DRAFT_Atch_14_Contractor_Guide_-_16_Jun_15.pdf

PDF 40 KB Posted

Attached to
Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA469019RA003
Issued by
Department of the Air Force Air Combat Command

About this file

This document contains a contractor's guide and solicitation for a Multiple Award Construction Contract at Ellsworth Air Force Base. The contractor's guide outlines items that must be submitted to the base contracting and civil engineering offices for construction projects, including questions regarding solicitations, bids, bonds and insurance, payrolls, access requests, as-built drawings, and operation and maintenance manuals. Invoices are to be submitted through WIDE AREA WORK FLOW. The solicitation seeks proposals for indefinite delivery indefinite quantity construction contracts with a target of awarding to three small businesses. The North American Industry Classification code is 237990 and annual revenue cannot exceed $36.5 million. The solicitation will provide new construction, renovation, alteration, demolition and repair work through design-build or design-bid-build methods. The contract period is from award date to 29 June 2021 with a minimum value of $500,000 and maximum of $18 million. The solicitation will be issued on or about 14 November 2018 via Federal Business Opportunities.

DRAFT Atch 14 Contractor Guide

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Atch_31_Follow_on_Q&As_26APR19.pdf PDF
Atch_30_Follow_on_Q&A_25APR19.pdf PDF
Atch_29_Follow_on_Q&As_23APR19.pdf PDF
Atch_20b_SOW_Updated_23APR19.pdf PDF
Solicitation_Amendment_FA469019RA0030009_SF_30.pdf PDF
Solicitation_Amendment_FA469019RA0030008_SF_30.pdf PDF
Atch_28_-_Follow_on_Q&As.pdf PDF
Solicitation_Amendment_FA469019RA0030005_SF_30.pdf PDF
Atch_26_X-XX_PROJECT_TITLE.dwg DWG drawing
Atch_25_Site_Vist_Q&As_14FEB19.pdf PDF
Atch_24_Site_Visit_Minutes_24JAN19.pdf PDF
Solicitation_Amendment_FA469019RA0030003_SF_30.pdf PDF
Atch_23_Site_Visit_Minutes.pdf PDF
Solicitation_Amendment_FA469019RA0030001_SF_30.pdf PDF
Atch_20_FOPR_Construct_Bath_House_3JAN19.pdf PDF
Atch_18_Past_Performance_Information.docx DOCX document
Atch_22,_SECTION_M_-_EVALUATION_BASIS_FOR_AWARD_2JAN19.pdf PDF
Atch_5_Spec_Section_01800_-20_Aug_15.pdf PDF
Atch_11_Underground_Electrical_20Aug15.pdf PDF
Atch_16a_-_WD_SD180002_Residental-Penn_5_Jan_18.pdf PDF
Atch_1_Utility_Outages.pdf PDF
Atch_12_General_Provisions_-_8NOV18.pdf PDF
Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
Atch_20b_SOW_6NOV18.pdf PDF
Atch_17_Determination_of_Resp.pdf PDF
Atch_20_FOPR_Construct_Bath_House.pdf PDF
Atch_20c_Drawing_1_Track_Utilities_Latrine_6NOV18.pdf PDF
Atch_15_Non-Nuclear_Intrusion_Det.pdf PDF
Atch_20g_AF_Form_3052.xls XLS spreadsheet
Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
Atch_20d_RMD_KTR_to_Complete.pdf PDF
DRAFT_Atch_20f_Bid_Schedule-17_Oct_18.doc DOC document
DRAFT_Atch_13_NAFGeneral_Provisions-21Jan15.pdf PDF
DRAFT_Atch_16e_-_WD_SD180035_Building-Penn_5_Jan_18.pdf PDF
DRAFT_Atch_20_FOPR_Construct_Bath_House.docx DOCX document
DRAFT_Atch_18_Past_Performance_Information.docx DOCX document
DRAFT_Atch_17_Determination_of_Resp.pdf PDF
DRAFT_Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
DRAFT_Atch_20d_RMD_KTR_to_Complete.pdf PDF
DRAFT_Atch_21_SECTION_L_Instructions,_Conditions,_and_Notices_to_Offerors.pdf PDF
DRAFT_Atch_12_General_Provisions_-_8NOV18.pdf PDF
DRAFT_Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
DRAFT_Atch_20b_SOW_6NOV18.pdf PDF
DRAFT_Atch_16c_-_WD_SD180001_Heavy-Highway_6_Apr_18.pdf PDF
DRAFT_-_FA469019RA003.pdf PDF
DRAFT_Atch_8_Exterior_Signs_-_10_Jun_05.pdf PDF
DRAFT_Atch_19_PPQ.docx DOCX document
DRAFT_Atch_9_Submittal_Form_3000-1_Sep_03.pdf PDF
DRAFT_Atch_20a_GIPR_6NOV18.pdf PDF
DRAFT_Atch_22_SECTION_M_Evaluation_Factors.pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor’s Guide Items Submitted for Construction Projects

