This document is a Quality Assurance Surveillance Plan (QASP) for a cabling requirement contract at Malmstrom Air Force Base, issued by the 341st Communication Squadron on August 18, 2026. The contract augments Inside Plant/Outside Plant (ISP/OSP) services to support communications infrastructure at Malmstrom AFB and the missile complex in response to increased workload demands.
The QASP establishes oversight procedures for monitoring contractor performance against contract standards through continuous surveillance activities. Key performance objectives include excellent customer service to base engineering offices and Malmstrom leadership, project schedule management with accurate proposals and timely notifications, quality technical products and deliverables that are complete and accurate, schedule compliance with major and minor milestones, and effective communication. The Contracting Officer is Charles McClintic (341 CONS), the Contracting Officer's Representative is Ed Stuart (341 CS), and the Quality Assurance Program Coordinator is Edsa L. Artates (341 CONS). The COR employs multiple surveillance methodologies including periodic inspection using checklists, review of reports for editorial and substantive flaws, technical inspection of actual work, and quarterly verification of non-service summary items. Performance is rated on a five-tier scale from Excellent/Outstanding to Unsatisfactory. The document provides specific remedies for non-conformance: minor discrepancies are documented on Performance Assessment Reports (PARs) with 10-day correction periods; three combined minor discrepancies escalate to Corrective Action Reports (CARs) with 30-calendar-day correction periods or up to six months for complex issues. Annual performance assessments are submitted to the Contractor Performance Assessment Reporting System (CPARS), and disputes are addressed through Alternate Dispute Resolution procedures before Contracting Officer final decisions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PMI.pdf | ||
| WAGE DETERMINATION.pdf | ||
| Questions and Answers.pdf | ||
| Solicitation Amendment - FA462626Q00350001.pdf | ||
| Solicitation Amendment FA462626Q00350001 SF 30.pdf | ||
| Solicitation - FA462626Q0035.pdf | ||
| Cabling Requirement Contract PWS.pdf | ||
| FA462626Q0035 - PPQ Title Page.pdf | ||
| FA462626Q0035 - PPQ.docx | DOCX document | |
| Cabling Price Sheet.xlsx | XLSX spreadsheet | |
| Cable Mock Project Small Med Lg.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CABLING REQUIREMENT CONTRACT
10 August 2026
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
FOR
CABLE REQUIREMENT CONTRACT
341st Communication Squadron
Malmstrom AFB
DATE: 18 August 2026
Reviewed and Approved by:
Mr. ED STUART
341 CS/ COR
Mr. TERRY WOODARD
341 CS/COR SUPERVISOR
Mr. CHARLES MCCLINTIC
341 CONS/Contracting Officer
Ms. EDSA L. ARTATES
341 CONS/QAPC
Table of Contents
1. Background, Vision, and Mission
2. QASP Purpose
3. Authority
4. Roles and Responsibilities
Government Personnel
Contracting Officer (CO)
Contracting Officer’s Representative (COR)
Contracting Officer’s Representatives Supervisor
Acquisition Management Support Specialist (AMSS)
Quality Assurance Program Coordinator (QAPC)
Contractor Personnel
5. Performance Requirements and Method of Surveillance
Contract Surveillance
Surveillance Matrix
Performance Rating Definitions
Performance Reporting
Appendix 1 - Surveillance Matrix (SERVICE SUMMARY)
CORRECTIVE ACTION REPORT (CAR)
CUSTOMER COMPLAINT RECORD
PERFORMANCE ASSESSMENT REPORT (PAR)
ACRONYMS AND ABBREVIATIONS LIST
Acronym/Abbreviation Definition
ADR Alternate Disputes Resolution
AFGSC Air Force Global Strike Command
AMSS Acquisition Management Support Specialist
AQL Acceptable Quality level
CAR Corrective Action Report
CDRL Contract Data Requirements List
CET Contractual Engineering Task
CO Contracting Officer
COR Contracting Officer Representative
CPARS Contractor Performance Assessment Reporting System
FAR Federal Acquisition Regulation
FC/FD Functional Commander/Functional Director
IAW In Accordance With
IMSC Installation Mission Support Center
PAR Performance Assessment Report
PM Program Manager
POC Point of Contact
PWS Performance Work Statement
QAPC Quality Assurance Program Coordinator
QASP Quality Assurance Surveillance Plan
QC/QA Quality Control/Quality Assurance
SS Services Summary
TOI Task Order Initiator
1. Background, Vision, and Mission
The overall purpose of this contract is to augment Inside Plant/Outside Plant (ISP/OSP) services at 341st Communications Squadron (CS) to perform communications infrastructure support.
These requirements are directly attributable to the surge in workload at the Malmstrom AFB and the missile complex. This document explains the contractor’s specific role in this mission, and how the contractor can ensure success in their role.
