Atch 6 Questions and Answers Rev 2 - 17 Sep 2027.pdf

PDF 695 KB Posted

Attached to
PKAB Stockpile Removal at FE Warren AFB, Wyoming AMENDMENT 02
Solicitation number
FA461326Q0020
Issued by

About this file

This is a Questions and Answers document (Revision 2, dated 17 September 2026) for federal contract FA461326Q0020 regarding stockpile removal services. The document clarifies contract requirements and material specifications for the disposal of concrete and asphalt debris from four stockpiles.

The contractor is responsible for loading all stockpile material into haul trucks and transporting it for disposal, with a maximum contractual obligation of 50 loads (approximately 700 cubic yards total) using 15-ton dump trucks with 12-14 cubic yard capacity per load. Pile 1 contains approximately 2,500 cubic yards of concrete broken into manageable pieces; Piles 2 and 3 combined contain approximately 4,000 cubic yards of asphalt with mixed large, medium, and milled pieces; and Pile 4 contains mixed concrete and asphalt material without a specified cubic yard estimate. The government has pre-screened Pile 1 for metal debris and rebar, though contractors must remove and dispose of any additional foreign materials identified during loading operations. Payment is limited to 50 loads, with contractors providing weight delivery tickets as proof of each load; any loads exceeding 50 are the contractor's responsibility. Clean concrete and asphalt may be delivered to permitted aggregate recycling facilities for final disposition, provided the contractor complies with applicable local, state, and federal environmental laws and submits certified scale receipts documenting load compliance.

View the file

Other files

File Type Posted
Atch 1 PWS Rev 2 17 Sept 2027.pdf PDF
Amendment 02.pdf PDF
Conformed Copy.pdf PDF
Atch 6 Q and A Rev 2 17 Sept 2027.pdf PDF
Amendment 01.pdf PDF
Atch 1 PWS Rev1 15 Sep 2026.pdf PDF
Atch 6 Questions and Answers.pdf PDF
Conformed Copy.pdf PDF
Amendment 01.pdf PDF
Atch 5 Site Visit Sign In Sheet.pdf PDF
Atch 7 Stockpile Photos.pdf PDF
Solicitation - FA461326Q0020.pdf PDF
Atch 2 Environmental Specs.pdf PDF
Atch 4 SCA 2015-5405 27 Aug 2026.pdf PDF
Atch 3 Contractor Safety Guide.pdf PDF
Atch 1 PWS 24 Aug 2026.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA461326Q0020 Stockpile Removal

Questions and Answers REV 2, 17 Sep 2026

1. Material Segregation & Sizing: Are the concrete and asphalt stockpiled separately in clean individual piles, or are the materials co-mingled within the stockpile? Additionally, is the debris already broken up into manageable pieces?

Govt Response: The one major concrete pile is broken down into manageable pieces that can be loaded with a bucket loader and hauled/transported. The second and third pile consists of asphalt that is a blend of large, medium pieces and millings that have compacted naturally over time. The fourth pile is mostly concrete with some asphalt material. This pile would need to be broken down and filtered. See Attachment 7 for Stockpile Photos.

2. Foreign Materials / Rebar: Does the concrete debris contain embedded rebar, wire mesh, or other structural steel/foreign contaminants?

Govt Response: We have thoroughly gone through pile one and broken down the concrete and removed metal debris. In the event, debris is identified during loading, the Contractor shall remove this small percentage of concrete/metal debris and set aside to be broken up later time. It will still be the contractor’s responsibility to dispose of these metal debris, however, they see fit. The Government shall pay to dispose up to 50 loads (each about 12-14 cubic yards on a 15-ton dump truck) for a total of about 700 cubic yards. Contractor shall have weight delivery tickets provided to make sure minimum load per dump truck is met. Anything exceeding 50 loads shall not be the responsibility of the contractor.

3. Site Photos & Footprint: Due to unavailability for site visit, can the Government provide representative site photos (wide-angle showing footprint/yard access, plus close-ups of material composition) along with approximate pile dimensions?

Govt Response: Pile 1 – approx. 2500 cu yds Pile 2 & Pile 3 combined – approx. 4,000 cu yds Pile 4 – no numbers or pictures. It is mixed material and we will hit our 700 cubic yard cap easily. Photos available but no estimate of cu yards. Total cubic yards for all four stockpile is about 8,000. However, the Government, under this solicitation, is only requesting up to 50 loads of 12-14 cubic yards each (on a 15-ton dump truck) which brings to about 700 cu yards. Anything in excess of 50 loads shall not be the responsibility of the contractor.

4. Loading Operations: Who is responsible for loading the concrete and asphalt material into the haul trucks at the site—the contractor or Government/base personnel?

Govt Response: The Contractor is responsible for loading all stockpile into haul trucks and disposal thereafter, up to 50 loads of 12-14 cu yards on a 15-ton dump truck.

5. Governing Quantity Basis: CLIN 0001 identifies 130 loads, an estimated 1,300 cubic yards, and a maximum of 1,600 tons. If these three metrics produce differing totals during execution, which metric strictly governs payment and contract completion?

Govt Response: The Contractor shall have weight tickets to provide proof of each load. The contractor should provide the cubic yard capacity of the haul vehicle(s) to help determine when we get to the estimated 700 cu yards for a 15-ton dump track capable to hold 12-14 cu yards of stockpile. A maximum of 50 loads is set under this service. Anything in excess is not the responsibility of the Contractor.

6. Payable Load Specification: The solicitation states that each load must meet the expected weight of a truckload. What specific truck configuration, minimum volume, or target net weight will the Government use to define an acceptable, payable load?

Govt Response: The contractor will use suitable hauling equipment within DOT guidelines and regulations. A payable load will consist of filling the haul truck/trailer to the cu yard capacity of that given asset. It is anticipated that a 15-ton dump truck capable of hauling 12-14 cu yards of debris per load, can meet a 50 load or up to an estimated 700 cu yards of debris.

7. Recycling & Final Disposition: While the PWS cites legal disposal at an authorized off-base site, environmental specifications address RCRA Subtitle D diversion. May clean concrete and asphalt be delivered to a permitted aggregate recycling facility as its final disposition, provided certified scale receipts are furnished?

Govt Response: In accordance with 1.1.4. of the PWS, as long as the concrete is disposed of properly in accordance with local, state, and federal laws. Therefore, a recycling center that is permitted to recycle these materials under those mandates would qualify, as long as the contractor adheres to the weighing requirements and submits weight delivery tickets as proof of meeting the number of loads allowed under this requirement.