This is an Amendment of Solicitation issued by the U.S. Air Force (FA4661) at Dyess Air Force Base in Texas. Amendment 0001, effective September 14, 2026, extends the proposal due date for Solicitation FA466126R0010 by three calendar days, moving the deadline from September 15, 2026 to September 18, 2026, with proposals due at 12:00 PM CST. All other terms and conditions of the original solicitation remain unchanged.

The solicitation requires a contractor to replace Substation Alpha Feeder Protection Relays at Building 11912 on Dyess AFB. The scope of work includes installing two new GE 850 Feeder Protection Relays (provided by the Government), wiring them in accordance with NEC/NETA standards, programming them to match the existing GE 760 relay settings, testing functionality without load, coordinating with the Electrical Shop for energization and commissioning, and conducting full-load testing with witnesses from Electrical, Contracting, and R&O personnel. A mandatory site visit is scheduled for September 1, 2026 at 1:00 PM CST. Questions must be submitted by September 8, 2026 at 12:00 PM CST. Proposals must include a cover page, technical section with draft progress schedule based on an 18 September work start date, proof of capability bonds, and a detailed pricing breakdown with identified major milestones. Contracting officers are 2d Lt Robert Albrightson (robert.albrightson@us.af.mil, 325-696-3864) and SrA Jesse Wisowaty (jesse.wisowaty@us.af.mil, 325-696-6043).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

J

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

14 Sep 2026

4. REQUISITION/PURCHASE

REQUISITION NUMBER

5. PROJECT NUMBER (if applicable)

6. ISSUED BY CODE FA4661

FA4661 7 CONS CD

381 3RD ST, CP 325 696 2285

DYESS AFB, TX 79607-1581

UNITED STATES

ROBERT ALBRIGHTSON, Email: robert.albrightson@us.af.mil Telephone: 3256963864 JESSE WISOWATY, Email: jesse.wisowaty@us.af.mil Telephone: 325-696-6043

7. ADMINISTERED BY (if other than Item 6)

CODE

SCD: PAS:

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)

CODE: FACILITY CODE:

9A. AMENDMENT OF SOLICITATION NUMBER

FA466126R0010

9B. DATED (SEE ITEM 11)

25 Aug 2026

10A. MODIFICATION OF CONTRACT/ORDER

NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; 1 or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required) See Section G - Contract Administration Data

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK

ONE

A.THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to:

1. Extend the Proposal due date by 3 calendar days changing from 21 calendar days (25 August 2026 - 15 September 2026) to 24 calendar days (25 August 2026 - 18 September 2026).

With proposals being due at 1200 CST.

2. All other terms and conditions remain unchanged.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Jesse Wisowaty

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

14 Sep 2026

Computer generated. Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA-FAR (48 CFR) 53.243

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section A - Solicitation/Contract Form

The following modifications were made:

Information From To

Contract Description

This is a solicitation for the requirement of properly replacing the Substation Alpha Feeder Protection Relays at Building 11912 on Dyess AFB. The Contractor shall install (2) NEW GE 850 Feeder Protection Relays which are provided by the Government. The contractor shall install and wire in (2) new Feeder Protection Relays in accordance with NEC/ NETA standards. The Contractor shall program the (2) new Feeder protection relays to match programming of the previously installed GE 760 relays, via settings provided by the Electrical shop and test functionality without load. The Contractor shall coordinate with the Electrical shop prior to energizing the primary voltage for testing and commissioning. The Contractor shall commission and test the two new relays with full base load once installed with witnesses from Electrical, Contracting and R&O. The Contractor will coordinate with the Electrical Shop before conducting any power outages for acceptance tests if needed.

SITE VISIT: A mandatory government site visit will be held at Building 11912 on Tuesday, 1 September 2026 at 1pm CST.

QUESTIONS: any questions whether technical or contractual in nature shall be submitted in writing. Questions must be submitted in writing to 2d Lt Robert Albrightson at robert.albrightson@us.af.mil and SrA Jesse Wisowaty at jesse.wisowaty@us.af.mil by Tuesday, 8 September 2026 by 12pm CST.

PROPOSALS: final proposals are due by Tuesday, 15 September 2026 by 12pm CST to 2d Lt Robert Albrightson at robert.albrightson@us.af.mil and SrA Jesse Wisowaty at jesse.wisowaty@us.af.mil. Late proposals will not be accepted.