2. QASP Purpose
This Quality Assurance Surveillance Plan (QASP) is a government-developed document used to determine if the contractor’s performance meets the performance standards contained in the contract. The QASP establishes procedures on how this assessment/inspection process will be conducted. It provides the detailed process for a continuous oversight process:
• What will be monitored
• How monitoring will take place
• Who will conduct the monitoring
• How monitoring efforts and results will be documented
The contractor is responsible for implementing and delivering performance that meets contract standards using its Quality Control Plan. The QSAP helps the government monitor the contractor’s performance to ensure that it meets the contract standards. It is the government’s responsibility to be objective, fair and consistent in evaluating contractor performance.
The QASP is not part of the contract nor is it intended to duplicate the contractor’s quality control plan. This QASP is meant to be updated as needed. Flexibility in QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance. QASP can be updated or modified at the Government’s discretion without a formal contract modification.
The government may provide a copy of the QASP to the contractor to support open communication. In addition, the QASP should recognize that unforeseen or uncontrollable circumstances might occur that are outside the control of the contractor.
The main goal of the QASP should ensure early identification and resolution of performance issues to minimize impact on mission performance.
3. Authority
Authority for issuance of this QASP is provided under Part 46 of the Federal Acquisition
Regulation (FAR), Inspection of Services clauses, which provide for inspection, acceptance and documentation of the service required by the contract or order. This acceptance is to be executed by the contracting officer or a duly authorized representative.
4. Roles and Responsibilities
The following personnel shall oversee and coordinate surveillance activities:
Government Personnel
Contracting Officer (CO)
Holds the ultimate, legally binding authority to administer the contract, accept or reject deliverables, and make final performance determinations. Only the CO can make commitments or changes affecting contract price, quality, quantity, or delivery.
The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine the final assessment of the contractor’s performance.
Assigned CO: CHARLES MCCLINTIC
Organization or Agency: 341 CONS
Telephone: 406-731-4463
Email: charles.mcclintic@us.af.mil
Contracting Officer’s Representative (COR)
COR is a delegated technical administration authority by the CO. The COR manages day-to-day surveillance, documents nonconformances, and implements the QASP methodology
The COR is responsible for providing continuous technical oversight of the contractor’s performance. The COR will use the QASP to conduct the oversight/surveillance process. The
COR shall keep a Quality Assurance file to accurately documents the contractor’s actual performance. The purpose is to help ensure the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the CO. Each year, the COR is required to give the CO a performance assessment, which is used to document past performance. The QASP is the primary tool for tracking contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government’s behalf.
Assigned COR: Mr. ED STUART
Organization or Agency: 341 CS
Telephone: 406-731-6010
Email: Edward.stuart@us.af.mil
Contracting Officer’s Representatives Supervisor
Nominates CORs in writing and sends nomination and COR nominee qualification documentation to the CO, ensures the COR has sufficient time resources to perform contract surveillance alongside their primary duties, and is trained before performing any COR duties and supports the COR’s performance assessment activities, reviews COR documentation on a regular basis, evaluates performance of COR duties as part of performance assessment throughout the period of the contract. The COR Supervisor must initiate nomination in the Joint Appointment
Module (JAM).
mailto:charles.mcclintic@us.af.mil mailto:Edward.stuart@us.af.mil
COR Supervisor: Mr. Terry Woodard
Organization or Agency: 341 CS
Telephone: 406-731-6800
Email: terry.woodard.2@us.af.mil
Quality Assurance Program Coordinator (QAPC)
QAPC assists in matters involving the Quality Assurance Program and assists the Contracting
Officer in training the Contracting Officers Representative.
Assigned QAPC: Ms. EDSA L. ARTATES
Organization or Agency: 341 CONS
Telephone: 406-731-3625
Email: edsa.artates.2@us.af.mil
5. Performance Requirements and Method of Surveillance
Contract Surveillance
The goal of the QASP is to ensure that contractor performance is effectively monitored and documented. The COR contributes through professional, non-adversarial relationships with the
CO, PM, and the contractor, which enables positive, open and timely communications. The foundation of this relationship is built upon objective, fair, and consistent COR evaluations of contractor performance against contract requirements. The COR uses the methods contained in this QASP to ensure the contractor’s compliance with contract requirements. The COR function is responsible for a wide range of surveillance requirements that effectively measure and evaluate the contractor’s performance. Additionally, this QASP is based on the premise that the contractor, not the government, is responsible for managing and checking Quality
Control/Quality Assurance (QC/QA) actions to successfully meet the contract terms.
Multi-functional Team Meetings – will manage the contract throughout the life of the contract.
This team will create a partnership between the government and the contractor to ensure the best possible service is provided throughout the contract’s life. All performance assessment data will be looked at during these meetings. If performance improvement is necessary, a plan of action will be created.
