONS, PAVILION (DEMOLITION) | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | Deck (Walking Surface) | Removal of the deck boards and various associated harware. | SF | $ - 0 | |||
| 2 | Railing | Removal of the existing railing | LF | $ - 0 | |||
| 3 | Deck Supporting Structure | Removal of the deck supporting structure and associated harware. | SF | $ - 0 | |||
| 4 | Disposal | Disposal of waste materials | CY | $ - 0 |
2.3.1 c CONSTRUCTION SECTION SUB TOTAL $ - 0
| BOARDWALK, PHONE STATIONS, PAVILION (CONSTRUCTION) | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | PT Piles | Provide and install timber piles | ERROR:#REF! | $ - 0 | |||
| 2 | Supporting Structure | Provide and Install the deck & pavilion supporting structure and associated harware. | SF | $ - 0 | |||
| 3 | Deck (Walking Surface) | Provide and Install precast deck. | SF | $ - 0 | |||
| 4 | Railing | Provide and Install new railing. | LF | $ - 0 | |||
| 5 | Roof | Provide and Install new roof framing & standing seem metal roof. | SQ | $ - 0 | |||
| 6 | Phone Station | Provide and install phone hardware and signage | EA | $ - 0 | |||
| $ - 0 |
PROJECT SUBTOTAL = $ - 0
| OVERHEAD, PROFIT, BOND | SUB TOT: | $ - 0 | |||
| LINE ITEM | DESCRIPTION | % | TOTAL | Notes | |
| 001 | Overhead | Overhead Costs | |||
| 002 | Profit | Profit | |||
| 003 | Bond | Actual Bond |
PROJECT TOTAL ESTIMATE (Overhead, Profit, Bond + Project Subtotal) = $ - 0
| CONTRACTOR PERIOD OF PERFORMANCE = | Days | |
| POP Design = | Days | |
| POP Construction = | Days |
Pricing Schedule &"-,Bold"&20 2.3.1 TASK 1 XLWU 19-8114 Repair Base Boardwalks &"-,Bold"Tyndall Beach Boardwalk, B11300 &"-,Bold"Contractor Name: _______________________________ Date:_______________________________
&"-,Italic"PRICING SCHEDULE TASK 1 &"-,Regular"
T1
| 2.2.4 EQUIPMENT RENTAL ( ITEMIZED LIST ) | SUB TOT | $0.00 | |||
| RENTAL DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | |
| ex. | (Example) 40' Straight Boom Manlift (Sunbelt Rentals) | MONTH | 1 | 2,180.00 | $ 2,180.00 |
| 1 | $ - 0 | ||||
| 2 | $ - 0 | ||||
| 3 | $ - 0 | ||||
| 4 | $ - 0 | ||||
| 5 | $ - 0 | ||||
| 6 | $ - 0 | ||||
| 7 | $ - 0 | ||||
| 8 | $ - 0 | ||||
| 9 | $ - 0 | ||||
| 10 | $ - 0 | ||||
| 11 | $ - 0 | ||||
| 12 | $ - 0 | ||||
| 13 | $ - 0 | ||||
| 14 | $ - 0 | ||||
| 15 | $ - 0 | ||||
| 16 | $ - 0 | ||||
| 17 | $ - 0 | ||||
| 18 | $ - 0 | ||||
| 19 | $ - 0 | ||||
| 20 | $ - 0 |
| OTHER PROJECT NOTES FOR BID | SUB TOT | $ - 0 | |||
| DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | |
| ex. | (Example) 40' Straight Boom Manlift (Sunbelt Rentals) | MONTH | 1 | 2,180.00 | $ 2,180.00 |
| 1 | $ - 0 | ||||
| 2 | $ - 0 | ||||
| 3 | $ - 0 | ||||
| 4 | $ - 0 | ||||
| 5 | $ - 0 | ||||
| 6 | $ - 0 | ||||
| 7 | $ - 0 | ||||
| 8 | $ - 0 | ||||
| 9 | $ - 0 | ||||
| 10 | $ - 0 | ||||
| 11 | $ - 0 | ||||
| 12 | $ - 0 | ||||
| 13 | $ - 0 | ||||
| 14 | $ - 0 | ||||
| 15 | $ - 0 | ||||
| 16 | $ - 0 | ||||
| 17 | $ - 0 | ||||
| 18 | $ - 0 | ||||
| 19 | $ - 0 | ||||
| 20 | $ - 0 |
&"-,Bold"&18PRICING SCHEDULE
2.3.1 TASK 1 &"-,Bold"&16XLWU 19-8114
Repair Base Boardwalks Tyndall Beach Boardwalk, B11300 &16
&14DATE: ______________________________&16
Note: Provide additional pages as needed
PRICING SCHEDULE TASK 1
BID CIBW (ext)
| 2.3.2 GENERAL CONDITIONS | SECTION SUB TOTAL | $ - 0 | |||||
| GENERAL CONDITIONS | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | Mobilization/Demobilization | A mobilization cost will be given in order to get the contractor set up on Tyndall AFB. This shall include, but may not be limited to the fees associated in moving equipment, material, and personnel to this area. | JOB | $ - 0 | |||
| 2 | Equipment Rental | All costs associated with equipment rental to accomplish the work. | Month | $ - 0 | |||