This is a solicitation for the requirement of properly replacing the Substation Alpha Feeder Protection Relays at Building 11912 on Dyess AFB. The Contractor shall install (2) NEW GE 850 Feeder Protection Relays which are provided by the Government. The contractor shall install and wire in (2) new Feeder Protection Relays in accordance with NEC/ NETA standards. The Contractor shall program the (2) new Feeder protection relays to match programming of the previously installed GE 760 relays, via settings provided by the Electrical shop and test functionality without load. The Contractor shall coordinate with the Electrical shop prior to energizing the primary voltage for testing and commissioning. The Contractor shall commission and test the two new relays with full base load once installed with witnesses from Electrical, Contracting and R&O. The Contractor will coordinate with the Electrical Shop before conducting any power outages for acceptance tests if needed.

SITE VISIT: A mandatory government site visit will be held at Building 11912 on Tuesday, 1 September 2026 at 1pm CST.

QUESTIONS: any questions whether technical or contractual in nature shall be submitted in writing. Questions must be submitted in writing to 2d Lt Robert Albrightson at robert.albrightson@us.af.mil and SrA Jesse Wisowaty at jesse.wisowaty@us.af.mil by Tuesday, 8 September 2026 by 12pm CST.

PROPOSALS: final proposals are due by Friday, 18 September 2026 by 12pm CST to 2d Lt Robert Albrightson at robert.albrightson@us.af.mil and SrA Jesse Wisowaty at jesse.wisowaty@us.af.mil. Late proposals will not be accepted.

Response Due Time 01:00 PM 12:00 PM Response Due Date 04 Sep 2026 18 Sep 2026 Solicitation Number FA466126R0010 FA466126R00100001

Section L - Instructions, Conditions, & Notices to Offerors or Quoters

Header Miscellaneous Text (Modified):

Proposal Preparation Instructions:

The proposal shall be clear, concise, and include sufficient detail for effective evaluation and for substantiating the validity of stated claims. The proposal should not simply rephrase or restate the Government's requirements but, rather, shall provide convincing rationale to address how the Offeror intends to meet these requirements. Offerors shall assume that the Government has no prior knowledge of their facilities or experience and will base its evaluation on the information presented in the Offeror's proposal.

To ensure timely and equitable evaluation of proposals, Offerors must follow the instructions contained herein. Proposals must be complete, self-sufficient, and respond directly to the requirement of this solicitation.

Proposals shall be sent to 2nd Lt Robert Albrightson (robert.albrightson@us.af.mil) and SrA Jesse Wisowaty (jesse.wisowaty@us.af.mil).

1. Complete blocks 14 through 20C of the RFQ Section A, SF1442. In doing so, the Offeror accepts the contract terms and conditions as written in RFQ Sections A through K. Signature by the Offeror constitutes an offer, which the Government may accept. The "original" copy should be clearly marked under a separate cover. Complete pricing information in Section B of the solicitation.

2. Complete the Pricing Schedule utilizing the individual Statement of Work, technical factors, and Drawings. The total price proposed on the Pricing Schedule is the price that shall be honored by the Offeror who is awarded the resultant contract

FA466126R00100001

3. Complete the necessary fill-ins and certifications in Sections I through K. Section K shall be returned in its entirety. For Section F through I, the Offeror shall submit only those pages that require a fill-in.

4. Other than Certified Cost or Pricing Data may be requested by the Government, if necessary.

5. No price information should be included in the technical proposal.

Proposal response shall consist of the following:

Cover page on company letterhead (1 page)

Section I - Technical, to include: Draft Progress Schedule based on a 18 September work start date, completed RFP, proof of capability bonds.

Section II - Pricing Breakdown: Pricing Breakdown must be filled out on the attached Pricing Schedule document. In order to be determined Technically acceptable, the Vendor must clearly identify major milestones for the requirement. Restating or copying the statement of work will not meet this objective. Additionally, the vendor must meet all requirements outlined in the Statement of Work. Failure to meet any of the requirements outlined will result in a determination of technical unacceptability.

SITE VISIT: A mandatory government site visit will be held at Building 11912 on Tuesday, 1 September 2026 at 1pm CST.

QUESTIONS: any questions whether technical or contractual in nature shall be submitted in writing. Questions must be submitted in writing to 2d Lt Robert Albrightson at robert.albrightson@us.af.mil and SrA Jesse Wisowaty at jesse.wisowaty@us.af.mil by Tuesday, 8 September 2026 by 12pm CST.

PROPOSALS: Final proposals are due by Tuesday, 18 September 2026 by 12pm CST to 2d Lt Robert Albrightson at robert.albrightson@us.af.mil and SrA Jesse Wisowaty at jesse.wisowaty@us.af.mil. Late proposals will not be accepted.

FA466126R00100001

SUMMARY OF CHANGES
Solicitation/Contract Form
Instructions, Conditions, & Notices to Offerors or Quoters