This is a technical specification document for concrete paving materials and construction requirements at Holloman Air Force Base, New Mexico, specifically detailing concrete specifications for airfield pavement construction.
The specification requires approximately 2,100 cubic yards of concrete with a flexural strength of 650 psi, 3-inch slump (±1%), and 6% air content (±1%). Concrete deliveries are scheduled between June 26 and July 26, 2026, distributed across a test pad and twelve lanes with quantities ranging from 30 to 210 cubic yards per location. The concrete must be composed of Type V portland cement or blended cement (ASTM C595/C595M), with allowable water-cementitious materials ratio between 0.38 and 0.45, and minimum cementitious content of 470-517 pounds per cubic yard. Coarse aggregate must have nominal maximum size of 1.5 inches with durability factor of 80 or greater for freeze-thaw resistance, and fine aggregate must meet ASTM C33/C33M with fineness modulus between 2.50 and 3.40. The specification establishes strict quality control requirements including accreditation of testing laboratories per ASTM C1077, pre-construction material testing, mixer performance and uniformity testing per NRMCA standards, and control charts for gradation, slump, air content, and strength development. Contractor must provide batch plants with minimum 350 cubic yard daily capacity, located within 30 minutes haul time of the placement site, and concrete must be placed within 45 minutes (or 30 minutes if ambient temperature exceeds 90°F) from cement charging for non-agitating equipment, or 90 minutes (60 minutes above 90°F) for truck mixers. Acceptance testing includes 7-day compressive strength conversion to equivalent 28-day flexural strength using correlation ratios established during mixture proportioning studies, with fabrication and testing of beams and cylinders per ASTM C31/C31M, C78/C78M, and C39/C39M standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Tab 4. HAFB TTP Asphalt Specs.docx | DOCX document | |
| Tab 5. HAFB TTP Prime Coat Specs.docx | DOCX document | |
| Tab 9. Base Course SOW.docx | DOCX document | |
| Solicitation - FA480126Q0005.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN: 002
Item: Concrete, 650 psi flex strength, 3” slump (+/-1”), 6% AC (+/- 1%) Quantity: 2,100 Unit: Cubic Yards Delivery Date(s): See table below. Subject to change.
Delivery Location(s): Holloman Air Force Base, NM (32.860 N, 106.110 W)
| Lane/Date |
| Quantity (cu yd) |
| Test Pad/15 June 26 |
| 30 (Subject to Change) |
| Lane 1/22 June 26 |
| 145 (Subject to Change) |
| Lane 2/10 July 26 |
| 145 (Subject to Change) |
| Lane 3/24 June 26 |
| 150 (Subject to Change) |
| Lane 4/14 July 26 |
| 155 (Subject to Change) |
| Lane 5/26 June 26 |
| 165 (Subject to Change) |
| Lane 6/16 July 26 |
| 170 (Subject to Change) |
| Lane 7/01 July 26 |
| 175 (Subject to Change) |
| Lane 8/20 July 26 |
| 180 (Subject to Change) |
| Lane 9/06 July 26 |
| 185 (Subject to Change) |
| Lane 10/ 22 July 26 |
| 195 (Subject to Change) |
| Lane 11/08 July |
| 195 (Subject to Change) |
| Lane 12/24 July 26 |
| 210 (Subject to Change) |
SECTION 32 13 14.13
CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS
11/22
PART 1 GENERAL
1.1 UNIT PRICES
1.1.1 Measurements
The quantity of concrete to be paid for will be the volume of concrete in cubic yards accepted by the Government according to the stipulations below. The quantity of other materials specified herein, and used in the construction of the work covered by this section, will not be measured for payment, but will be considered a subsidiary obligation, covered under the price per cubic yard for concrete.
1.1.2 Payments
1.1.2.1 Unit Price
The quantity of concrete measured as specified above will be paid for at the contract unit price when placed in completed and accepted pavements. Payment will be made at the contract price for cubic yard for the scheduled item, with necessary adjustments as specified below. Payment will constitute full compensation for providing all materials, equipment, plant and tools, and for all labor and other incidentals necessary to provide the concrete pavement, except for other items specified herein for separate payment.
1.1.3 Payment of Lots
When a lot of material fails to meet the specification requirements, that lot will be accepted at a reduced price or be removed and replaced with acceptable material at no cost to the Government. Strength will be evaluated, but will not be considered for payment adjustment. Remove and replace any sublot not meeting the required 'Concrete Strength for Final Acceptance' at no additional cost to the Government.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-06 Test Reports
Batch Plant Manufacturer's Inspection Report; G; Submit a written Batch Plant Manufacturer's Inspection Report signed by the technical representative noting all inspection items and corrections and stating the batch plant is capable of producing the volume of concrete as required herein.
Sampling and Testing; G
Mixer Performance (Uniformity) Testing; G
SD-07 Certificates
Laboratory Accreditation and Validation; G
NRMCA Certificate of Conformance
Concrete Batch Plant Operator; G
1.3 QUALITY CONTROL
1.3.1 Laboratory Accreditation and Validation
Provide laboratory and testing facilities. Submit accreditation of the commercial laboratory by an independent evaluation authority, indicating conformance to ASTM C1077, including all applicable test procedures identified in this specification. If multiple laboratories are proposed, identify which tests will be conducted by each. Submit accreditation documentation a minimum of 30 days before any specified testing is performed. The laboratories performing the tests are required to be accredited in accordance with ASTM C1077, including ASTM C78/C78M and ASTM C1260. Provide current accreditation and include the required and optional test methods, as specified.
1.3.1.1 Aggregate Testing and Mix Proportioning
Aggregate testing and mixture proportioning studies are required to be performed by a commercial laboratory.
1.3.1.2 Acceptance Testing
Provide all materials, labor, and facilities required for molding, curing, testing, and protecting test specimens in the laboratory. Provide steel molds for molding the beam specimens. Provide on-site temperature-controlled concrete curing facilities. Provide and maintain boxes or other facilities suitable for storing and curing the specimens at the paving site while in the mold within the temperature range stipulated by ASTM C31/C31M. Provide flexural loading equipment in accordance with ASTM C78/C78M Provide compressive loading equipment in accordance with ASTM C39/C39M.
