This file is a Questions and Answers document addressing contractor inquiries regarding the South Lot 3 parking lot construction project at Offutt Air Force Base, Nebraska (Solicitation FA460026B0004).
The Q&A clarifies several key project requirements and specifications. The original bid due date of September 7, 2026 (Labor Day) was extended to September 8, 2026 at 2:00 PM local time, with public bid opening on September 9, 2026. Regarding overhead utility work, the contractor must coordinate with Omaha Public Power District (OPPD) for pole removal, relocation, and bracing; an updated OPPD point of contact will be provided to the awardee. For asphalt paving specifications, contractors must follow the drawings calling for a 6-inch asphalt pavement base course, though alternative materials with cost justification may be proposed. The document addresses electrical specifications, including clarifications on pole base sizing (4 inches and 24 inches as detailed on drawing detail #2), OPPD pedestal location, and existing as-built documentation. The project has a 200 calendar day period of performance with no winter exclusion; excusable delays are governed by FAR 52.249-14. Regarding construction standards, contractors must adhere to specifications for stringline/laser/GPS requirements, tack test strips, prime coat application, asphalt test strips, profilograph testing, diamond grinding, straight edge testing, grade shots, and longitudinal/transverse joint cutting. The document also clarifies drainage work scope, including removal of a rain garden subdrain pipe within project limits and modification of an existing inlet to a manhole per the drainage plan on Sheet C2.9.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question | Answer | |||
| The bid due date is currently set for September 7th, which is Labor Day. With this being a federal holiday would the due date be able to be extended to a later date? | We will extend the due date to 8 Sept at 2:00PM local time. Public opening will be 9 Sept. Please watch SAM.gov for updates and links | |||
| The specifications call out that all overhead utility pole removal, relocation, and/or bracing shall be accomplished by OPPD. The POC that is provided is David Ortiz at 402-636-3396, this number seems to be discontinued. Is there an updated POC for OPPD we can reach out to coordinate electrical work? | The awardee will be provided with an updated POC for OPPD. CE can assist with coordinating POCs. | |||
| Could you please clarify what the base course is to be underneath the 3” asphalt paving surface course. The detail ‘Typical Asphalt Section’ on drawing C3.1 has a text call out of ‘6.0” Asphalt Pavement Base Course’. Does the government want the 6” basecourse layer to be Asphalt Pavement, or normal basecourse material, we have used 1.5” crusher run in the past as our basecourse material. | Follow what is on the drawings, if there is a better option, provide cost and explaination of the new option | |||
| Page ED1.01 electrical demo, note #1 turn over to OPPD for storage. Do we leave them at the edge of the lot for them to pick up. | Contact OPPD to coordinate the details on the removal, relocation, and storage of the light poles | |||
| Page E1.01 site electrical, note #1 need clarification on base size a 4” base for a 28’ pole seems a little suspect, even the detail -2/E1.01 says 4” Base, in the drawing it says 24”, please clarify. | Refer to drawing detail #2 for clarification of notes. 4" and 24" are explained | |||
| Page E1.01 site electrical, note #2 can the location of the OPPD pedestal be provided? | See Flag Note #2 in the bottom left of the drawing | |||
| Are there any existing as-builts for the existing Light Pole circuiting? | See attachment | |||
| Will this Contract include Winter Exclusion and/or Weather Delays taken into consideration due to conditions needed to obtain and lay asphalt. | The PoP is 200 calendar days. Winter exclusion is not included in this SOW. FAR 52.249-14 details excusable delays. | |||
| Can this project be done under Superpave Specs and if so: a. | What are the design specs b. | What are the testing specs – you would be looking for | Follow the specifications given | |
| Do you want all lifts Gradation #1 or #2 or can we pick which gradation we want to use based off the lift? | Yes | |||
| Specs call for Stringline / laser / GPS requirement – since this is a parking lot do those need to be used | Specs call for it | |||
| Will the project require tack test strip as outlined in the specs – since this is a parking lot | As outlined in the specs | |||
| Does this project require profilograph testing | Refer to the specs | |||
| Does this project require diamond grinding | Refer to the specs | |||
| Will this project require straight edge testing | Refer to the specs | |||
| Will this project require Plan grade shots on the asphalt paving and since we have curb to meet | Refer to the specs | |||
| Will this project require an asphalt test strip as outlined in the | Refer to the specs | |||
| Does this project require Prime Coat – past projects not required If required will the test strip for the Prime Coat be required as outlined in the specs – since it is a parking lot | Refer to the specs | |||
| What are the specs on longitudinal and transverse joint cutting | ||||
| a. | Do all joints require | |||
| b. | Do only joints that fall below 175 degrees require cutting | |||
| c. | Is how we cut them up to us ( i.e. saw, mill, pizza cutter, etc. ) | Refer to the specs | ||
| SHEET 15 C1.3 ENLARGED SITE PLAN AREA A – ALTERNATE | noted | |||
| Key note number 7 is listed twice, and note number 8 is not listed. On the site plan there is a keynote number 8 referencing an existing inlet. Please confirm that keynote 8 on the site plan is referencing the inlet to be modified.7. MANHOLE, SEE DRAINAGE PLAN ON SHEET C2.9 |
7. EXISTING INLET TO BE MODIFIED TO MANHOLE SEE SHEET C2.9
| SHEET 13 C2.1 REMOVAL PLAN – ALTERNATE | As drawings say, remove the pipe |
| KEYNOTE 9 – REMOVE RAIN GARDEN SUBDRAIN PIPE | |
| It is unclear on the drawings how much of this pipe is removed. The pipe appears to go outside the project limits, so we would like to get clarification on where that particular pipe is to be removed. |