Surveillance Matrix
The Surveillance Matrix (Attachment 1) list the performance objectives and standards the contractor must meet. This matrix details the surveillance method the COR will use to validate and inspect these performance elements. Each inspection will be documented in the COR file.
Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed to measure performance.
The Government uses this QASP to perform surveillance, to determine the quality of the contractor’s performance against the performance element standards. The Services Summary should be used to form the foundation of the COR’s inspection checklist.
mailto:
mailto:edsa.artates.2@us.af.mil
Performance Rating Definitions
In evaluating the quality of contractor’s performance, the following performance ratings may be used.
Performance Rating Criteria
Excellent / Outstanding Performance meets contractual requirements and exceeds many to the government’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and contractor actions were highly effective.
Very Good Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were effective.
Good Performance meets contractual requirements. The contractual performance contains some minor problems for which corrective actions taken by the contractor were satisfactory.
Marginal Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear marginally effective or were not fully implemented.
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
Performance Reporting
Remedies for Non-Conformance
If inspections indicate unacceptable performance, the COR will notify the contractor’s POC of the deficiencies for correction. Use the remedy the government is going to use per what is stated in the Services Summary (SS). If deficiencies are not corrected within the required time frame, the COR should notify the CO for action. If the contractor disagrees with the noted discrepancy and an agreement cannot be reached, the CO shall be notified for a final decision
Performance Assessment Report (PAR)
PARs will be used to report ALL minor discrepancies and will be generated by the COR and sent to the contractor for corrective action. Contractors will be given 10 days to correct PARs unless they have requested an extension. If 3 minor discrepancies are found, combine them and process a CAR.
Customer Complaint Form
The COR must furnish instructions to the customer receiving the contractor’s service. The customer must retain supporting evidence of complaint or feedback. After the COR validates feedback or complaint demonstrating contractor noncompliance, the COR processes a
Performance Assessment Report (PAR) or Corrective Action Report (CAR) to the CO. ALL
Customer Complaint forms WILL be validated by the COR prior to notifying the contractor.
Corrective Action Report (CAR)
The CAR will be forwarded to the Chief COR for review. The COR will forward the CAR to the
CO for action. A copy will be provided to the contractor’s representative by the CO. Most CARs will be corrected within 30 calendar days depending on the complexity of the finding, the contractor may be allowed for up to six months (maximum) correcting a CAR. The contractor will be asked for the status of the CAR on a monthly basis. The COR will keep an electronic log of all CARs and will keep a hard copy of CARs in the contract oversight file.
Contract Performance Assessment Reporting System (CPARS)
CPARS will be initiated annually, documenting contractor performance for this specific contract.
More frequent updates may be made as required to document a significant improvement or degradation of the level of contract performance.
Disputes
Every attempt will be made to resolve all disputes arising under this contract/plan using the
Alternate Dispute Resolution (ADR) as outlined in FAR 33.214. If no resolution can be made under ADR, the CO will make a Contracting Officer’s final decision.
Appendix 1 - Surveillance Matrix (SERVICE SUMMARY)
Inspection & CET
Paragraph
Performance
Objective /
Elements Standards / AQL
Inspection Calculation /
Ratings (see above) What How/ Method* When/ Freq
SS# 1
2.1-2.5
Excellent
Customer Service
Contractor shall provide excellent customer service to
(at minimum): base engineering offices, and Malmstrom
Leadership meet contract/TO requirements with little rework and open lines of communication.
Customer satisfied with overall performance
COR will ensure that lines of communication are open and that customers are satisfied with performance
COR will conduct random interviews with customers, both regular and as identified by the contractor, to check status of communication and satisfaction
Interviews will be random, based on monthly reports, COR will give feedback monthly or as needed
Unsatisfactory rating = customers find contractors unresponsive, or if areas of customer service dissatisfaction remain unresolved for a full month
SS# 2
Project Schedule
Management
Provided accurate schedule proposals and schedule performance data.
Timely notifications of schedule over/under-runs and pursued schedule containment.
Contractor shall provide accurate schedule proposals and schedule performance data.
Timely notifications of schedule over/under-runs and pursued schedule containment.
COR will ensure that project designs and construction management is accurate and timely
COR will randomly check status of project designs to check accuracy, communication, and compliance to building codes.
Checks will be random, based on monthly reports
Unsatisfactory rating = proposals by contractor are consistently outside acceptable standards (60%
<< 125%)
Inspection & CET
Paragraph
Performance
Objective /
Elements Standards / AQL
Inspection Calculation /
Ratings (see above) What How/ Method* When/ Freq
SS# 3
Quality provide quality technical products/ deliverables:
complete, accurate, clear, and in conformance with requirements
Contractor shall provide quality technical products;
problems identified/ resolved prior to adverse impact;
subcontractors managed effectively
COR will ensure that technical products and deliverables are of high quality.
