SOW_SubAttachment_3-1_-_UFGS_02_41_00_ DEMOLITION_AND_DECONSTRUCTION .docx

DOCX document 29 KB Posted

Attached to
Carpet and Tile Amendment
Solicitation number
FA4661-14-R-0002
Issued by

About this file

SOW SubAttachment 3-1 Demolition and Construction

View the file

Other files

File Type Posted
Bid_Schedule_Clarification_MFR.pdf PDF
SOW_SubAttachment_6_-_UFGS_09_30_00_ CERAMIC_TILE _QUARRY_TILE _AND_PAVER_TILE .docx DOCX document
FA4661-14-R-0002-0004.pdf PDF
SOW_SubAttachment_3-2_-_UFGS_02_41_00_Atch_-_TX-AsbestosDemoNotifcationForm.pdf PDF
Bid_Schedule.pdf PDF
SOW_SubAttachment_2_-_UFGS_01_78_23_ OPERATION_AND_MAINTENANCE_DATA .docx DOCX document
SOW_SubAttachment_5_-_UFGS_09_06_90_ COLOR_SCHEDULE .docx DOCX document
SOW_SubAttachment_7_-_UFGS_09_65_00_ RESILIENT_FLOORING .docx DOCX document
SOW_SubAttachment_1_-_UFGS_01_33_00_ SUBMITTAL_PROCEDURES .docx DOCX document
SOW_SubAttachment_4_-_UFGS_07_92_00_ JOINT_SEALANTS .docx DOCX document
SOW_SubAttachment_8_-_UFGS_09_68_00_ CARPET .docx DOCX document
FA4661-14-R-0002_-_Q A_Response.pdf PDF
FA4661-14-R-0002-0003_Amendment.pdf PDF
FA4661-14-R-0002_Amendment_0002.pdf PDF
Corrected_Attachment_4_Site_Visit_Reservation_Form.doc DOC document
Corrected_Attachment_5_Question_Form.doc DOC document
FA4661-14-R-0002_Amendment_00001.pdf PDF
Pre_Bid_Site_Visit_Attendance_Roster.pdf PDF
Attachment_3.pdf PDF
14-R-0002_FINAL_Solicitation.doc DOC document
Attachment_2_WD.pdf PDF
13-R-0003_Attachment_4_Reservation_Form.pdf PDF
Attachment_1_Scope_of_Work_FY-14_Carpet-Tile_IDIQ.pdf PDF
13-R-0003_Attachment_5_Question_Form.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UFGS-02 41 00

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION TABLE OF CONTENTS DIVISION 02 - EXISTING CONDITIONS SECTION 02 41 00

DEMOLITION AND DECONSTRUCTION

November 2013

PART 1 GENERAL

1.1REFERENCES
1.2PROJECT DESCRIPTION
1.2.1Demolition/Deconstruction Plan
1.2.2General Requirements
1.3ITEMS TO REMAIN IN PLACE
1.3.1Existing Construction Limits and Protection
1.3.2Weather Protection
1.3.3Trees
1.3.4Utility Service
1.3.5Facilities
1.4BURNING
1.5AVAILABILITY OF WORK AREAS
1.6SUBMITTALS
1.7QUALITY ASSURANCE
1.7.1Texas Requirements
1.7.2Dust [and Debris] Control
1.8PROTECTION
1.8.1Traffic Control Signs
1.8.2Protection of Personnel
1.9FOREIGN OBJECT DAMAGE (FOD)
1.10RELOCATIONS
1.11EXISTING CONDITIONS

PART 2 PRODUCTS

2.1FILL MATERIAL PART 3EXECUTION
3.1EXISTING FACILITIES TO BE REMOVED
3.1.1Structures
3.1.2Utilities and Related Equipment
3.1.2.1General Requirements
3.1.2.2Disconnecting Existing Utilities

