This document is a solicitation amendment for repair and restoration services for Building 1801 at Tyndall Air Force Base in Florida. The solicitation is set aside for small businesses and seeks electronic proposals by 1:00 PM on September 10, 2020. A pre-proposal site visit will be held on August 13, 2020, with attendees limited to two people per prime contractor. The estimated value of the construction is between $500,000 and $1,000,000. The amendment extends the question deadline to August 19, 2020 and the proposal deadline to September 10, 2020. It provides instructions for preparing and submitting proposals, including formatting and content requirements. The Department of the Air Force Air Combat Command is the issuing agency.

View the file

Other files for this federal contract opportunity

Other files attached to WEG ADMIN 1801, newest first.
File Type Posted
QuestionForm_08182020 Signed.pdf PDF
Solicitation Amendment FA481920R00180002 SF 30.pdf PDF
Appendix A Scope of Work Updated.pdf PDF
Appendix C Compressor House Photos.pdf PDF
Solicitation Amendment FA481920R00180001 SF 30.pdf PDF
Attachment 09_Sample RFI.PDF PDF
Attachment 1_Statment of Work.pdf PDF
Attachment 08_AF3065.pdf PDF
82906804.PDF PDF
B477B440.PDF PDF
Attachment 2_Appendix A Scope of Work.pdf PDF
Attachment 04_Wage Determination.pdf PDF
Attachment 07_AF 3064.pdf PDF
Attachment 05_AF Form 66.xls XLS spreadsheet
Attachment 06_AF Form 3000.pdf PDF
Solicitation - FA481920R0018.pdf PDF
Site Visit Document.xlsx XLSX spreadsheet
C02BB650.PDF PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section L - Instructions, Conditions, & Notices to Offerors or Quoters

Miscellaneous text in this section has been modified to:

INSTRUCTIONS TO OFFERORS

I. General Instructions:

A. This solicitation is set-aside for 100% Small Business Set Aside.

B. Provide an electronic copy via email and all information required by this RFP to Contract Personnel.

Please title your email subject line: Repair (Restore), Bldg. 1801 FA481920R0018. Documents may be emailed to:

Melissa Sanders email: melissa.sanders @us.af.mil Phone: (850) 283-8637

Pedro Bonachea email: pedro.bonachea@us.af.mil Phone: (850) 283-9625

325 CONS Construction Organization Box email: 325CONS.PKC.Construction@us.af.mil

It is the contractors responsibility to ask government to acknowledge receipt.

Questions and Answers are due on 19 August 2020 at 1:00 PM, CDT. Proposals are due no later than 1:00 PM CDT, on 10 September 2020. Recommend all offerors (via telephone call to appropriate Government POC) confirm receipt of all e-mailed proposals and revisions. Ensure you acknowledge all amendments in your proposal.

C. Site Visit Details Date: 13 August 2020 Time: 1000 Location: Bldg 1801, Tyndall AFB, FL Directions: Each Prime Contractor is allowed to bring two personnel. If you are attending contact SSgt Pedro Bonachea at pedro.bonachea@us.af.mil with the name(s) of the individual(s) who are planning on attending by COB 11 August 2020.

L-1 PROPOSAL PREPARATION INSTRUCTIONS

A. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein. Proposals must be complete, self-sufficient, and respond directly to the requirements of this solicitation.

Alternate proposals will not be accepted.

B. The contracting officer has determined there is a high probability of adequate price competition in this acquisition. Upon examination of the initial offers, the Contracting Officer will review this determination and if, in the contracting officer's opinion, adequate price competition exists, no additional cost information will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this competition the contracting officer determines that adequate price competition no longer exists; offerors may be required to submit information to the extent necessary for the contracting officer to determine the reasonableness of the price.

FA481920R00180003

C. Format for proposal shall be as follows:

1. Electronic Copy

Please submit your proposal via email.

Covers for tables of contents, indices, title pages, cross reference indices, and section dividers/tables will not be included in the page count if they are inserted solely to provide ease to the reader in locating volumes/sections of the proposal. They will be counted if they contain any other information, (e.g. diagrams, extraneous data, etc). Pages marked "This page intentionally left blank" will not be counted.

2. Type face shall not be less than 12 font, with 1" margins on all sides. Smaller, legible font size, no smaller than 6 point, may be used for charts and tables.

3. Elaborate formats or color presentations are not desired or required.

4. Electronic copies shall be searchable documents.

5. Documents submitted in response to this solicitation must be fully responsive to and consistent with the following:

a. Requirements of the solicitation, and government standards and regulations pertaining to the specification.

b. Evaluation Factors for Award in Section M of this solicitation.

c. Any limitation on the number of proposal pages. Pages exceeding the page limitations set forth in this Section L will be removed from the proposal and not read or evaluated.

6. The estimated magnitude of construction for this project is between $500,000 and $1,000,000.

7. Specific Instructions:

Documents submitted in response to this RFP must be fully responsive to and consistent with the following:

Volume I - PRICE PROPOSAL A. Complete blocks 14 (to include CAGE Code), 15, 16, 17, 19 (if applicable), and 20A-C of the SF 1442, Solicitation, Offer, and Award. An authorized official of the firm must sign and date the SF 1442 in Block 20A C. In doing so, the Offeror accedes to the contract terms and conditions as written in the RFP Sections A through K. These sections constitute the model contract.

B. Complete the necessary fill-ins and certifications in Sections I through K. For Sections C through I, the Offeror shall submit only those pages that require a fill-in. Section K shall be submitted in its entirety.

C. Acknowledge all amendments issued to the solicitation.

VOLUME II -TECHNICAL PROPOSAL

Offerors must meet a standard in all sub-factors of the Technical Factor in order for their technical proposal to be determined "technically acceptable." The standards are defined in Section M for each sub-factor.

A. Technical and Management Approaches: The Offeror shall provide a narrative detailing its management approach to include mobilization, safety, quality control, and resolution of potential issues and challenges; its design approach to include an understanding of the design effort required, required permits, applicable codes and disciplines; and its construction approach to include an understanding of the construction effort required and environmental compliance as detailed in the Statement of Work.

B. Proposed Schedule: The Offeror shall provide a proposed schedule capturing all SOW requirements, execution timelines and critical path items; and demonstrates coordination of work activities, phasing, and potential weather considerations

IDCode:
Page: 1
Pages: 4
AmendNo: 0003
EffDate: 9/2/2020
ReqNo: F4A3640145AW01
ProjNo: XLWU 20-8138
IssCode: FA4819
AdmCode:
IssuedBy: FA4819 325TH CONTRACTING SQ

501 AIREY AVE STE 5 BLDG 647

STOP 28 CP 850 283 8643

TYNDALL AFB, FL 32403-5526

United States Pedro Bonachea, Email: pedro.bonachea@us.af.mil Telephone: 850-283-8618

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA481920R0018
SolDate: 8/5/2020
AwardChg:
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: 1
NoCopies: 0
ApprData: See Section G
ChgeOrd:
ChgeOrder:
Modify:
SuppAgre:
SuppAuth:
ModOthr:
OthrSpec:
NoReq: 1
Require:
Copies:
Descript: 1. Post Questions & Answers

2. Extend the due date from 3 September at 1:00PM to 10 September at 1:00PM

The point of contact for this modification is SSgt Pedro J. Bonachea; pedro.bonachea@us.af.mil.

ContNameTitle:
CoNameTitle: Allyson E. Cooper

Email: allyson.cooper@us.af.mil Telephone: 773-6649

ContDate:
CODate:

File details come from the government source that posted it. Updated .