UFGS-01 33 00
UNIFIED FACILITIES GUIDE SPECIFICATIONS
SECTION TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS SECTION 01 33 00
SUBMITTAL PROCEDURES
November 2013
PART 1 GENERAL
| 1.1 | SUMMARY |
| 1.2 | DEFINITIONS |
| 1.2.1 | Submittal Descriptions (SD) |
| 1.2.2 | Approving Authority |
| 1.2.3 | Work |
| 1.3 | SUBMITTALS |
| 1.4 | SUBMITTAL CLASSIFICATION |
| 1.4.1 | Designer of Record Approved (DA) |
| 1.4.2 | Government Approved [G] |
| 1.4.3 | Government Conformance Review of Design (CR) |
| 1.4.4 | Designer of Record Approved/Government Conformance Review |
(DA/CR)
| 1.4.4.1 | Deviations to the Accepted Design |
| 1.4.4.2 | Substitutions |
| 1.4.5 | Designer of Record Approved/Government Approved (DA/GA) |
| 1.4.6 | Information Only |
| 1.5 | FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL |
| 1.5.1 | Submittals Required from the Contractor |
| 1.5.1.1 | Reserved |
| 1.5.1.2 | Reserved |
| 1.5.1.3 | Reserved |
| 1.6 | PREPARATION |
| 1.6.1 | Transmittal Form |
| 1.6.2 | Identifying Submittals |
| 1.6.3 | Format for SD-02 Shop Drawings |
| 1.6.4 | Format of SD-03 Product Data and SD-08 Manufacturer's |
Instructions
| 1.6.5 | Format of SD-04 Samples |
| 1.6.6 | Reserved |
| 1.6.7 | Reserved |
| 1.6.8 | Format of SD-10 Operation and Maintenance Data (O&M) |
| 1.6.9 | Reserved |
| 1.7 | QUANTITY OF SUBMITTALS |
SECTION 01 33 00
Page of 13
| 1.7.1 | Number of Copies of SD-02 Shop Drawings |
| 1.7.2 | Number of Copies of SD-03 Product Data and SD-08 |
| Manufacturer's | Instructions |
| 1.7.3 | Number of Samples SD-04 Samples |
| 1.7.4 | Reserved |
| 1.7.5 | Reserved |
| 1.7.6 | Number of Copies of SD-10 Operation and Maintenance Data |
| 1.7.7 | Reserved |
| 1.8 | INFORMATION ONLY SUBMITTALS |
| 1.9 | VARIATIONS |
| 1.9.1 | Considering Variations |
| 1.9.2 | Proposing Variations |
| 1.9.3 | Warranting That Variations Are Compatible |
| 1.9.4 | Review Schedule Is Modified |
| 1.10 | Reserved |
| 1.10.1 | Reserved |
| 1.10.2 | Reserved |
| 1.10.3 | Reserved |
| 1.10.4 | Reserved |
| 1.10.4.1 | Reserved |
| 1.10.4.2 | Reserved |
| 1.10.5 | Reserved |
| 1.11 | Reserved |
| 1.11.1 | Reserved |
| 1.11.2 | Reserved |
| 1.11.3 | Reserved |
| 1.11.4 | Reserved |
| 1.12 | GOVERNMENT APPROVING AUTHORITY |
| 1.12.1 | Review Notations |
| 1.13 | DISAPPROVED[ OR REJECTED] SUBMITTALS |
| 1.14 | APPROVED[/ACCEPTED] SUBMITTALS |
| 1.15 | APPROVED SAMPLES |
| 1.16 | WITHHOLDING OF PAYMENT |
| 1.17 | PROGRESS SCHEDULE |
| 1.17.1 | Reserved |
| 1.17.2 | Reserved |
| 1.18 | Reserved |
| 1.19 | Reserved |
PART 2 PRODUCTS PART 3 EXECUTION
PART 1 GENERAL
1.1 SUMMARY
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittals requirements are specified in the technical sections.
Submittals are identified by Submittal Description (SD) numbers and titles as follows:
SD-01 Preconstruction Submittals
Submittals which are required prior to start of construction (work) issuance of contract notice to proceed or commencing work on site or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.
List of proposed products Construction progress schedule Schedule of prices Health and safety plan Work plan Quality Control (QC) plan Environmental protection plan
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
SD-04 Samples
Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.
Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.
Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.
SD-08 Manufacturer's Instructions Preprinted material describing installation of a product, system or material, including special notices and (MSDS)concerning impedances, hazards and safety precautions.
SD-10 Operation and Maintenance Data
Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
1.2.2 Approving Authority
Office or designated person authorized to approve submittal.