SECTION 02 41 00

Page of 8

3.1.3Chain Link Fencing
3.1.4Paving and Slabs
3.1.5Roofing
3.1.5.1Temporary Roofing
3.1.5.2Reroofing
3.1.6Masonry
3.1.7Concrete
3.1.8Structural Steel
3.1.9Miscellaneous Metal
3.1.10Carpentry
3.1.11Carpet
3.1.12Acoustic Ceiling Tile
3.1.13Airfield Lighting
3.1.14Patching
3.1.15Air Conditioning Equipment
3.1.16Cylinders and Canisters
3.1.17Locksets on Swinging Doors
3.1.18Mechanical Equipment and Fixtures
3.1.18.1Preparation for Storage
3.1.18.2Piping
3.1.18.3Ducts
3.1.18.4Fixtures, Motors and Machines
3.1.19Electrical Equipment and Fixtures
3.1.19.1Fixtures
3.1.19.2Electrical Devices
3.1.19.3Wiring Ducts or Troughs
3.1.19.4Conduit and Miscellaneous Items
3.1.20Elevators and Hoists
3.1.21Items With Unique/Regulated Disposal Requirements
3.2CONCURRENT EARTH-MOVING OPERATIONS
3.3DISPOSITION OF MATERIAL
3.3.1Title to Materials
3.3.2Reuse of Materials and Equipment
3.3.3Salvaged Materials and Equipment
3.3.4Debris Disposal in the San Diego Area
3.3.5Disposal of Ozone Depleting Substance (ODS)
3.3.5.1Special Instructions
3.3.5.2Fire Suppression Containers
3.3.6Transportation Guidance
3.3.7Unsalvageable and Non-Recyclable Material
3.4CLEANUP
3.5DISPOSAL OF REMOVED MATERIALS
3.5.1Regulation of Removed Materials
3.5.2Burning on Government Property
3.5.3Removal to Spoil Areas on Government Property
3.5.4Removal from Government Property
3.6REUSE OF SALVAGED ITEMS

ATTACHMENTS:

Texas State Asbestos/Demolition Notification Form

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.6 (2006) Safety Requirements for Demolition Operations

CARPET AND RUG INSTITUTE (CRI)

CRI CIS (2011) Carpet Installation Standard

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008; Errata 1-2010; Changes 1-3 2010; Changes 4-6 2011; Change 7 2012) Safety and Health Requirements Manual

U.S. DEPARTMENT OF DEFENSE (DOD)

DOD 4000.25-1-M (2006) MILSTRIP - Military Standard Requisitioning and Issue Procedures

MIL-STD-129 (2007; Rev P; Change 4 2007) Military Marking for Shipment and Storage

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

40 CFR 61 National Emission Standards for Hazardous Air Pollutants

40 CFR 82 Protection of Stratospheric Ozone

1.2 PROJECT DESCRIPTION

1.2.1 Demolition/Deconstruction Plan

Prepare a Demolition Plan and submit proposed demolition and removal procedures for approval before work is started. Include in the plan procedures for careful removal and disposition of materials specified to be salvaged, coordination with other work in progress. Identify components and materials to be salvaged for reuse or recycling with reference to paragraph Existing Facilities to be Removed. Append tracking forms for all removed materials indicating type, quantities, condition, destination, and end use. Coordinate with Waste Management Plan. Provide procedures for safe conduct of the work in accordance with EM 385-1-1. Plan shall be approved by Contracting Officer prior to work beginning.

1.2.2 General Requirements

Do not begin demolition or deconstruction until authorization is received from the Contracting Officer. The work of this section is to be performed in a manner that maximizes the value derived from the salvage and recycling of materials. Remove rubbish and debris from the project site; do not allow accumulations inside or outside the building[s]. The work includes demolition, salvage of identified items and materials, and removal of resulting rubbish and debris. Remove rubbish and debris from Government property daily, unless otherwise directed. Store materials that cannot be removed daily in areas specified by the Contracting Officer. In the interest of occupational safety and health, perform the work in accordance with EM 385-1-1, Section 23, Demolition, and other applicable Sections.

1.3 ITEMS TO REMAIN IN PLACE

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the Contracting Officer. Coordinate the work of this section with all other work indicated.

1.3.1 Existing Construction Limits and Protection

Do not disturb existing construction beyond the extent indicated or necessary for installation of new construction.

1.3.2 Reserved.

1.3.3 Reserved.

1.3.4 Reserved.

1.3.5 Reserved.

1.4 BURNING

The use of burning at the project site for the disposal of refuse and debris will not be permitted.

1.5 AVAILABILITY OF WORK AREAS

Areas in which the work is to be accomplished will be coordinated and scheduled with facility manager and construction inspector.

1.6 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Existing Conditions

SD-07 Certificates

Notification of Demolition and Renovation form

SD-11 Closeout Submittals

Receipts

1.7 QUALITY ASSURANCE

Submit timely notification of demolition and renovation projects to Federal, State, regional, and local authorities in accordance with 40 CFR 61, Subpart M. When required notify the State's environmental protection agency and the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61, Subpart M. Comply with federal, state, and local hauling and disposal regulations. In addition to the requirements of the "Contract Clauses," conform to the safety requirements contained in ASSE/SAFE A10.6. Comply with the Environmental Protection Agency requirements specified.