1.3.1.3 Laboratory Inspection
The Government will inspect all laboratories requiring validation for equipment and test procedures prior to the start of any concreting operations for conformance to ASTM C1077. The laboratory is to maintain this certification for the duration of the project.
1.3.2 Preconstruction Testing of Materials
All sampling and testing is required to be performed using an approved commercial laboratory or, for cementitious materials and chemical admixtures, a laboratory maintained by the manufacturer of the material. Materials are not allowed to be used until notice of acceptance has been given. Additional payment or extension of time due to failure of any material to meet project requirements, or for any additional sampling or testing required is not allowed. Additional tests may be performed by the Government; such Government testing does not relieve any required testing responsibilities.
1.3.2.1 Aggregates
Sample aggregates in the presence of a Government Representative. Obtain samples representative of the materials to be used for the project in accordance with ASTM D75/D75M. Perform all aggregate tests no earlier than 6 months prior to test section construction.
1.3.2.2 Chemical Admixtures, Curing Compounds and Epoxies
At least 30 days before the material is used, submit certified copies of test results for the specific lots or batches to be used on the project. Provide test results less than 5 years old prior to use in the work. Retest chemical admixtures that have been in storage for longer than 6 months or that have been subjected to temperatures outside of manufacturer requirements. Reject if test results do not meet the Level 2 proof of compliance requirements of ASTM C494/C494M.
1.3.2.3 Testing of Cementitious Materials
All materials referenced under paragraph CEMENTITIOUS MATERIALS will be accepted on the basis of manufacturer's certification of compliance, accompanied by mill test reports showing that the material in each shipment meets the requirements of the specification under which it is provided. Provide mill test reports no more than 1 month old, prior to use in the work. Cementitious materials may be subjected to testing by the Government from samples obtained at the mill, at transfer points, or at the project site. If tests prove that a cementitious material that has been delivered is unsatisfactory, promptly remove it from the project site. Retest cementitious material that has not been used within 6 months after testing, and reject if test results do not meet manufacturer requirements.
1.3.3 Testing During Construction
During construction, the Government will sample and test concrete and ingredient materials as considered appropriate. Testing by the Government does not relieve the specified testing requirements. The Government will sample concrete in accordance with ASTM C172/C172M from each batch or truckload (daily production. The Government will perform the following Tests on the proposed material upon delivery prior to commencing construction to demonstrate that the proposed material meets all specified requirements prior to installation. This testing will be completed for each source (or batch) if materials from more than one source are proposed. Tentative approval/acceptance of material will be based on test results meeting the criteria in Part 2 Products.
a. Water-Cement Ratio: The water-cementitious material ratio is the equivalent water-cement ratio as determined by conversion from the weight ratio of water to cement plus SCM by the mass equivalency method described in ACI 211.1.
b. Air content: Determine air content in accordance with ASTM C231/C231M. Air content results must meet Sec
c. Slump: Concrete slump will be determined in accordance with ASTM C143/C143M. The maximum allowable slump of the concrete at the point of placement is listed in Table 12.
d. Temperature: Concrete temperature will be determined in accordance with ASTM C1064/C1064M.
e. Strength testing will also be performed in accordance with Section 2.13 Mixture Proportions. The Contractor will not be held liable for failed strength tests provided that all other delivery, storage, handling, and product requirements in this specification are met.
1.4 DELIVERY, STORAGE, AND HANDLING
1.4.1 Bulk Cementitious Materials
Provide all cementitious materials in bulk at a temperature, as delivered to storage at the site, not exceeding 150 degrees F. Provide sufficient cementitious materials in storage to sustain continuous operation of the concrete mixing plant while the pavement is being placed. Provide separate facilities to prevent any intermixing during unloading, transporting, storing, and handling of each type of cementitious material.
1.4.2 Aggregate Materials
Store aggregate at the site of the batching and mixing plant avoiding breakage, segregation, intermixing or contamination by foreign materials. Store each size of aggregate from each source separately and allow the fine aggregate and the smallest size coarse aggregate to drain. Provide a minimum 24 inch thick sacrificial layer left undisturbed for each aggregate stored on ground or provide a paved or chemically stabilized surface course beneath the stockpiles. Maintain sufficient aggregate at the site at all times to permit continuous uninterrupted operation of the mixing plant at the time concrete pavement is being placed. Do not allow tracked equipment on coarse aggregate stockpiles.
1.4.3 Other Materials
Store reinforcing bars and accessories above the ground on supports. Store all materials to avoid contamination and deterioration.
PART 2 PRODUCTS
2.1 CEMENTITIOUS MATERIALS
Provide cementitious materials consisting of portland cement, or portland cement in combination with supplementary cementitious materials (SCM), that conform to appropriate specifications listed below. New submittals are required when the cementitious materials sources or types change.
2.1.1 Portland Cement
Provide portland cement conforming to ASTM C150/C150M, Type V.
2.1.2 Blended Cements
Provide blended cement conforming to ASTM C595/C595M, Type IP, IS, or IL. Provide pozzolan added to the Type IP blend consisting of ASTM C618 Class F or Class N and that is interground with the cement clinker. Include a written statement from the manufacturer that the amount of pozzolan in the finished cement does not vary more than plus or minus 5 mass percent of the finished cement from lot to lot or within a lot. Provide limestone added to the Type IL blend that is interground with the cement clinker. Include a written statement from the manufacturer that the amount of limestone in the finished cement does not vary more than plus or minus 2.5 mass percent of the finished cement from lot to lot or within a lot. Limit the percent of slag, pozzolan, or limestone to a maximum of IS(50), IP(35) or IL(15). The percentage and type of mineral admixture used in the blend is not allowed to change from that submitted for the aggregate evaluation and mixture proportioning.
