4. Rewind Transformers - Questions and Answers.pdf
PDF 508 KB Posted
- Attached to
- Rewind - 100 KVA Single Phase Transformers
- Solicitation number
- FA466126Q0100
About this file
This document is a Questions and Answers file for a transformer rewind contract opportunity at Dyess Air Force Base.
The Government seeks to have transformers repaired through rewinding services at an offsite repair facility. The selected vendor is responsible for picking up the transformers from Dyess AFB, transporting them to an offsite repair shop, completing the rewind work, and returning the units to the base. The vendor bears all transportation costs and related expenses. The transformers are currently not in service and require repair; they are ready for transport. Data plate photographs are provided showing transformer specifications. The period of performance is 60 days after contract award, with no specific start date established. This is a brand-new contract with no incumbent contractor. No cost estimate, budget, or ballpark figure has been disclosed. The document includes photographs of three transformers with varying specifications, including ABB and Sundelt Solomon models with single-phase configurations and voltage ratings ranging from 100 KVA to 12470 Grdy/Y7200 HV with 240/120 LV specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 4. Rewind Transformers - Questions and Answers.pdf | ||
| Xformer Sunbelt 1.jpg | JPG image | |
| Xformer ABB 1.jpg | JPG image | |
| 1. Revised SOW.pdf | ||
| xformer ABB.jpg | JPG image | |
| Xformer Sunbelt.jpg | JPG image | |
| 1. Statement of Work.pdf | ||
| FA466126Q0100 RFQ.pdf | ||
| 1. Statement of Work.pdf | ||
| 2. Wage Determination 2015-5211.pdf | ||
| 3. Provisions and Clauses.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rewind Transformers – Questions and Answers
Technical Questions
1. Can we get a picture of the data plates?
Yes, pictures are attached.
2. Are the units in service or in storage?
The units are not in service as they need repair.
3. Could you please clarify whether the transformers are to be repaired/rewound at the Government-provided workspace at Dyess AFB, or whether the Vendor is expected to pick up and transport the transformers to its facility for repair and subsequently return them to the Government?
The transformers are to be picked up and taken to an offsite repair shop for the rewind and returned to Dyess AFB.
4. If being transported, are the units ready for transportation?
The units are ready for transport.
5. Is the bid recipient responsible for transportation to and from your location/inspector travel and lodging?
The bid recipient is responsible for the transport of the transformers and any expense that said transport incurs.
Contracting Questions
1. Is this a brand new contract OR if there is (was) an incumbent performing these services?
This will be a brand-new contract.
2. Is there a cost estimate, budget, or ballpark figure for the project listed?
That information is not available.
3. Is there an actual start date for the project?
There is no current start date, but the period of performance will be 60 Days After Date of Contract Award