1.2.3 Work
As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
| 1.4 | SUBMITTAL CLASSIFICATION Submittals are classified as follows: |
| 1.4.1 | Designer of Record Approved (DA) |
| Designer of Record (DOR) approval is required for extensions of design, critical materials, any deviations from the solicitation, the accepted proposal, or the completed design, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. | Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings." | Contractor to provide the Government with the number of copies designated hereinafter of all DOR approved submittals. | The Government may review any or all Designer of Record approved submittals for conformance to the Solicitation, Accepted Proposal and the completed |
| design. | The Government will review all submittals designated as deviating from the Solicitation or Accepted Proposal, as described below. | Design |
submittals to be in accordance with Section 01 33 16 DESIGN AFTER AWARD. Generally, design submittals should be identified as SD-05 Design Data submittals.
1.4.2 Government Approved [G]
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.4.3 Government Conformance Review of Design (CR)
The Government will review all intermediate and final design submittals for conformance with the technical requirements of the solicitation. Section 01 33 16 DESIGN AFTER AWARD covers the design submittal and review process in detail. Review will be only for conformance with the applicable codes, standards and contract requirements. Design data includes the design documents described in Section 01 33 16 DESIGN AFTER AWARD. Generally, design submittals should be identified as SD-05 Design Data submittals.
1.4.4 Designer of Record Approved/Government Conformance Review (DA/CR)
1.4.4.1 Deviations to the Accepted Design
Designer of Record approval and the Government's concurrence are required for any proposed deviation from the accepted design which still complies with the contract before the Contractor is authorized to proceed with material acquisition or installation. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction", they are considered to be "shop drawings." If necessary to facilitate the project schedule, the Contractor and the DOR may discuss a submittal proposing a deviation with the Contracting Officer's Representative prior to officially submitting it to the Government. However, the Government reserves the right to review the submittal before providing an opinion, if deemed necessary. In any case, the Government will not formally agree to or provide a preliminary opinion on any deviation without the DOR's approval or recommended approval. The Government reserves the right to non-concur with any deviation from the design, which may impact furniture, furnishings, equipment selections or operations decisions that were made, based on the reviewed and concurred design.
1.4.4.2 Substitutions
| Unless prohibited or provided for otherwise elsewhere in the Contract, where the accepted contract proposal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, and the Contractor desires to substitute manufacturer or model after award, submit a requested substitution for Government concurrence. | Include substantiation, identifying information |
| and the DOR's approval, as meeting the contract requirements and that it is equal in function, performance, quality and salient features to that in the accepted contract proposal. | If the Contract otherwise prohibits substitutions of equal named products, systems, materials or equipment by manufacturer, brand name and/or by model number or other specific identification, the request is considered a "variation" to the contract. Variations are discussed below in paragraphs: "Designer of Record Approved/Government Approved" and "VARIATIONS." |
1.4.5 Designer of Record Approved/Government Approved (DA/GA)
In addition to the above stated requirements for proposed deviations to the accepted design, both Designer of Record and Government Approval and, where applicable, a contract modification are required before the Contractor is authorized to proceed with material acquisition or installation for any proposed variation to the contract (the solicitation and/or the accepted proposal), which constitutes a change to the contract terms. Within the terms of the Contract Clause entitled, "Specifications and Drawings for Construction," they are considered to be "shop drawings." The Government reserves the right to accept or reject any such proposed deviation at its discretion.
1.4.6 Information Only
Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring Designer of Record or Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.5 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.5.1 Submittals Required from the Contractor
As soon as practicable after award of contract, and before procurement forward to the Contracting Officer submittals required in the technical sections of this specification, including shop drawings, product data and samples.
1.5.1.1 Reserved.
1.5.1.2 Reserved.
1.5.1.3 Reserved.
1.6 PREPARATION
1.6.1 Transmittal Form
Transmit each submittal to the contracting officer.
Use AF Form 3000 for submitting both Government approved and information only submittals.
1.6.2 Identifying Submittals
Identify submittals, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location.
b. Construction contract number.
c. Date of the drawings and revisions.
d. Reserved.
e. Section number of the specification section by which submittal is required.
f. Submittal description (SD) number of each component of submittal.
g. When a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission.
h. Reserved.
1.6.3 Format for SD-02 Shop Drawings
Shop drawings are not to be less than 210 by 297 mm (8 1/2 by 11 inches) nor more than 1189 by 841 mm (30 by 42 inches). Prepare drawings to accurate size, with scale indicated, unless other form is required. Drawings are to be suitable for reproduction and be of a quality to produce clear, distinct lines and letters with dark lines on a white background.
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled, "Identifying Submittals," of this section.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location adjacent to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
1.6.4 Format of SD-03 Product Data and SD-08 Manufacturer's Instructions
Indicate, by prominent notation, each product which is being submitted; indicate specification section number and paragraph number to which it pertains.
Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry and technical society publication references.