2.1.3 Pozzolan
2.1.3.1 Fly Ash
Provide fly ash that conforms to ASTM C618, Class F, including the optional requirement for uniformity with a loss on ignition not exceeding 3 percent. Provide Class F fly ash for use in mitigating Alkali-Silica Reactivity with a total equivalent alkali content less than 4 percent.
2.1.3.2 Raw or Calcined Natural Pozzolan
Provide natural pozzolan that is raw or calcined and conforms to ASTM C618, Class N, including the optional requirement for uniformity with a loss on ignition not exceeding 3 percent. Provide Class N pozzolan for use in mitigating Alkali-Silica Reactivity with a total equivalent alkali content less than 4 percent.
2.1.3.3 Ultra Fine Fly Ash and Ultra Fine Pozzolan
Provide Ultra Fine Fly Ash (UFFA) and Ultra Fine Pozzolan (UFP) that conforms to ASTM C618, Class F or N, and the following additional requirements:
a. The strength activity index at 28 days of age of at least 95 percent of the control specimens.
b. The average particle size is a maximum of 6 microns.
2.1.3.4 Silica Fume
2.1.4 Slag Cement
Provide slag cement (ground-granulated blast-furnace slag) that conforms to ASTM C989/C989M, Grade 100 or Grade 120.
2.1.5 Supplementary Cementitious Materials (SCM) Content
Use of one of the SCMs listed below is optional, unless the SCM is required to mitigate ASR. The use of SCMs is encouraged in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING.
TABLE 6
SUPPLEMENTARY CEMENTITIOUS MATERIALS CONTENT
| Supplementary Cementitious Material |
| Minimum Content (percent) |
| Maximum Content (percent) |
Class N Pozzolan and Class F Fly Ash
| SiO2 + Al2O3 + Fe2O3 > 70 percent |
| 25 |
| 35 |
| SiO2 + A12O3 + Fe2O3 > 80 percent |
| 20 |
| 35 |
| SiO2 + A12O3 + Fe2O3 > 90 percent |
| 15 |
| 35 |
| UFFA and UFP |
| 7 |
| 16 |
| Slag Cement |
| 40 |
| 50 |
2.2 AGGREGATES
Provide aggregates meeting the requirements of this specification. If aggregate sources in the project area do not meet the requirements of this specification, provide aggregates from sources outside the project area.
2.2.1 Aggregate Sources
2.2.1.1 Durability of Coarse Aggregate
Provide aggregate with a satisfactory service record in freezing and thawing of at least 5 years successful service in three concrete paving projects. Include a condition survey of the existing concrete and a review of the concrete-making materials, including coarse aggregates, cement, and mineral admixtures in the service record. Consider the previous aggregate source and test results, cement mill certificate data, mineral admixture chemical and physical composition, and the mix design (cement factor and water-cementitious material ratio) in the review. Provide service record performed by an independent third party professional engineer, petrographer, or concrete materials engineer along with their resume. Include photographs and a written report addressing D-cracks and popouts in accordance with ACI 201.1R in the service record. Provide coarse aggregate with a durability factor of 80 or more when subjected to freezing and thawing of specimens prepared in accordance with ASTM C1646/C1646M and tested in accordance with ASTM C666/C666M, Procedure A, when a coarse aggregate size group or source proposed for use does not have a satisfactory demonstrable service record. Test all coarse aggregate size groups and sources proposed for use individually.
2.2.1.2 Alkali-Silica Reactivity
Evaluate and test fine and coarse aggregates to be used in all concrete for alkali-aggregate reactivity. Test all size groups and sources proposed for use individually.
a. Evaluate the aggregate size groups and sources separately using ASTM C1260. Reject individual aggregates with test results that indicate an expansion of greater than 0.08 percent after 28 days of immersion in 1N NaOH solution, or perform additional testing as follows: utilize the proposed portland cement, blended cement, and SCM, or Lithium Nitrate in combination with each individual aggregate. If only SCMs are being evaluated, test in accordance with ASTM C1567. If Lithium Nitrate is being evaluated, with or without SCMs, test in accordance with COE CRD-C 662. Determine the quantity that meets all the requirements of these specifications and that lowers the expansion equal to or less than 0.08 percent after 28 days of immersion in a 1N NaOH solution. Base the mixture proportioning on the highest percentage of SCM required to mitigate ASR-reactivity.
b. If any of the above options does not lower the expansion to less than 0.08 percent after 28 days of immersion in a 1N NaOH solution, reject the aggregate(s) and submit new aggregate sources for retesting. Submit the results of testing for evaluation and acceptance.
2.2.1.3 Combined Aggregate Gradation
In addition to the grading requirements specified for coarse aggregate and for fine aggregate, provide the combined aggregate grading meeting the following requirements:
a. Provide materials selected and the proportions used such that when the Coarseness Factor (CF) and the Workability Factor (WF) are plotted on a diagram as described in d. below, the point and its associated production tolerance thus determined falls within the parallelogram described therein. Refer to TSPWG M 3-250-04.97-05 for combined aggregate plot locations for the intended placement technique(s).
b. Determine the Coarseness Factor (CF) from the following equation:
CF = (cumulative percent retained on the 3/8 inch sieve)(100) (cumulative percent retained on the No. 8 sieve)
c. The Workability Factor (WF) is defined as the percent passing the No. 8 sieve based on the combined aggregate gradation. Adjust the WF, prorated upwards only, by 2.5 percentage points for each 94 pounds per cubic yard of cementitious material greater than 564 pounds per cubic yard.
d. Plot a diagram using a rectangular scale with WF on the Y-axis with units from 20 (bottom) to 45 (top), and with CF on the X-axis with units from 80 (left side) to 30 (right side). On this diagram, plot a parallelogram with corners at the following coordinates (CF-75, WF-28), (CF-75, WF-40), (CF-45, WF-32.5), and (CF-45, WF-44.5). If the point determined by the intersection of the computed CF and WF does not fall within the above parallelogram, revise the grading of each size of aggregate used and the proportions selected as necessary.
e. Plot the associated production tolerance limits, identified in Table 17, around the CF and adjusted WF point.