1.7.1 Texas Requirements

"Notification of Asbestos/Demolition" form is required for all demolition and deconstruction involving asbestos work.

Contractor shall comply with current requirements U.S. Environmental Protection Agency (EPA) regulations, OSHA Occupational Exposure to Asbestos Standard’s Permissible Exposure Limits (PEL), Texas and local regulations when working with and disposing of asbestos-containing resilient floor covering materials and associated adhesive. Removal of asbestos does not include wooden sub-surfaces. See Technical Provisions Section 1C – Environmental Protection.

1.7.2 Reserved.

1.8 PROTECTION

1.8.1 Reserved.

1.8.2 Protection of Personnel

Before, during and after the demolition work continuously evaluate and take immediate action to protect all personnel working in and around the project site.

1.9 Reserved.

1.10 Reserved.

1.11 EXISTING CONDITIONS

Before beginning any demolition or deconstruction work, survey the site and examine the drawings and specifications to determine the extent of the work.

PART 2 PRODUCTS

2.1 Reserved.

PART 3 EXECUTION

3.1 Reserved.

3.1.1 Reserved.

3.1.2 Reserved.

3.1.2.1 Reserved.

3.1.2.2 Reserved.

3.1.3 Reserved.

3.1.4 Reserved.

3.1.5 Reserved.

3.1.5.1 Reserved.

3.1.5.2 Reserved.

3.1.6 Reserved.

3.1.7 Reserved.

3.1.8 Reserved.

3.1.9 Reserved.

3.1.10 Reserved.

3.1.11 Carpet

Remove existing carpet for reclamation in accordance with manufacturer recommendations and as follows. Remove used carpet in large pieces, roll tightly, and pack neatly in a container. Remove adhesive according to recommendations of the Carpet and Rug Institute (CRI). Adhesive removal solvents shall comply with CRI CIS. Recycle removed carpet cushion.

3.1.12 Reserved.

3.1.13 Reserved.

3.1.14 Reserved.

3.1.15 Reserved.

3.1.16 Reserved.

3.1.17 Reserved.

3.1.18 Reserved.

3.1.18.1 Reserved.

3.1.18.2 Reserved.

3.1.18.3 Reserved.

3.1.18.4 Reserved.

3.1.19 Reserved.

3.1.19.1 Reserved.

3.1.19.2 Reserved.

3.1.19.3 Reserved.

3.1.19.4 Reserved.

3.1.20 Reserved.

3.1.21 Reserved.

3.2 Reserved.

3.3 DISPOSITION OF MATERIAL

3.3.1 Title to Materials

Except for salvaged items specified in related Sections, and for materials or equipment scheduled for salvage, all materials and equipment removed and not reused or salvaged, shall become the property of the Contractor and shall be removed from Government property.Title to materials resulting from demolition and deconstruction, and materials and equipment to be removed, is vested in the Contractor upon approval by the Contracting Officer of the Contractor's demolition, deconstruction, and removal procedures, and authorization by the Contracting Officer to begin
demolition and deconstruction.The Government will not be responsible for the condition or loss of, or damage to, such property after contract
award.Showing for sale or selling materials and equipment on site is prohibited.

3.3.2 Reserved.

3.3.3 Salvaged Materials and Equipment

a. Salvage items and material to the maximum extent possible.

b. Store all materials salvaged for the Contractor as approved by the Contracting Officer and remove from Government property before completion of the contract. On site sales of salvaged material is prohibited.

c. Reserved.

d. Reserved.

e. Reserved.

f. Reserved.

3.3.4 Reserved.

3.3.5 Reserved.

3.3.5.1 Reserved.

3.3.5.2 Reserved.

3.3.6 Reserved.

3.3.7 Reserved.

3.4 CLEANUP

Remove and transport debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

3.5 DISPOSAL OF REMOVED MATERIALS

3.5.1 Regulation of Removed Materials

Dispose of debris, rubbish, scrap, and other nonsalvageable materials resulting from removal operations with all applicable federal, state and local regulations as contractually specified off Dyess AFB.

3.5.2 Burning on Government Property

Burning of materials removed from demolished and deconstructed structures will not be permitted on Government property.

3.5.3 Reserved.

3.5.4 Reserved.

3.6 Reserved.