Questions_set_1.docx

DOCX document 15 KB Posted

Attached to
Repair Launch Facility Security Lighting Federal contract opportunity
Solicitation number
FA4626-15-R-0024
Issued by
Department of the Air Force Global Strike Command

View the file

Other files for this federal contract opportunity

Other files attached to Repair Launch Facility Security Lighting, newest first.
File Type Posted
Updated_Drawings_(Amendment_5).pdf PDF
Updated_Specs__(amendment_5).pdf PDF
Amendment_5.pdf PDF
Questions_Set_3.docx DOCX document
Amendment_4.pdf PDF
Amendment_notice.docx DOCX document
Notice_Regarding_Pre-proposal_confrence.docx DOCX document
Questions_Set_2.docx DOCX document
Amendment_3.pdf PDF
Updated_Specs_(Amendment_3).pdf PDF
Updated_Drawings_(Amendment_3).pdf PDF
updated_Specs_for_amendment_2.pdf PDF
Amendment_2.pdf PDF
Amendment_1.pdf PDF
updated_Drawings_(Amendment_1).pdf PDF
Attach_2_Submittal_Schedule.xlsx XLSX spreadsheet
Attach_1_Specs.pdf PDF
Attach_4_All_Drawings.pdf PDF
Attach_5_Wage_Determinations.docx DOCX document
Solicitation.pdf PDF
Attach_3_SCHEDULE_OF_DRAWINGS.doc DOC document
Attach_6_Base_Entry_Policy_letter.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4626-15-R-0024 Questions. 1st set

1. WHAT ARE THE SITES?

The exact sites will be determined at a latter date but do encompass the entire missile complex. It won’t necessairly be an entire squadron at once. This is subject to change.

1. WILL WE BE ALLOWED TO WORK ON MORE THAN ONE SITE AT A TIME?

Work on mulitple sites can be done on an as needed basis. We prefer not to have several sites open at one time, but do realize that things come up from time to time in the missile field (i.e code change) that may require this to be the case.

1. CAN ON-SITE SUPERVISOR BE ONE OF THE WORKERS ON THE PROJECT?

An on-site supervisor is in charge of his personnel, responsible for onsite safety operations, and responsible for the contractors quality assurance on the project. It would be up to the contractor to decide if a worker meets the qualifications of an on-site supervisor. Key word being responsible.

1. THIS PROJECT MAY COVER TWO YEARS. SOME MATERIAL FOR WHOLE PROJECT MAY HAVE TO BE PURCHASED AT THE BEGINNING. CAN WE BE PAID FOR STORED MATERIAL?

While material storage is not a line item for this project, we will allow payment for materials purchased provied that the contractor can prove via site visit to the storage facility that the materials have been purchased and are being stored in a secure location.

1. GENERAL NOTE A ON SHEET E2.0 SAYS THAT THE GOVERNMENT HAS SELECTIVE

SALVAGE, AND WE ARE TO DELIVER TO LOCATION DESIGNATED BY 341ST CES/CEM. IT IS A LOT OF WORK TO DELIVER THE POLES IF SALVAGED. WE NEED TO KNOW IF THEY ARE GOVERNMENT SALVAGE AND WHAT LOCATION THEY MUST BE DELIVERED TO?

The Government would like to salvage up to 10 poles if they are in good/usable condition, the on-site inspector would need to determine what or if any are usable. Our Engineer feels most or all the poles are dry rotted. Also included in Government salvage would be 10 sets of any of the lighting hardware. Hardware can be turned over to the on-site Contracting Officer Representative and they will deliver to Zone. The poles, if kept, would require delivery to 341 CES electric shop with coordination do be done though the COR.