2.2.2 Coarse Aggregate
2.2.2.1 Coarse Aggregate Composition
Provide coarse aggregate consisting of crushed or uncrushed gravel, crushed stone, or a combination thereof. Provide aggregates, as delivered to the mixers, consisting of clean, hard, uncoated particles meeting the requirements of ASTM C33/C33M except as specified herein. Provide coarse aggregate with no more than 40 percent loss when subjected to the Los Angeles abrasion test in accordance with ASTM C131/C131M. Provide coarse aggregates with a maximum sodium sulfate soundness loss of 12 percent, or with a magnesium sulfate soundness loss of 18 percent after five cycles when tested in accordance with ASTM C88.
2.2.2.2 Particle Shape Characteristics
Provide particles of the coarse aggregate that are generally spherical or cubical in shape. The quantity of flat particles and elongated particles in any size group coarser than the 3/8 inch sieve are not allowed to exceed 20 percent by weight as determined by the Flat Particle Test and the Elongated Particle Test of ASTM D4791, Method A. A flat particle is defined as one having a ratio of width to thickness greater than 3; an elongated particle is one having a ratio of length to width greater than 3.
2.2.2.3 Size and Grading
Provide coarse aggregate with a nominal maximum size (as defined in ASTM C125) of 1.5 inches with a minimum of 10 percent retained on the 1.0 inch sieve of the proposed combined aggregate gradation that meets the criteria of paragraph COMBINED AGGREGATE GRADATION. Grade and provide the coarse aggregates in a minimum of two size groups meeting the individual grading requirements of ASTM C33/C33M, Size No. 4 (1.5 inches to 0.75 inch) and Size No. 67 (0.75 inch to No. 4). A third coarse aggregate size group may be required to meet the criteria of paragraph Combined Aggregate Gradation.
Mix designs that include a minimum of three coarse aggregate size groups can use grading limits not defined by ASTM C33/C33M provided all other requirements are met. Provide upper and lower grading limits of historic gradations and for all proposed coarse aggregates not defined by ASTM C33/C33M but intended for use in the mix design.
2.2.2.4 Deleterious Materials - Airfield Pavements
The amount of deleterious material in each individual size group and source of coarse aggregate is not allowed to exceed the limits shown in Table 7A below, determined in accordance with the test methods shown.
TABLE 7A
LIMITS OF DELETERIOUS MATERIALS IN COARSE AGGREGATE FOR AIRFIELD PAVEMENTS
Percentage by Mass
| Materials (h) |
| Severe Weather |
| Moderate Weather |
| Clay lumps and friable particles (ASTM C142/C142M) |
| 0.2 |
| 0.2 |
| Shale (a) (ASTM C295/C295M) |
| 0.1 |
| 0.2 |
| Material finer than No. 200 sieve (b) (ASTM C117) |
| 0.5 |
| 0.5 |
| Lightweight particles (c) (ASTM C123/C123M) |
| 0.2 |
| 0.2 |
| Clay ironstone (d) (ASTM C295/C295M) |
| 0.1 |
| 0.5 |
| Chert, cherty stone, and other aggregates (less than 2.40 Sp. Gr.) (e) (ASTM C123/C123M and ASTM C295/C295M) |
| 0.1 |
| 0.5 |
| Claystone, mudstone, and siltstone (f) (ASTM C295/C295M) |
| 0.1 |
| 0.1 |
| Shaly and argillaceous limestone (g) (ASTM C295/C295M) |
| 0.2 |
| 0.2 |
| Other soft particles (COE CRD-C 130) |
| 1.0 |
| 1.0 |
| Total of all deleterious substances exclusive of material finer than No. 200 sieve |
| 1.0 |
| 2.0 |
(a) Shale is defined as a fine-grained, thinly laminated or fissile sedimentary rock. It is commonly composed of clay or silt or both. It has been indurated by compaction or by cementation, but not so much as to have become slate.
(b) Limit for material finer than No. 200 sieve is allowed to be increased to 1.5 percent for crushed aggregates if the fine material consists of crusher dust that is essentially free from clay or shale. Use XRD or other appropriate techniques as determined by petrographer to quantify amount and justify increase.
(c) Test with a separation medium with a density of Sp. Gr. of 2.0. This limit does not apply to coarse aggregate manufactured from blast-furnace slag unless contamination is evident.
(d) Clay ironstone is defined as an impure variety of iron carbonate, iron oxide, hydrous iron oxide, or combinations thereof, commonly mixed with clay, silt, or sand. It commonly occurs as dull, earthy particles, homogeneous concretionary masses, or hard-shell particles with soft interiors. Other names commonly used for clay ironstone are "chocolate bars" and limonite concretions.
(e) Chert is defined as a rock composed of quartz, chalcedony or opal, or any mixture of these forms of silica. It is variable in color. The texture is so fine that the individual mineral grains are too small to be distinguished by the unaided eye. Its hardness is such that it scratches glass but is not scratched by a knife blade. It may contain impurities such as clay, carbonates, iron oxides, and other minerals. Cherty stone is defined as any type of rock (generally limestone) that contains chert as lenses and nodules, or irregular masses partially or completely replacing the original stone. Other aggregates consist of obsidian, ash tuff, and palygorskite.
(f) Claystone, mudstone, or siltstone, is defined as a massive fine-grained sedimentary rock that consists predominantly of indurated clay or silt without laminations or fissility. It may be indurated either by compaction or by cementation.
(g) Shaly limestone is defined as limestone in which shale occurs as one or more thin beds or laminae. These laminae may be regular or very irregular and may be spaced from a few inches down to minute fractions of an inch. Argillaceous limestone is defined as a limestone in which clay minerals occur disseminated in the stone in the amount of 10 to 50 percent by weight of the rock; when these make up from 50 to 90 percent, the rock is known as calcareous (or dolomitic) shale (or claystone, mudstone, or siltstone).
