This is a pricing template for a GFAFB Snow/Ice Removal contract. The contract spans five years, consisting of a base year (1 October 2026 – 30 September 2027) and four option years (1 October 2027 – 30 September 2030 and 1 October 2030 – 30 September 2031). The contract requires contractors to provide snow and ice removal services for both streets and parking lots across three priority levels.

Each contract period contains six Contract Line Item Numbers (CLINs) covering Priority 1, Priority 2, and Priority 3 Street Removal services and Priority 1, Priority 2, and Priority 3 Parking Lots services. All services are quoted on a monthly basis for seven months of performance per contract year. Contractors must provide unit prices and total costs for each CLIN, with grand totals calculated for each contract year and an overall grand total for the base year plus all four option years. All pricing fields are currently blank, indicating this is a template awaiting contractor proposals. The template does not specify pricing terms, evaluation criteria, or other contractual details beyond the service categories and performance periods.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN Description Qty Unit Unit Price Total Cost 0001 Priority 1 Street Removal 7 Mo -$ -$ 0002 Priority 2 Street Removal 7 Mo -$ -$ 0003 Priority 3 Street Removal 7 Mo -$ -$ 0004 Priority 1 Parking Lots 7 Mo -$ -$ 0005 Priority 2 Parking Lots 7 Mo -$ -$ 0006 Priority 3 Parking Lots 7 Mo -$ -$ Base Year Grand Total: -$

CLIN Description Qty Unit Unit Price Total Cost 1001 Priority 1 Street Removal 7 Mo -$ -$ 1002 Priority 2 Street Removal 7 Mo -$ -$ 1003 Priority 3 Street Removal 7 Mo -$ -$ 1004 Priority 1 Parking Lots 7 Mo -$ -$ 1005 Priority 2 Parking Lots 7 Mo -$ -$ 1006 Priority 3 Parking Lots 7 Mo -$ -$ 1st Option Year Grand Total: -$

CLIN Description Qty Unit Unit Price Total Cost 2001 Priority 1 Street Removal 7 Mo -$ -$ 2002 Priority 2 Street Removal 7 Mo -$ -$ 2003 Priority 3 Street Removal 7 Mo -$ -$ 2004 Priority 1 Parking Lots 7 Mo -$ -$ 2005 Priority 2 Parking Lots 7 Mo -$ -$ 2006 Priority 3 Parking Lots 7 Mo -$ -$ 2nd Option Year Grand Total: -$

CLIN Description Qty Unit Unit Price Total Cost 3001 Priority 1 Street Removal 7 Mo -$ -$

2nd Option Year

Base Year 1 Oct 2026 - 30 Sep 2027

GFAFB Snow/Ice Removal

1st Option Year 1 Oct 2027 - 30 Sep 2028

1 Oct 2028 - 30 Sep 2029

3rd Option Year 1 Oct 2029 - 30 Sep 2030

3002 Priority 2 Street Removal 7 Mo -$ -$ 3003 Priority 3 Street Removal 7 Mo -$ -$ 3004 Priority 1 Parking Lots 7 Mo -$ -$ 3005 Priority 2 Parking Lots 7 Mo -$ -$ 3006 Priority 3 Parking Lots 7 Mo -$ -$ 2nd Option Year Grand Total: -$

CLIN Description Qty Unit Unit Price Total Cost 4001 Priority 1 Street Removal 7 Mo -$ -$ 4002 Priority 2 Street Removal 7 Mo -$ -$ 4003 Priority 3 Street Removal 7 Mo -$ -$ 4004 Priority 1 Parking Lots 7 Mo -$ -$ 4005 Priority 2 Parking Lots 7 Mo -$ -$ 4006 Priority 3 Parking Lots 7 Mo -$ -$ 4th Option Year Grand Total: -$

GRAND TOTAL BASE PLUS 4 OPTION YEARS -$

4th Option Year 1 Oct 2030 - 30 Sep 2031