This document is a Questions and Answers (Q&A) addendum for Solicitation FA465426Q0007 regarding the Grissom Air Reserve Base Tank Replacement Project, dated June 30, 2026. The Q&A addresses eight inquiries from potential contractors regarding project specifications and government responsibilities.
Key details include: the replacement tank weighs 1,450 lbs per manufacturer specifications, while the weight of the existing tank is unknown. The contractor is responsible for cleaning the tank interior from the top down to remove residual material and debris prior to pumping contents into drums, but steam cleaning is not required. The government will handle disposal of government-furnished barrels containing residual liquid and waste. The contractor must provide all materials necessary for connection to existing infrastructure, including piping, unions, and parts, as the government has none available. Bonding is not required for this project. Base-specific recycling procedures and a map or latitude/longitude coordinates of the building location will be provided to the contractor following contract award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Grissom ARB 6/30/26
Solicitation FA465426Q0007
Grissom ARB Tank Replacement Project:
Additional Questions & Answers
1.
Q: What is the weight of the existing tank?
A: Unknown
2.
Q: What is the weight of the replacement tank?
A: Manufacturer specs state 1,450 lbs.
3.
Q: Will the Government furnished barrels for residual liquid/waste remain left on site for in the parking lot for disposal by the Government, or will the Contractor be responsible for disposal?
A: Disposal will be done by the government.
4.
Q: Will the Contractor be required to steam clean the tank prior to delivery to the base recycling center?
A: Steam cleaning is not required; tank only needs to be cleaned from the top down (interior) of any residual material/debris prior to pumping into drums.
5.
Q: Can the base's local recycling procedures be provided?
A: These can be provided to the Contractor following award.
Grissom ARB 6/30/26
6.
Q: Will any/all materials necessary for connection to existing infrastructure be provided by the Government?
A: Government does not have any piping/unions/parts for the installation/reconnection of piping to the tank.
7.
Q: Will bonding be required for this project?
A: N/A
8.
Q: Can a map or lat/long of building be provided?
A: A map will be provided to the Contractor following award.