(h) Perform testing in accordance with the referenced test methods, except use the minimum sample size specified below.
2.3.2.5 Testing Sequence for Deleterious Materials in Coarse Aggregate - Airfields Only
No extension of time or additional payment due to any delays caused by the testing, evaluation, or personnel requirements is allowed. The minimum test sample size of the coarse aggregate is 200 pounds for the 3/4 inch and larger maximum size and 25 pounds for the No. 4 to 3/4 inch coarse aggregate. Provide facilities for the ready procurement of representative test samples. The testing procedure on each sample of coarse aggregate for compliance with limits on deleterious materials is as follows:
Step 1: Wash each full sample of coarse aggregate for material finer than the No. 200 sieve. Discard material finer than the No. 200 sieve.
Step 2: Test remaining full sample for clay lumps and friable particles and remove.
Step 3. Test remaining full sample for chert and cherty stone with SSD density of less than 2.40 specific gravity. Remove lightweight chert and cherty stone. Retain other materials less than 2.40 specific gravity for Step 4.
Step 4: Test the materials less than 2.40 specific gravity from Step 3 for lightweight particles (Sp. GR. 2.0) and remove. Restore other materials less than 2.40 specific gravity to the sample.
Step 5: Test remaining sample for clay-ironstone, shale, claystone, mudstone, siltstone, shaly and argillaceous limestone, and remove.
Step 6: Test a minimum of one-fifth of remaining full sample for other soft particles.
2.3.3 Fine Aggregate
2.3.3.1 Fine Aggregate Composition
Provide fine aggregate consisting of natural sand, manufactured sand, or a combination of the two, each composed of clean, hard, durable particles meeting the requirements of ASTM C33/C33M. Stockpile and batch each type of fine aggregate separately. Provide fine aggregate with particles that are generally spherical or cubical in shape. For fine aggregate provided as a combination of sources, test each source individually.
2.3.3.2 Grading
Provide fine aggregate, as delivered to the mixer, with a grading that conforms to the requirements of ASTM C33/C33M and having a fineness modulus of not less than 2.50 nor more than 3.40. For fine aggregate supplied as a combination of sources, determine the fineness modulus on a composite sample.
2.3.3.3 Deleterious Material
The minimum test sample size for fine aggregate proposed for use in airfield paving is 10 pounds. The amount of deleterious material in the fine aggregate is not to exceed the limits listed in Table 8 when performed on the full sample:
TABLE 8
LIMITS OF DELETERIOUS MATERIALS IN FINE AGGREGATE
| Material |
| Percentage by Mass |
| Clay lumps and friable particles ASTM C142/C142M |
| 1.0 |
| Material finer than No. 200 sieve ASTM C117 |
| 3.0 |
| Lightweight particles ASTM C123/C123M using a medium with a density of Sp. Gr. of 2.0 |
| 0.5 |
| Total of all above |
| 3.0 |
2.3.3.4 Testing Sequence for Deleterious Materials in Fine Aggregate - Airfields Only
The testing procedure on each sample of fine aggregate for compliance with limits on deleterious materials is as follows:
Step 1: Wash each full sample of fine aggregate for material finer than the No. 200 sieve. Discard material finer than the No. 200 sieve.
Step 2: Test remaining full sample for clay lumps and friable particles and remove.
Step 3. Test remaining full sample for lightweight particles (Sp. GR. 2.0).
2.3 CHEMICAL ADMIXTURES
2.3.1 General Requirements
Only use chemical admixtures when the specific admixture type and manufacturer is the same material used in the mixture proportioning studies. Provide all chemical admixtures from the same manufacturer. Provide air-entraining admixture conforming to ASTM C260/C260M. Use an accelerating admixture conforming to ASTM C494/C494M, Type C or Type E, when specified in paragraph MIXTURE PROPORTIONS below provided it is not used to reduce the amount of cementitious material. Calcium chloride and admixtures containing calcium chloride are not allowed. Provide retarding or water-reducing admixture that meet the requirements of ASTM C494/C494M, Type A, B, or D, except that the 6-month and 1-year compressive strength tests are waived. ASTM C494/C494M, Type F and G high range water reducing admixtures and Type S specific performance admixtures are not allowed. ASTM C1017/C1017M flowable admixtures are not allowed.
2.3.2 Lithium Nitrate
Provide lithium admixture consisting of a nominal 30 percent aqueous solution of Lithium Nitrate, with a density of 10 pounds per gallon, with the approximate chemical form as shown below:
TABLE 9
LITHIUM NITRATE COMPOSITION
| Constituent |
| Limit (Percent by Mass) |
| LiNo3 (Lithium Nitrate) |
| 30 plus or minus 0.5 |
| SO4-2 (Sulfate Ion) |
| 0.1 (max) |
| Cl- (Chloride Ion) |
| 0.2 (max) |
| Na+ (Sodium Ion) |
| 0.1 (max) |
| K+ (Potassium Ion) |
| 0.1 (max) |
Provide the services of a manufacturer's technical representative experienced in dispensing, mixing, proportioning, placement procedures and curing of concrete containing lithium nitrate, at no expense to the Government. This representative is required to be present on the project prior to and during at least the first two days of placement using lithium nitrate.
2.4 WATER
Provide water for mixing and curing that is fresh, clean, potable, and free of injurious amounts of oil, acid, salt, or alkali, except that non-potable water, or water from concrete production operations, can be used if it meets the requirements of ASTM C1602/C1602M.
2.5 EQUIPMENT
2.5.1 Batching and Mixing Plant
2.5.1.1 Location
Locate the batching and mixing plant no more than 30 minutes haul and gate security check time from the placing site. Provide operable telephonic or radio communication between the plant and the placing site at all times concreting is taking place.
