Appendix A Scope of Work Updated.pdf
PDF 217 KB Posted
- Attached to
- WEG ADMIN 1801 Federal contract opportunity
- Solicitation number
- FA481920R0018
About this file
This document outlines the scope of work for repair and restoration of Building 1801 at WEG Administration. The scope of work includes replacing the raised flooring and supporting framework in several server rooms totaling approximately 1610 square feet. It also includes replacing vinyl composite tile flooring in two areas totaling 400 square feet. The lighting in all server rooms will be replaced with dimmable LED lights, including approximately 29 fixtures without battery backup and 7 with battery backup. Optional tasks include replacing lighting throughout the entire facility with approximately 200 additional dimmable LED fixtures. The fire protection system will be extended and the sprinkler system in one room will be assessed and optimized. The HVAC system will be balanced in several rooms to effectively cool and dehumidify areas where condensation was observed. Mold remediation, wall repairs, and cove base replacement are outlined for one room. Optional work includes converting the building structure to withstand 170 mph winds and installing temperature control fans in the compressor house.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA481920R00180003 SF 30.pdf | ||
| QuestionForm_08182020 Signed.pdf | ||
| Appendix C Compressor House Photos.pdf | ||
| Solicitation Amendment FA481920R00180002 SF 30.pdf | ||
| Solicitation Amendment FA481920R00180001 SF 30.pdf | ||
| B477B440.PDF | ||
| Attachment 2_Appendix A Scope of Work.pdf | ||
| Attachment 04_Wage Determination.pdf | ||
| Attachment 07_AF 3064.pdf | ||
| Attachment 05_AF Form 66.xls | XLS spreadsheet | |
| Attachment 06_AF Form 3000.pdf | ||
| Solicitation - FA481920R0018.pdf | ||
| Site Visit Document.xlsx | XLSX spreadsheet | |
| C02BB650.PDF | ||
| Attachment 1_Statment of Work.pdf | ||
| Attachment 08_AF3065.pdf | ||
| 82906804.PDF | ||
| Attachment 09_Sample RFI.PDF |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPENDIX A – SCOPE OF WORK
XLWU208138 REPAIR (RESTORE) WEG ADMIN, BLDG 1801
13 Aug 2020
Interior
Task 1 - Replace raised floor and supporting framework ~1610 sf
Replace raised floor in room 114 (contractor will need to determine a way to replace the floor without removing or turning off all of the comm equipment – equipment is mission essential). ~ 1125 sf
Replace raised floor and supporting framework in room 117 adjacent to room 114. ~ 250 sf
Replace raised floor and supporting framework in room 125 adjacent to room 114. ~ 125 sf
Replace the supporting framework in room 114 holding up the floor (check UFC for floor certification requirements and load rating).
Install wall-mounted placard stating flooring load rating in room 114 and room 117.
Task 2 - Replace VCT flooring ~ 400 sf
Replace VCT flooring in room 116 adjacent to room 114. ~ 200 sf
Replace VCT flooring in room 117entry way. ~ 200 sf
Lighting
Task 3 - Replace lights in all server rooms with dimmable LED lighting. ~ (23) 1 by 4 without battery backup and (6) with battery backup. ~ (1) 2 by 4 with battery backup
Replace 1 by 4 lights in room 114 with dimmable LED lighting. ~ 17 without battery backup and 3 with battery backup as required
Replace 1 by 4 lights in room 116 with dimmable LED lighting. ~ 1 without battery backup and 1 with battery backup as required
Replace 1 by 4 lights in room 117 with dimmable LED lighting. ~ 3 without battery backup and 2 with battery backup as required
Replace 1 by 4 lights in room 125 with dimmable LED lighting. ~ 2 without battery backup and 0 with battery backup as required
Replace 2 by 4 lights in room 140 with dimmable LED lighting. ~ 0 without battery backup and 1 with battery backup as required
APPENDIX A – SCOPE OF WORK
XLWU208138 REPAIR (RESTORE) WEG ADMIN, BLDG 1801
13 Aug 2020
Optional Lighting
Task 4 - Consider replacing lighting throughout the facility with dimmable LED lighting ~ 200 plus.
Fire Protection
Task 5 - Extend VESDA system to under the floor into room 114 from the master panel in room
124.
Task 6 - Assess and optimize fire sprinkler system in room 114. Equipment appears to be blocking the effectiveness of the sprinkler heads.
HVAC
Task 7 - Balance air conditioning system in room 114, 116, 117, 125 to effectively cool and dehumidify the rooms. Condensation observed in room during site visit.
Wall Repair RM 140
Task 8 – Ensure drain from HVAC properly routed and draining properly.
Task 9 –Mold remediate Rm 140
Task 10 - Repair wall where HVAC has leaked
Task 11 – Prep and paint wall repair
Task 12 _ Replace damaged or missing cove base in room 140.
Optional Compressor House Work
Task 13 – Convert building to a HVHZ building able to with stand 170 mph winds.
Task 14 – Provide a thermostatically controlled fan to maintain temperature in the compressor house