21R1001 SV Minutes and Sign in.pdf

PDF 329 KB Posted

Attached to
Whiteman Building Demolition (S6)
Solicitation number
FA462521R1001
Issued by

About this file

This memorandum and solicitation document provide details for the Building S-6 Demolition project at Whiteman Air Force Base. The memorandum describes a site visit held on November 2nd 2020 between the 509th Civil Engineering Squadron, 509th Contracting Squadron, and prospective contractors. Attendees were able to inspect and measure the building to be demolished. Questions are due by November 5th and will be responded to on November 9th. Proposals must be submitted by November 16th.

The solicitation seeks proposals to demolish Building S-6 at Whiteman Air Force Base. The North American Industry Classification System code for this acquisition is 562910 for remediation services. This is a 100% small business set-aside with a size standard of $22 million. Offerors should refer to the attached COMBO document for additional requirement details.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

509TH CONTRACTING SQUADRON (AFGSC)

WHITEMAN AIR FORCE BASE, MISSOURI

You Fly The Skies…CONS Makes The Buys!

2 November 2020

MEMORANDUM FOR

FROM: 509 CONS/LGCA

660 Tenth St, Ste 222 Whiteman AFB, MO 65305

SUBJECT: FA462521R1001, Building S-6 Demolition

1. This meeting was held jointly by the 509th Civil Engineering Squadron (509 CES) and the 509th Contracting Squadron (509 CONS) and began at approximately 1300.

2. The sign-in sheet for the site visit has been scanned and is attached.

3. SSgt Hopkin and MSgt Seay (CONS), along with Mr. Virgil and Mr. Sewell (CES), met with prospective contractors for the Building S-6 demolition requirement. Attendees were able to visually inspect the interior and exterior of the building to be demolished, take measurements, and analyze the type and amount of materials used in construction of S-6.

4. Questions are due in via electronic correspondence by November 5th and subsequently will be sent to 509th CES for responses, which will be added to beta.sam.gov on November 9th.

Proposals are scheduled to be sent no later than November 16th. Dates are scheduled dates and are subject to change.

5. The meeting concluded at approximately 1400.

RYAN F. HOPKIN, SSgt, USAF Contract Administrator