2.5.1.2 Type and Capacity
Provide a batching and mixing plant consisting of a stationary-type central mix plant, including permanent installations and portable or relocatable plants installed on stable foundations. Provide a plant designed and operated to produce concrete within the specified tolerances, with a minimum capacity of 350 cubic yards per day, that conforms to the requirements of NRMCA QC 3 including provisions addressing:
1. Material Storage and Handling
2. Batching Equipment
3. Central Mixer
4. Ticketing System
5. Delivery System
2.5.1.3 Tolerances
TABLE 10
BATCH PLANT MIXING TOLERANCES
| Materials |
| Percentage of Required Mass |
| Cementitious Materials |
| plus or minus 1 |
| Aggregate |
| plus or minus 2 |
| Water |
| plus or minus 1 |
| Admixture |
| plus or minus 3 |
For volumetric batching equipment for water and admixtures, the above numeric tolerances apply to the required volume of material being batched. Dilute concentrated admixtures uniformly, if necessary, to provide sufficient volume per batch so that the batchers operate consistently within the above tolerance.
2.5.1.4 Moisture Control
Provide a plant capable of ready adjustment to compensate for the varying moisture contents of the aggregates and to change the quantities of the materials being batched. Provide an electric moisture meter complying with the provisions of COE CRD-C 143 for measuring of moisture in the fine aggregate. Provide a sensing element arranged so that measurement is made near the batcher charging gate of the fine aggregate bin or in the fine aggregate batcher.
2.5.2 Concrete Mixers
Provide stationary or truck mixers that are capable of combining the materials into a uniform mixture and of discharging this mixture without segregation. Do not charge the mixers in excess of the capacity recommended by the manufacturer. Operate the mixers at the drum or mixing blade speed designated by the manufacturer. Maintain the mixers in satisfactory operating condition, with the mixer drums kept free of hardened concrete. Replace mixer blades or paddles when worn down more than 10 percent of their depth when compared with the manufacturer's dimension for new blades or paddles.
2.5.2.1 Stationary Mixers
Stationary mixers are required to be drum or pan mixers. Provide mixers with an acceptable device to lock the discharge mechanism until the required mixing time has elapsed. Perform mixer performance (uniformity) testing in accordance with COE CRD-C 55 and with paragraph TESTING AND INSPECTION FOR 823 RHS QUALITY CONTROL DURING CONSTRUCTION in PART 3.
2.5.2.2 Mixing Time and Uniformity for Stationary Mixers
Use the project's approved mixture proportions for uniformity testing. For stationary mixers, before uniformity data are available, the minimum mixing time for each batch after all solid materials are in the mixer, provided that all of the mixing water is introduced before one-fourth of the mixing time has elapsed, is 1 minute for mixers having a capacity of 1 cubic yard. For mixers of greater capacity, increase this minimum time by 20 seconds for each additional 1.33 cubic yard or fraction thereof. Provide uniformity test results meeting the properties required by this specification in addition to meeting the requirements of Table 11. After results of uniformity tests are available, the mixing time may be reduced to the minimum time required to meet uniformity requirements; but if uniformity requirements are not being met, increase the mixing time as directed. Perform mixer uniformity tests at new mixing times immediately after any change in mixing time or volume. Any changes to the mix constituents or sequence of charging the mixer after a batch requires an additional three consecutive passing batches. For regular testing perform all six tests on three consecutive batches of concrete. The range for regular testing is the average of the ranges of the three consecutive batches. Conduct the Regular Test sequence for initial determination of the mixing time or as directed. When regular testing is performed, the concrete is required to meet the limits of any five of the six uniformity requirements listed in Table 11 below.
TABLE 11
UNIFORMITY REQUIREMENTS--STATIONARY MIXERS
| Parameter |
| Regular Tests Allowable Maximum Range for 3 Consecutive Batches |
| Abbreviated Tests Allowable Maximum Range for 1 Batch |
| Unit weight of air-free mortar |
| 2.0 pounds per cubic foot |
| 2.0 pounds per cubic foot |
| Air content |
| 1.0 percent |
| Not Applicable |
| Slump |
| 1.0 inch |
| 1.0 inch |
| Coarse aggregate |
| 6.0 percent |
| 6.0 percent |
| Compressive strength at 7 days |
| 10.0 percent |
| 10.0 percent |
| Water content |
| 1.5 percent |
| Not Applicable |
2.5.2.3 Abbreviated Uniformity Test
Use the project's approved mixture proportions for uniformity testing. Conduct the Abbreviated Test sequence for production concrete verification at the frequency specified in Table 17. Provide uniformity test results meeting the fresh and hardened concrete properties required by this specification in addition to meeting the requirements of Table 11. When abbreviated testing is performed, the concrete is required to meet only those requirements listed for abbreviated testing. Abbreviated testing is performed on a single batch of concrete. The range for abbreviated testing is the range for one batch. If more than one mixer is used and all are identical in terms of make, type, capacity, condition, speed of rotation, the results of tests on one of the mixers apply to the others, subject to Government approval.
2.5.2.4 Truck
Provide only truck mixers designed for mixing or transporting paving concrete with extra large blading and rear opening specifically for low slump paving concrete. Provide truck mixers, the mixing of concrete therein, and concrete uniformity and testing thereof that conform to the requirements of ASTM C94/C94M. Any changes to the mix constituents or sequence of charging the truck mixer requires an additional three consecutive passing batches. Determine the number of revolutions between 70 to 100 for truck-mixed concrete and the number of revolutions for shrink-mixed concrete by uniformity tests as specified in ASTM C94/C94M and in requirements for mixer performance stated in paragraph TESTING AND INSPECTION FOR 823 RHS QUALITY CONTROL DURING CONSTRUCTION in PART 3. If requirements for the uniformity of concrete are not met with 100 revolutions of mixing after all ingredients including water are in the truck mixer drum, discontinue use of the mixer until the condition is corrected. Water is not allowed to be added after the initial introduction of mixing water except, when on arrival at the job site, the slump is less than specified and the water-cement ratio is less than that given as a maximum in the approved mixture. Additional water may be added to bring the slump within the specified range provided the approved water-cement ratio is not exceeded. Inject water into the head of the mixer (end opposite the discharge opening) drum under pressure, and turn the drum or blades a minimum of 30 additional revolutions at mixing speed. The addition of water to the batch at any later time is not allowed.
