This document is a combined synopsis and solicitation for office furniture for three facilities at Tyndall Air Force Base. The Air Force Civil Engineer Center Natural Disaster Recovery Division is seeking fixed-price proposals for furniture for the ABM Sim, Fire Station 2, and WEG Large Boat facilities. Required furniture includes systems, seating, executive, conference, appliances, and weight equipment. Offerors must be able to deliver and install the furniture by the estimated installation dates of April 18, 2022 for ABM Sim, September 6, 2022 for Fire Station 2, and October 7, 2022 for WEG Large Boat. Proposals are due by February 18, 2022 and must include itemized pricing, product specifications and dimensions, delivery and installation timeframes, and representations and certifications documentation. The NAICS code is 337214 for office furniture manufacturing and there is no set-aside designated. The agency will evaluate proposals based on technical acceptability, price reasonableness, and overall best value to the government.

View the file

Other files

File Type Posted
Q and A 20220328 signed.pdf PDF
Attachment 3 SOW Attachment 2 Fire Station 2 Specifications 16 Mar 2022.pdf PDF
Attachment 2 SOW Attachment 1 ABM Sim Specifications 16 Mar 2022.pdf PDF
Attachment 1 Statement of Work BOD22 16 Mar 22.pdf PDF
Attachment 4 SOW Attachment 3 WEG Specifications 16 Mar 2022.pdf PDF
Attachment 8 Pricing Breakdown.xlsx XLSX spreadsheet
Q and A 20220214 signed.pdf PDF
Attachment 2 SOW Attachment 1 ABM Sim Specifications 14 Feb 2022.pdf PDF
Attachment 1 Statement of Work BOD22 10 Feb 2022.pdf PDF
Attachment 1 Statement of Work BOD22 10 Feb 2022.pdf PDF
Attachment 7 CLINs Provisions and Clauses AMD 3.pdf PDF
Attachment 2 SOW Attachment 1 ABM Sim Specifications 10 Feb 2022.pdf PDF
Q and A 20220210 signed.pdf PDF
Attachment 4 SOW Attachment 3 WEG Specifications 10 Feb 2022.pdf PDF
Attachment 3 SOW Attachment 2 FS2 Specifications 10 Feb 2022.pdf PDF
Q and A 20220205 signed.pdf PDF
Attachment 7 CLINs Provisions and Clauses AMD 2.pdf PDF
Q and A 20220126 signed.pdf PDF
Attachment 7 CLINs Provisions and Clauses AMD 1.pdf PDF
Q and A 20220124 signed.pdf PDF
Attachment 3 SOW Attachment 2 Fire Station 2 Specifications.pdf PDF
Attachment 7 CLINs Provisions and Clauses.pdf PDF
Attachment 4 SOW Attachment 3 WEG Drone Boat Specifications.pdf PDF
Attachment 6 Reps and Certs.pdf PDF
Attachment 2 SOW Attachment 1 ABM SIM Specifications.pdf PDF
Attachment 1 Statement of Work BOD22 3 Jan 2022.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

NATURAL DISASTER RECOVERY DIVISION

TYNDALL AIR FORCE BASE, FLORIDA

18 Feb 2022

FROM: AIR FORCE CIVIL ENGINEER CENTER/NATURAL DISASTER RECOVERY

DIVISION

103 MISSISSIPPI AVE

TYNDALL AFB, FL 32403

SUBJECT: Response to Inquiries regarding FA4507-22- Q-0002

QUESTIONS

1. QUESTION: We normally see an Excel document that we add in our prices. Attachment 7 is a PDF and would be a “Lot” price. If you look at

Attachment 4 starting on Page 21, that is normally what we see. It’s a Live Excel doc that we enter into. Are those available for each building? Can they be uploaded to SAM.gov?

ANSWER: Excel document created, titled Attachment 8 Pricing Breakdown. Each

Tab lists the breakdown of the projects by line. Installation is added after the product lines. Then the total is the CLIN total showing up on the Summary Tab.

The Storage Tab is filled out as stated in the solicitation with 4,000 sq ft for 60 days for evaluation purposes. Please include your estimated sq ft in the column as listed.

This will not be used for evaluation purposes and will only be used if selected for award.

Overview of Amendments

Amendment 1:

-added FAR 52.225-1 to clauses selected in FAR 52.212-5

Amendment 2:

-CLIN 0001 installation date updated from 18 Apr 2022 to 1 Jun 2022

-Offer due date extended to 25 Feb 2022

Amendment 3:

- SOW and attachments updated and highlighted to reflect changes listed in Q and A 20220210

Amendment 4:

-Attachment 2 SOW Attachment 1 updated to reflect change listed in Q and A 20220214

Amendment 5:

-Attachment 8 Pricing Breakdown added to solicitation to provide live excel document of projects

Tiffany L. Hoover

Contracting Officer

2022-02-18T15:50:54-0600
HOOVER.TIFFANY.L.1513318045

File details come from the government source that posted it. Updated .