16 Jun 15

Ellsworth AFB SD

A. The following items are to be submitted to the base contracting office (as required) Located in the lower level, north end of the Rushmore Center Mail address: 28 CONS/LGCB

1000 Ellsworth Street, Suite 1200 Ellsworth AFB, SD 57706 - 4904

1. Questions regarding the IFB or RFP package

2. Bids or proposals in response to IFB or RFP

3. Signed contract / delivery order

4. SF 1413 (Sub-contractor statement and acknowledgement)

5. Bonds and proof of insurance

6. Acknowledgement of NTP for interim stages of design (Design-Build; D-B)

7. Interim and final design packages (D-B)

8. Proposed change of scope during design or construction (D-B)

9. Progress schedule (if construction period exceeds 60 calendar days & cost is over $150K)

10. Payroll reports

11. Requests for airfield access

12. IEAL (Installation Entry Authorization List) approval request

13. Request for final inspection

14. Personnel and vehicle passes at the project conclusion

B. The following items are to be submitted to the base civil engineering office (as required) Located in the Engineering Building Mail address: 28 CES/CEPM

2125 Scott Drive Ellsworth AFB, SD 57706 - 4711

1. Requests for clarification of requirements during design or construction (D-B)

2. Submittals - material, equipment, and test results

3. Draft copy of progress report for review prior to submitting with invoice in WAWF

4. Technical or logistical questions during construction

5. As-built drawings (draft and final)

6. Completed Real Property Checklist (Form 1354)

7. O & M Manuals

The following are to be submitted to both the contracting office and the civil engineering office

1. Work start notification

2. Copy of completed “digging permit”

Other: Invoices – submit via Wide Area Work Flow (WAWF)

Guide for Applying the 6 Percent Limit on Design Fee

The portion of the contract price for A-E services for the preparation of designs, plans, drawings and specifications may not exceed 6 percent of the project's Estimated Construction Cost. This limitation is statutory (10 U.S.C. 4540(b), 7212, and 9540. The cost of preparation of plans and specifications is discussed in FAR 15.404-4(c)(4)(i)(B) and 36.606(a) and DFARS 236.606-70 .

The 6% fixed fee includes:

• Design development

• Working drawings & specifications

• Post design contract services (clarification drawings & specifications)

• Preparation of bid package including detailed estimate

• Drawings and specifications for demolition

• Travel related to preparation/approval of design documents with a pre set number of trips

Exclusions to the Fixed Fee are:

• Pre-design programming

• Feasibility, functional, and economic studies

• Initial site visits

• Field, topographic, property, boundary, utility, and right-of-way surveys

• Subsurface explorations and borings, soils and materials testing, and resultant reports

• Flow gauging and model testing

• Reproduction of design documents for review purposes

• Preparation of construction cost estimates

• Comprehensive interior design (CID) services

• Preparation of general and feature design memoranda

• Models, renderings, or photographs of completed designs

• Construction-phase services

• Preparation or verification of as-built drawings during construction

• The services of consultants not specifically applied to the preparation of designs, plans, drawings, or specifications for a project

• Preparation of general and development criteria not specifically related to a military construction project

• Management and contract administration of A-E services contracts in connection with services excluded from the 6% limitation

• Document reproduction, travel, and per diem costs in connection with services excluded from the 6% limitation

• Preparation of environmental impact assessments, statements, and supporting data