2.5.3 Transporting Equipment
Transport fixed form concrete in non-agitating equipment or approved truck mixers designed with extra large blading and rear opening specifically for low slump concrete. Provide transporting equipment designed and operated to deliver and discharge the required concrete mixture completely without segregation.
2.6 SPECIFIED CONCRETE STRENGTH AND OTHER PROPERTIES
2.6.1 Specified Flexural Strength
Specified flexural strength, R, for concrete is 650 psi at 28 days, as determined by equivalent flexural strength, as specified in paragraph Mixture Proportioning for Flexural Strength below.
2.6.2 Allowable Water-Cementitious Materials Ratio
The allowable water-cementitious material ratio is 0.38 to 0.45. The water-cementitious material ratio is the equivalent water-cement ratio as determined by conversion from the weight ratio of water to cement plus SCM by the mass equivalency method described in ACI 211.1.
2.6.3 Air Content
Provide concrete that is air-entrained with a total air content of 6.0 plus or minus 1.5 percentage points, at the point of placement. Determine air content in accordance with ASTM C231/C231M.
2.6.4 Slump
The maximum allowable slump of the concrete at the point of placement is listed in Table 12.
TABLE 12
MAXIMUM ALLOWABLE SLUMP
| Placement Method |
| Maximum Slump |
| Other Types of Finishing Equipment |
| 3 inches |
| Hand Placement |
| 3 inches |
The selected slump is applicable to both pilot and fill-in lanes. Perform separate trial mixture studies for each placement method, as specified in paragraph Trial Mixture Studies.
2.6.5 Concrete Temperature
The temperature of the concrete as delivered is required to conform to the requirements of paragraphs Paving in Hot Weather and Paving in Cold Weather. Determine the temperature of concrete in accordance with ASTM C1064/C1064M.
2.7 MIXTURE PROPORTIONS
2.7.1 Mixture Proportions Composition
Provide concrete composed of cementitious material, water, fine and coarse aggregates, and admixtures. Include supplementary Cementitious Materials (SCM) choice and usage in accordance with paragraph Supplementary Cementitious Materials (SCM) Content. Provide a minimum total cementitious materials content of [ 470 pounds per cubic yard] [ 517 pounds per cubic yard]. Limit the total alkali loading contributed by the portland cement or the portland cement portion of a blended cement to a maximum of 3.0 lb per cubic yard. Calculate the alkali loading as the product of the portland cement content of the concrete multiplied by the alkali content of the portland cement or the portland cement portion of the blended cement, divided by 100. Determine the alkali content in accordance with ASTM C114. Acceptable admixtures consist of air entraining admixture and may also include, as approved, retarding admixture, accelerating admixture, water-reducing and retarding admixtures, water reducing and accelerating admixtures.
2.7.2 Proportioning Studies
Perform trial design batches, mixture proportioning studies, and testing, at no expense to the Government. Submit for approval the Preliminary Proposed Proportioning to include items a., b., and i. below a minimum of 21 days prior to beginning a mixture proportioning study. Submit the results of the mixture proportioning studies signed and stamped by the registered professional engineer having technical responsibility for the mix design study, and submitted at least 30 days prior to commencing concrete placing operations. Include a statement summarizing the maximum nominal coarse aggregate size and the weights and volumes of each ingredient proportioned on a one cubic yard basis. Base aggregate quantities on the mass in a saturated surface dry condition. Provide test results demonstrating that the proposed mixture proportions produce concrete of the qualities indicated. Base methodology for trial mixtures having proportions, slumps, and air content suitable for the work as described in ACI 211.1, modified as necessary to accommodate flexural strength. ACI 211.1 can be supplemented with ACI 325.14R. Submit test results including:
a. Individual coarse and fine aggregate gradations and plots. Include historic gradation averages and standard deviations on individual sieves for each aggregate size group.
b. Combined aggregate gradation and coarseness vs. workability plots.
c. Coarse aggregate quality test results.
d. Fine aggregate quality test results.
e. Mill certificates for cement and supplementary cementitious materials.
f. Certified test results for air entraining, water reducing, retarding, non-chloride accelerating, and Lithium Nitrate admixtures.
g. Specified flexural strength, slump, and air content.
h. Documentation of required average CQC flexural strength, Ra.
i. Recommended proportions and volumes for proposed mixture and each of three trial water-cementitious materials ratios for each proposed placement method.
j. Individual beam and cylinder breaks.
k. Flexural and compressive strength summaries and plots.
l. Correlation ratios for acceptance testing and CQC testing.
m. Historical record of ACI 214R strength test results, documenting production standard deviation (if available).
n. Narrative discussing methodology on how the mix design was developed in accordance with ACI 211.1 and ACI 325.14R.
o. Alternative aggregate blending to be used during the test section if necessary to meet the required surface and consolidation requirements.
2.7.2.1 Water-Cementitious Materials Ratio
Perform at least three different water-cementitious materials ratios, within the limits specified in paragraph Allowable Water-Cementitious Materials Ratio, which produce a range of strength encompassing that required on the project. The minimum and maximum water-cementitious materials ratios of the approved mix design become the minimum and maximum water-cementitious materials ratio for the project during production.
2.7.2.2 Trial Mixture Studies
Perform separate sets of trial mixture studies made for each combination of cementitious materials and each combination of admixtures proposed for use. No combinations are to be used until proven by such studies, except that, if approved in writing and otherwise permitted by these specifications, an accelerating or retarding admixture can be used without separate trial mixture study. Perform separate trial mixture studies for each placing method (slip form, fixed form, or hand placement) proposed. Report the temperature of concrete in each trial batch. Design each mixture to promote easy and suitable concrete placement, consolidation and finishing, and to prevent segregation and excessive bleeding. Proportion laboratory trial mixtures for maximum slump and air content, as permitted by the placement method being utilized.