| 3 | Superintendence | All costs associated with providing oversite during the performance of on site activities; layout, demolition, construction. | DAY | $ - 0 |
2.3.2 a DESIGN & PROFESSIONAL SERVICES SECTION SUB TOTAL $ - 0
| DESIGN & PROFESSIONAL SERVICES | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | Professional Services | All costs associated with professional services to enable design and construction such as assessments, surveys, permitting, testing, etc | JOB | $ - 0 | |||
| 2 | Design | All costs associated with professional design and construction document creation | JOB | $ - 0 | |||
| 3 | Project Management | All Costs associated with project management | JOB | $ - 0 |
2.3.2 b DEMOLITION SECTION SUB TOTAL $ - 0
| BOARDWALK, RAMPS (DEMOLITION) | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | Deck (Walking Surface) | Removal of the deck boards and various associated harware. | SF | $ - 0 | |||
| 2 | Railing | Removal of the existing railing | LF | $ - 0 | |||
| 3 | Deck Supporting Structure | Removal of the deck supporting structure and associated harware. | SF | $ - 0 | |||
| 4 | Disposal | Disposal of waste materials | CY | $ - 0 |
2.3.2 c CONSTRUCTION SECTION SUB TOTAL $ - 0
| BOARDWALK, PHONE STATIONS, PAVILION (CONSTRUCTION) | SUB TOT | $ - 0 | |||||
| LINE ITEM | DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | Notes | |
| 1 | PT Piles | Provide and install timber piles | LF | $ - 0 | |||
| 2 | Supporting Structure | Provide and Install the deck supporting structure and associated harware. | SF | $ - 0 | |||
| 3 | Deck (Walking Surface) | Provide and Install precast deck. | SF | $ - 0 | |||
| 4 | Railing | Provide and Install new railing. | LF | $ - 0 | |||
| $ - 0 | |||||||
| $ - 0 |
PROJECT SUBTOTAL = $ - 0
| OVERHEAD, PROFIT, BOND | SUB TOT: | $ - 0 | |||
| LINE ITEM | DESCRIPTION | % | TOTAL | Notes | |
| 001 | Overhead | Overhead Costs | $ - 0 | ||
| 002 | Profit | Profit | $ - 0 | ||
| 003 | Bond | Actual Bond | $ - 0 |
PROJECT TOTAL ESTIMATE (Overhead, Profit, Bond + Project Subtotal) = $ - 0
| CONTRACTOR PERIOD OF PERFORMANCE = | Days | |
| Design = | Days | |
| Construction = | Days |
Pricing Schedule &"-,Bold"&20 2.3.2 TASK 2 XLWU 19-8114 Repair Base Boardwalks &"-,Bold"Crooked Island Beach Boardwalk &"-,Bold"Contractor Name: _______________________________ Date:_______________________________&"-,Regular"
&"-,Italic"PRICING SCHEDULE TASK 2 &"-,Regular"
T2
| 2.2.4 EQUIPMENT RENTAL ( ITEMIZED LIST ) | SUB TOT | $0.00 | |||
| RENTAL DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | |
| ex. | (Example) 40' Straight Boom Manlift (Sunbelt Rentals) | MONTH | 1 | 2,180.00 | $ 2,180.00 |
| 1 | |||||
| 2 | $ - 0 | ||||
| 3 | $ - 0 | ||||
| 4 | $ - 0 | ||||
| 5 | $ - 0 | ||||
| 6 | $ - 0 | ||||
| 7 | $ - 0 | ||||
| 8 | $ - 0 | ||||
| 9 | $ - 0 | ||||
| 10 | $ - 0 | ||||
| 11 | $ - 0 | ||||
| 12 | $ - 0 | ||||
| 13 | $ - 0 | ||||
| 14 | $ - 0 | ||||
| 15 | $ - 0 | ||||
| 16 | $ - 0 | ||||
| 17 | $ - 0 | ||||
| 18 | $ - 0 | ||||
| 19 | $ - 0 | ||||
| 20 | $ - 0 |
| OTHER PROJECT NOTES FOR BID | SUB TOT | $0.00 | |||
| DESCRIPTION | UNIT | QUANTITY | UNIT COST | TOTAL | |
| ex. | (Example) 40' Straight Boom Manlift (Sunbelt Rentals) | MONTH | 1 | 2,180.00 | $ 2,180.00 |
| 1 | $ - 0 | ||||
| 2 | $ - 0 | ||||
| 3 | $ - 0 | ||||
| 4 | $ - 0 | ||||
| 5 | $ - 0 | ||||
| 6 | $ - 0 | ||||
| 7 | $ - 0 | ||||
| 8 | $ - 0 | ||||
| 9 | $ - 0 | ||||
| 10 | $ - 0 | ||||
| 11 | $ - 0 | ||||
| 12 | $ - 0 | ||||
| 13 | $ - 0 | ||||
| 14 | $ - 0 | ||||
| 15 | $ - 0 | ||||
| 16 | $ - 0 | ||||
| 17 | $ - 0 | ||||
| 18 | $ - 0 |
&"-,Bold"&18PRICING SCHEDULE
2.3.2 TASK 2 &"-,Bold"&16XLWU 19-8114
Repair Base Boardwalks Crooked Island Beach Boardwalk &16
&14DATE: ______________________________&16
Note: Provide additional pages as needed
PRICING SCHEDULE TASK 2
File details come from the government source that posted it. Updated .