Questions_Set_3.docx

DOCX document 17 KB Posted

Attached to
Repair Launch Facility Security Lighting Federal contract opportunity
Solicitation number
FA4626-15-R-0024
Issued by
Department of the Air Force Global Strike Command

About this file

Questions set 3.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Launch Facility Security Lighting, newest first.
File Type Posted
Amendment_5.pdf PDF
Updated_Drawings_(Amendment_5).pdf PDF
Updated_Specs__(amendment_5).pdf PDF
Amendment_4.pdf PDF
Amendment_notice.docx DOCX document
Notice_Regarding_Pre-proposal_confrence.docx DOCX document
Questions_Set_2.docx DOCX document
Amendment_3.pdf PDF
Updated_Drawings_(Amendment_3).pdf PDF
Updated_Specs_(Amendment_3).pdf PDF
Questions_set_1.docx DOCX document
updated_Specs_for_amendment_2.pdf PDF
Amendment_2.pdf PDF
Amendment_1.pdf PDF
updated_Drawings_(Amendment_1).pdf PDF
Solicitation.pdf PDF
Attach_3_SCHEDULE_OF_DRAWINGS.doc DOC document
Attach_6_Base_Entry_Policy_letter.pdf PDF
Attach_2_Submittal_Schedule.xlsx XLSX spreadsheet
Attach_1_Specs.pdf PDF
Attach_4_All_Drawings.pdf PDF
Attach_5_Wage_Determinations.docx DOCX document
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4626-15-R-0024 Questions

1. Can we to make the ditches wider than 8” for compaction, is that okay?

Answer: Yes, maximum width of trench has been changed to 16 inches.

1. Which silos have rip rap?

Answer: Approximately half the sites have rip rap with a total of 5000 linear feet of trenching which will go through the rip rap for the entire project.

1. What “i” silo do to we start with for estimation of mobilization?

Answer: This contract is following the work of another contractor. The contractor replacing the power panels has completed the sites in Charlie (with the exception of C-02 and C-03), Golf, Julie, and India Flights. The sites in Oscar Flight will probably be done by the time this contract is ready for construction. These sites may be worked in any order.

1. Identify how many of the silos are north entrance, east entrance, south entrance, and west entrance. The entrances make up different measurements?

Answer: There are 6 North, 11 East, 22 South, and 11 West

1. If we are using stand off brackets on the pole per drawing. Is there a set distance off the pole we need to be?

Answer: If the question is about Detail 2 on page 7 of the drawings, the pole arm for the lights needs to be 15 inches.

1. The brackets for the heaters that need to be built do not call to be painted. What color and how many coats?

Answer: The parts will require 1 coat of metal grade primer paint and 2 coats of metal grade paint, federal standard color #37056, or similar color.

1. Where do we deliver the spare parts?

Answer: Spare parts will be delivered to 341st CES on Malmstrom AFB. Contractor needs to coordinate delivery with the Government prior to delivery.

Clarification: on the light bulb warranty and what is expected from the contractor.

Answer: The light bulbs require a 1 year warranty.

Clarification of the underground marker tape. It IS 3 in. not 6 in. correct?

(The original question was answered and stated that it would be clarified in the new drawing but the drawing still showed 6 in.)

Answer: 3"

Will the conduit depth be set below ground elevation or rip rap elevation?

Answer: conduit depth is determine from ground elevation, not the rip rap elevation.

Also could the conduit installation be installed by means of horizontal directional drilling?

Answer: Yes, horizontal directional drilling is an acceptable method for this project.