2.7.2.3 Mixture Proportioning for Flexural Strength
Follow the step by step procedure below:
a. Fabricate all beams and cylinders for each mixture from the same batch or blend of batches. Fabricate and cure all beams and cylinders in accordance with ASTM C192/C192M, using 6 x 6 inches steel beam molds and 6 x 12 inches single-use cylinder molds.
b. Cure test beams from each mixture for 3, 7, 14, and 28 -day flexural tests; 6 beams to be tested per age.
c. Cure test cylinders from each mixture for 3, 7, 14, and 28 -day compressive strength tests; 6 cylinders to be tested per age.
d. Test beams in accordance with ASTM C78/C78M, cylinders in accordance with ASTM C39/C39M.
e. Using the average strength for each w/c at each age, plot all results from each of the three mixtures on separate graphs for w/c versus:
3-day flexural strength 7-day flexural strength 14-day flexural strength 28-day flexural strength
3-day compressive strength 7-day compressive strength 14-day compressive strength 28-day compressive strength
f. From these graphs select a w/c that produces a mixture giving a 28 -day flexural strength equal to the required strength determined in accordance with paragraph Average CQC Flexural Strength Required for Mixtures.
g. Using the above selected w/c, select from the graphs the expected 3, 7, 14, 28 -day flexural strengths and the expected 3, 7, 14, 28 -day compressive strengths for the mixture.
h. From the above expected strengths for the selected mixture determine the following Correlation Ratios:
(1) Ratio of the 14-day compressive strength of the selected mixture to the 28-day flexural strength of the mixture (for acceptance).
(2) Ratio of the 7-day compressive strength of the selected mixture to the 28-day flexural strength of the mixture (for CQC control).
i. If there is a change in materials, perform additional mixture design studies using the new materials and new Correlation Ratios determined.
j. No concrete pavement placement is allowed until the mixture proportions are approved. The approved water-cementitious materials ratio is restricted to the minimum and maximum values specified in paragraph Water-Cementitious Materials Ratio and is not to be increased without written approval.
2.7.3 Average CQC Flexural Strength Required for Mixtures
a. In order to meet the strength requirements specified in paragraph SPECIFIED CONCRETE STRENGTH AND OTHER PROPERTIES during production, the mixture proportions selected during mixture proportioning studies and used during construction require an average CQC flexural strength, Ra, exceeding the specified flexural strength, R, by the amount indicated below.
b. The required average CQC flexural strength, Ra, is used only for proportioning studies and CQC operations as specified in paragraph Concrete Strength Testing for CQC.
c. Acceptance of production flexural strength results is based on the specified flexural strength R specified in paragraph: Specified Flexural Strength.
2.7.3.1 From Previous Test Records
Where a concrete production facility has previous test records current to within 18 months, establish a standard deviation in accordance with the applicable provisions of ACI 214R. Include test records from which a standard deviation is calculated that represent materials, quality control procedures, and conditions similar to those expected, that represent concrete produced to meet a specified flexural strength or strengths within 150 psi of the 28 day flexural strength specified for the proposed work, and that consist of at least 30 consecutive tests. Perform verification testing to document the current strength. A strength test is the average of the strengths of two specimens made from the same sample of concrete and tested at 28 days. Required average CQC flexural strength, Ra, used as the basis for selection of concrete proportions is the value from the equation that follows, using the standard deviation as determined above:
Ra = R + 1.34S
Where: S = standard deviation R = specified flexural strength Ra = required average CQC flexural strength
Where a concrete production facility does not have test records meeting the requirements above but does have a record based on 15 to 29 consecutive tests, establish a standard deviation as the product of the calculated standard deviation and a modification factor from Table 13:
2.7.3.2 Without Previous Test Records
When a concrete production facility does not have sufficient field strength test records for calculation of the standard deviation, determine the required average CQC flexural strength, Ra, by adding 15 percent to the specified flexural strength, R.
PART 3 EXECUTION
3.1 WEATHER LIMITATIONS
3.1.1 Placement and Protection During Inclement Weather
Do not commence placing operations when heavy rain or other damaging weather conditions appear imminent. At all times when placing concrete, maintain on-site sufficient waterproof cover and means to rapidly place it over all unhardened concrete or concrete that might be damaged by rain. Immediately cover and protect all unhardened concrete from rain or other damaging weather. Suspend placement of concrete whenever rain, high winds, or other weather commences to damage the surface or texture of the placed unhardened concrete, washes cement out of the concrete, or changes the water content of the surface concrete.
Remove and replace any slab damaged by rain or other weather, as defined in paragraph Weak Surfaces, full depth, by full slab width, to the nearest original joint as specified in paragraph REPAIR, REMOVAL AND REPLACEMENT OF NEWLY CONSTRUCTED SLABS, at no expense to the Government.
3.2 CONCRETE PRODUCTION
823 RHS will maintain a continuous, uniform forward movement of the paver of not less than 2.5 feet per minute. Provide batching, mixing, and transporting equipment with a capacity sufficient to meet this production rate. Deposit concrete transported in non-agitating equipment in front of the paver within 45 minutes from the time cement has been charged into the mixing drum, except that if the ambient temperature is above 90 degrees F, the time is reduced to 30 minutes. Deposit concrete transported in truck mixers in front of the paver within 90 minutes from the time cement has been charged into the mixer drum of the plant or truck mixer. If the ambient temperature is above 90 degrees F, the time is reduced to 60 minutes.
Accompany every load of concrete delivered to the paving site with a batch ticket from the operator of the batching plant. Provide batch ticket information required by ASTM C94/C94M on approved forms. In addition, provide design quantities in mass or volume for all materials, batching tolerances of all materials, mixture batching time, and design and actual water cementitious materials ratio on each batch delivered, the water meter and revolution meter reading on truck mixers and the time of day on all batch tickets.