COR will conduct random interviews with customers/ recipients of technical products to check quality
Interviews will be random, based on monthly reports. COR will give feedback monthly or as needed
Unsatisfactory rating = customers find quality 15% unacceptable, or
5% unacceptable and unresolved
SS# 4
Schedule meet major and minor milestones/ deadlines, and coordinate schedule updates to the government
Contractor shall accurately project/ forecast schedules throughout the life of projects, meet all milestones, and communicate changes
COR will ensure that milestones are being set, milestones are being met, and that problems/ changes are being communicated
COR will conduct random interviews with customers/ owners of milestones/ deadlines to check status of completion and communication
Interviews will be random, based on monthly reports. COR will give feedback monthly or as needed
Unsatisfactory rating = failure to meet milestones
15% of the time, or failure to meet milestones 5% of the time without communication in advance
*Inspection Methodologies:
M1: Periodic. Periodic surveillance/inspection is the type of surveillance that is based upon selecting samples for evaluation on other than 100% inspection or on a statistically random basis. Periodic surveillance can be accomplished, weekly, monthly or quarterly using a checklist method.
M2: Inspection of Reports. All reports shall be reviewed upon receipt. The reviewer will report any flaws in the document and categorize the flaws (Editorial, Format, and/or Substance).
M3: Technical Inspection: Surveillance/inspection is the type of surveillance that will be performed as specified on the project schedule by actually looking at the work being done.
M4: Non-Service Summary. Assessment of Non-SS Items: All other tasks required under the CET may be inspected on a random basis at a frequency determined by the Functional Commander/Functional Director (FC/FD), CO, and/or COR per the Inspection of
Services Clause in the contract. Non-SS Items will be verified by the COR at least quarterly or on an event basis as required.
CORRECTIVE ACTION REPORT (CAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACTOR
2. CONTRACT NUMBER
3. TYPE OF SERVICES
4. FUNCTIONAL AREA
5. SUSPENSE
DATE
6. CONTROL
NUMBER
7. DEFICIENCY MAJOR MINOR
FINDING:
FINDING IMPACT:
Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the deficiency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.
8. QUALITY ASSURANCE PERSONNEL (COR)
TYPED NAME AND GRADE
SIGNATURE AND DATE
9. ISSUING AUTHORITY
TYPED NAME AND GRADE
SIGNATURE AND DATE
10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT
RECURRENCE
11. COR DETERMINATION
ACCEPTED REJECTED
12. CLOSE DATE
CUSTOMER COMPLAINT RECORD
DATE/TIME OF
COMPLAINT
SOURCE OF COMPLAINT
ORGANIZATION
BUILDING
INDIVIDUAL
PHONE
NATURE OF COMPLAINT
CONTRACT REFERENCE
VALIDATION
DATE/TIME CONTRACTOR INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR
RECEIVED/VALIDATED BY
PERFORMANCE ASSESSMENT REPORT (PAR)
(If more space is needed, use reverse and identify by number)
1. CONTRACT/TASK
ORDER NUMBER
2. CONTRACTOR 3. TYPE OF SERVICES
4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE
AND DATE
5. COR PHONE 6. SUSPENSE
DATE
I. PERFORMANCE
7. DEFICIENCY (CHECK ALL
BOXES THAT APPLY)
NEW
REPEAT
NO DEFICIENCY NOTED
8. SERVICES SUMMARY or CET PARAGRAPH
ITEM REVIEWED
9. BRIEF DESCRIPTION OF DEFICIENCY (IF
DEFICIENCY BOX WAS CHECKED)
10. DETAILED PERFORMANCE ASSESSMENT
II. CONTRACTOR VALIDATION
11. CONTRACTOR REPRESENTATIVE
CONCUR NON-CONCUR
12. CORRECTIVE ACTION ESTIMATED
COMPLETION DATE
13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF
RECURRENCE OR REASON FOR NON-CONCURRENCE OF COR CITED DEFICIENCY
III. ACTION CORRECTED
14. CONCUR NON-CONCUR COR SIGNATURE AND DATE
15. COR REMARKS (REQUIRED)
6. CONTRACTOR REPRESENTATIVE REMARKS
| 2026-08-19T09:36:34-0600 | |
| STUART.EDWARD.J.1158764560 |
| 2026-08-19T15:01:09-0600 | |
| WOODARD.TERRY.WAYNE.1125461120 |
| 2026-08-20T08:52:31-0600 | |
| MCCLINTIC.CHARLES.JOSEPH.1156317647 |
| 2026-08-18T12:06:16-0600 | |
| ARTATES.EDSA.LAPINA.1284130320 |
File details come from the government source that posted it. Updated .