Appendix A Scope of Work Updated.pdf

PDF 217 KB Posted

Attached to
WEG ADMIN 1801 Federal contract opportunity
Solicitation number
FA481920R0018
Issued by
Department of the Air Force Air Combat Command

About this file

This document outlines the scope of work for repair and restoration of Building 1801 at WEG Administration. The scope of work includes replacing the raised flooring and supporting framework in several server rooms totaling approximately 1610 square feet. It also includes replacing vinyl composite tile flooring in two areas totaling 400 square feet. The lighting in all server rooms will be replaced with dimmable LED lights, including approximately 29 fixtures without battery backup and 7 with battery backup. Optional tasks include replacing lighting throughout the entire facility with approximately 200 additional dimmable LED fixtures. The fire protection system will be extended and the sprinkler system in one room will be assessed and optimized. The HVAC system will be balanced in several rooms to effectively cool and dehumidify areas where condensation was observed. Mold remediation, wall repairs, and cove base replacement are outlined for one room. Optional work includes converting the building structure to withstand 170 mph winds and installing temperature control fans in the compressor house.

View the file

Other files for this federal contract opportunity

Other files attached to WEG ADMIN 1801, newest first.
File Type Posted
Solicitation Amendment FA481920R00180003 SF 30.pdf PDF
QuestionForm_08182020 Signed.pdf PDF
Appendix C Compressor House Photos.pdf PDF
Solicitation Amendment FA481920R00180002 SF 30.pdf PDF
Solicitation Amendment FA481920R00180001 SF 30.pdf PDF
B477B440.PDF PDF
Attachment 2_Appendix A Scope of Work.pdf PDF
Attachment 04_Wage Determination.pdf PDF
Attachment 07_AF 3064.pdf PDF
Attachment 05_AF Form 66.xls XLS spreadsheet
Attachment 06_AF Form 3000.pdf PDF
Solicitation - FA481920R0018.pdf PDF
Site Visit Document.xlsx XLSX spreadsheet
C02BB650.PDF PDF
Attachment 1_Statment of Work.pdf PDF
Attachment 08_AF3065.pdf PDF
82906804.PDF PDF
Attachment 09_Sample RFI.PDF PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

APPENDIX A – SCOPE OF WORK

XLWU208138 REPAIR (RESTORE) WEG ADMIN, BLDG 1801

13 Aug 2020

Interior

Task 1 - Replace raised floor and supporting framework ~1610 sf

Replace raised floor in room 114 (contractor will need to determine a way to replace the floor without removing or turning off all of the comm equipment – equipment is mission essential). ~ 1125 sf

Replace raised floor and supporting framework in room 117 adjacent to room 114. ~ 250 sf

Replace raised floor and supporting framework in room 125 adjacent to room 114. ~ 125 sf

Replace the supporting framework in room 114 holding up the floor (check UFC for floor certification requirements and load rating).

Install wall-mounted placard stating flooring load rating in room 114 and room 117.

Task 2 - Replace VCT flooring ~ 400 sf

Replace VCT flooring in room 116 adjacent to room 114. ~ 200 sf

Replace VCT flooring in room 117entry way. ~ 200 sf

Lighting

Task 3 - Replace lights in all server rooms with dimmable LED lighting. ~ (23) 1 by 4 without battery backup and (6) with battery backup. ~ (1) 2 by 4 with battery backup

Replace 1 by 4 lights in room 114 with dimmable LED lighting. ~ 17 without battery backup and 3 with battery backup as required

Replace 1 by 4 lights in room 116 with dimmable LED lighting. ~ 1 without battery backup and 1 with battery backup as required

Replace 1 by 4 lights in room 117 with dimmable LED lighting. ~ 3 without battery backup and 2 with battery backup as required

Replace 1 by 4 lights in room 125 with dimmable LED lighting. ~ 2 without battery backup and 0 with battery backup as required

Replace 2 by 4 lights in room 140 with dimmable LED lighting. ~ 0 without battery backup and 1 with battery backup as required

APPENDIX A – SCOPE OF WORK

XLWU208138 REPAIR (RESTORE) WEG ADMIN, BLDG 1801

13 Aug 2020

Optional Lighting

Task 4 - Consider replacing lighting throughout the facility with dimmable LED lighting ~ 200 plus.

Fire Protection

Task 5 - Extend VESDA system to under the floor into room 114 from the master panel in room

124.

Task 6 - Assess and optimize fire sprinkler system in room 114. Equipment appears to be blocking the effectiveness of the sprinkler heads.

HVAC

Task 7 - Balance air conditioning system in room 114, 116, 117, 125 to effectively cool and dehumidify the rooms. Condensation observed in room during site visit.

Wall Repair RM 140

Task 8 – Ensure drain from HVAC properly routed and draining properly.

Task 9 –Mold remediate Rm 140

Task 10 - Repair wall where HVAC has leaked

Task 11 – Prep and paint wall repair

Task 12 _ Replace damaged or missing cove base in room 140.

Optional Compressor House Work

Task 13 – Convert building to a HVHZ building able to with stand 170 mph winds.

Task 14 – Provide a thermostatically controlled fan to maintain temperature in the compressor house