Amendment 0003 Questions and Answers
1. Is there a preference for Metal siding profile or brand?
Metal siding to be Delta-Rib, or approved equal. Installation of the siding shall include all J-channel/trim/transition/finish pieces at all doors, windows, soffits, installed IAW building and industry standards and per manufacturers’ instructions. Industry standard seal at the bottom edge of the siding shall also be installed.