Where equipment or materials are specified to conform to industry and technical society reference standards of the organizations such as American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), and Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal and marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically.
Submit manufacturer's instructions prior to installation.
1.6.5 Format of SD-04 Samples
Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as specified:
a. Reserved
b. Sample of Materials Less Than 50 by 75 mm (2 by 3 inches): Built up to 210 by 297 mm (8 1/2 by 11 inches).
c. Sample of Materials Exceeding 210 by 297 mm (8 1/2 by 11 inches): Cut down to 210 by 297 mm (8 1/2 by 11 inches) and adequate to indicate color, texture, and material variations.
d. Reserved.
e. Reserved.
f. Color Selection Samples: 50 by 100 mm (2 by 4 inches). Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard unit.
g. Reserved.
h. Reserved.
1.6.6 Reserved.
1.6.7 Reserved.
1.6.8 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.
1.6.9 Reserved.
1.7 QUANTITY OF SUBMITTALS
1.7.1 Number of Copies of SD-02 Shop Drawings
Submit three copies of submittals of shop drawings requiring review and approval only by Government.
1.7.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions
Submit in compliance with quantity requirements specified for shop drawings.
1.7.3 Number of Samples SD-04 Samples
a. Submit one sample, or one set of samples showing range of variation, of each required item.
b. Reserved.
| c. | Reserved. |
| d. | Reserved. |
| 1.7.4 | Reserved. |
1.7.5 Reserved.
1.7.6 Number of Copies of SD-10 Operation and Maintenance Data
Submit two copies of O&M Data to the Contracting Officer for review and approval.
1.7.7 Reserved.
1.8 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.
The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.9 VARIATIONS
Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.
1.9.1 Considering Variations
Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.
1.9.2 Proposing Variations
When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
1.9.3 Warranting That Variations Are Compatible
When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.9.4 Review Schedule Is Modified
In addition to normal submittal review period, a period of five working days will be allowed for consideration by the Government of submittals with variations.
1.10 Reserved.
1.10.1 Reserved.
1.10.2 Reserved.
1.10.3 Reserved.
1.10.4 Reserved.
1.10.4.1 Reserved.
1.10.4.2 Reserved.
1.10.5 Reserved.
1.11 Reserved.
1.11.1 Reserved.
1.11.2 Reserved.
1.11.3 Reserved.
1.11.4 Reserved.
1.12 GOVERNMENT APPROVING AUTHORITY
When approving authority is Contracting Officer, the Government will:
a. Note date on which submittal was received from QC Manager.
b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph entitled, "Review Notations," of this section and with markings appropriate for action indicated.
Upon completion of review of submittals requiring Government approval, stamp and date approved submittals. One copy of the approved submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor.
1.12.1 Review Notations
Contracting Officer review will be completed within 21 calendar days after date of submission. Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.
b. Submittals marked "approved as noted" "or approved except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.
c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.
d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
1.13 DISAPPROVED [OR REJECTED] SUBMITTALS
Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes," is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.14 APPROVED [ACCEPTED] SUBMITTALS
The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.
Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work design, dimensions, all design extensions, such as the design of adequate connections and details, etc., and the satisfactory construction of all work.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.15 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
Match the approved samples for materials and equipment incorporated in the work.
Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.
Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals. Contractor to replace such materials or equipment to meet contract requirements.
Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.
1.16 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained. No payment for materials incorporated in the work will be made if all required Designer of Record or required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
1.17 PROGRESS SCHEDULE
AF Form 3064, Contract Progress Schedule (AFFM 3064). The Contractor shall submit to the CO for approval within 10 calendar days after the NTP for all T.O.’s with a performance period greater than 60 calendar days, unless otherwise specified by the CO, IAW FAR 52.236-15 Schedules for Construction Contracts.
The Contractor shall develop each AFFM 3064 to reflect particulars for each T.O. and the parameters of the NTP. The Contractor shall breakdown all work into measurable elements, entering these in logical order on the form.
a. All work element line entry percentages shall reflect negotiated costs, and shall not be entered front-loaded.
b. All T.O.s will indicate as a minimum the final 5% of a project for post construction/pre-final inspection closeout items.
c. Any partial progress payments for materials, as approved by the CO, shall be entered separately on the AFFM 3064.
Multiple Facilities/Phased Schedules. When a project consists of multiple facilities, and/or divided into phased construction within a single T.O., these instances shall be considered as T.O. phases. The Contractor shall provide for approval to the CO a separate AFFM 3064 for each phase and its apportioned project percentage. In addition, the Contractor shall include an accumulative AFFM 3064 summarizing all phases of the T.O. to equal 100%.
1.17.1 Reserved.
1.17.2 Reserved.
1.18 Reserved.
1.19 Reserved.
| PART 2 | PRODUCTS Not Used |
| PART 3 | EXECUTION Not Used |
-- End of Section --