20260001A_SV Minutes_S.pdf
PDF 130 KB Posted
- Attached to
- XUMU 20260001A Bldg 15501 FOC Comm Install
- Solicitation number
- FA461026Q0040
About this file
This is a Memorandum for Record documenting a Site Validation Visit conducted by the United States Space Force, Space Launch Delta 30, for contract opportunity XUMU 20260001A FOC Comm Install Bldg 15501.
The site visit was held on August 4, 2026, at 9:30 AM PST to address contractor questions and provide clarification on project requirements. Key deadlines established for the solicitation are an RFI due date of August 7, 2026, at 1:30 PM PST and a proposal due date of August 20, 2026, at 3:00 PM PST. All contractors are required to submit questions through the Request for Information (RFI) process to clarify project requirements. Contractors were notified that access to Building 15501 is controlled due to the nature of the project. Framelights were discussed during the visit, and contractors are advised to submit RFIs for further clarification on this topic. The memorandum is signed by Shelby Cordts, Contract Specialist.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
UNITED STATES SPACE FORCE
SPACE LAUNCH DELTA 30
MEMORANDUM FOR RECORD
SUBJECT: Site Visit Minutes; XUMU 20260001A FOC Comm Install Bldg 15501
1. On 04 August 2026, a Site Validation Visit was conducted at 9:30 AM PST.
a. During the Site Validation Visit, the following items were discussed:
i) It was restated per the solicitation that the RFI due date is 07 August 2026 at
1:30pm (PST) and the proposal due date is 20 August 2026 at 3:00pm (PST).
ii) It was requested that all questions to be submitted as an Request for Information
(RFI), in order to clarify project requirements.
iii) Contractors were made aware access to building 15501 is controlled.
iv) Due to the nature of the project, Framelights were discussed. Contractors were advised to submit RFI’s for further clarification.
Shelby Cordts Contract Specialist